In short. Components that pass their own tests can still fail together. Integrated systems testing (IST) runs the whole power chain as one: the utility is removed, generators start, transfers happen, UPS units ride through, loads restart and the system recovers, with failures deliberately injected along the way. It is the evidence that the design works, the way to find interaction faults before a real outage does, and the baseline for every later test.
Who this page is for: For commissioning managers, consultants and critical-facility owners planning acceptance and periodic testing of power systems.
Key facts
- IST tests the whole chain together, not each item alone.
- Every test has a procedure, measurable acceptance criteria and a rollback plan.
- Inject failures: a set that fails to start, a UPS module lost, a breaker that does not close.
- Record voltage, frequency and transfer times with time-synchronised instruments.
- Use load banks where the real load is not available or not safe to risk.
- Repeat key scenarios after significant changes and at agreed intervals.
The testing ladder
| Stage | What is tested |
|---|---|
| Factory acceptance | Each item at the maker’s works |
| Installation checks | Wiring, torque, labels, settings |
| Pre-functional tests | Each device energised and operated alone |
| Functional tests | Subsystems, such as a generator with its ATS |
| Load-bank tests | Capacity, cooling and stability under load |
| Integrated systems test | The whole chain, with failures injected |
| Periodic tests | Key scenarios repeated through the system’s life |
Typical scenarios
- Utility loss with all systems normal.
- Utility loss with the first generator failing to start.
- Loss of one UPS or one power path.
- Generator trip under load, with load shedding.
- Retransfer to the utility.
- Black start from a dead bus.
- Loss of control power or the control network.
- A failure while equipment is in maintenance.
Worked example: one scenario with acceptance criteria (illustrative)
Scenario: utility removed at full load with generator 1 prevented from starting.
| Measure | Criterion agreed before the test | Recorded | Result |
|---|---|---|---|
| UPS on battery, no break to IT load | No interruption | No interruption | Pass |
| Generator 2 on the bus | Within 15 s of utility loss | 11 s | Pass |
| Generator 3 synchronised | Within 30 s of utility loss | 24 s | Pass |
| Deferrable load shed until capacity is restored | Shed within 1 s of transfer | 0.6 s | Pass |
| Chiller restart | Restarts automatically after generator 3 is on line | Did not restart; controller waited for an operator reset | Fail: setting changed, retested and passed |
Each item had passed its own commissioning; the chiller fault only appeared when the whole sequence ran. That is exactly what IST is for. See load bank testing.
Do not run an integrated test without written acceptance criteria, a rollback plan and people stationed at every key point. A test that injects real failures must be controlled so that it never becomes the outage it is meant to prevent.
Test plan content
- Purpose and scope of each test.
- Prerequisites and safety measures.
- Step-by-step procedure with expected results.
- Acceptance criteria with numbers.
- Instruments: recorders, power analysers, time synchronisation.
- Rollback plan and responsible people.
See the design review and acceptance framework and FAT and SAT.
Managing findings
Log every deviation with severity and owner, fix, retest and record the evidence. Do not hand over with an open critical finding.
IST scenario record
Six scenarios run on that same hospital block, where the example above runs one scenario in detail. Failures are injected rather than assumed. Every criterion is a number measured with time-synchronised instruments, because “it worked” is not a result that can be compared against the next test.
| Scenario | Criterion | Recorded | Pass or fail | Action |
|---|---|---|---|---|
| Mains fail, both sets start | Critical load never loses supply; essential restored inside 15 s | UPS carried 287 kW for 11.4 s; both sets on load at 11.4 s. Battery autonomy 10 min, so 2% used | Pass | — |
| Mains fail, set A fails to start | Essential restored inside 15 s on set B alone; shedding acts before set B overloads | Set B on load at 12.1 s. Shedding dropped 148 kW of non-essential at 12.4 s, leaving 434 kW against a 400 kW set for 9 s | Fail | Ward lighting cannot be shed separately — split that board and add it as shed stage 3. Retest |
| One UPS module removed under load | No transfer to bypass; output voltage within tolerance | Six remaining modules carried 287 kW; output held 230 V within 1% | Pass | — |
| Bus coupler breaker fails to close | Alarm inside 2 s; no loss of load | Alarm at 1.4 s; no load lost | Pass | — |
| Data room cooling loses its supply | Cooling restored before the IT temperature trip at about 4 min | Cooling is on the UPS-backed supply and was restored at 11.4 s with everything else | Pass | Confirms the reclassification in the load sheet was correct |
| Fuel transfer pump fails | Eight-hour run achievable on the day tank alone | 300 litre day tank at 434 kW gives about 2.6 h, not 8 | Fail | Second transfer pump on an independent supply. Owner: facilities |
Four passes and two failures, and neither failure would have been found by testing the equipment separately. Both sets start correctly. Set B carries load correctly. The shedding scheme operates correctly, at 12.4 s, exactly as configured. Every item passes its own test, and the system still leaves a 400 kW set carrying 434 kW for nine seconds — because the only load left to shed was one that shares a board with something that must not be shed.
That is what integrated testing is for. The arithmetic was available on paper all along: 582 kW total, 148 kW sheddable, 434 kW remaining, one 400 kW set. Nobody did the subtraction until a set was deliberately failed with the building on load.
The fuel row is the same kind of finding in a different system. The generators ran, the electrical chain performed, and the installation had 2.6 hours of autonomy against a requirement of eight because one pump stood between the bulk tank and the day tank. An electrical test plan that stops at the switchboard never asks the question.
What to record, and where, during an integrated test
An integrated test is only as useful as its records. A test watched on equipment displays tells you what happened in broad terms; a test recorded with synchronised instruments tells you exactly when each event happened, how deep each dip was and how long each recovery took, and can be compared line by line with the next test years later.
| Point | What to record | Why |
|---|---|---|
| Generator terminals or plant bus | Voltage and frequency at a fast sample rate, current on each phase | Load acceptance, recovery time, sharing between sets |
| UPS input and output | Voltage and current, UPS state changes from its event log | Walk-in behaviour and output stability through each transfer |
| Critical distribution boards | Voltage on each phase, with event capture for dips | What the load actually saw |
| Cooling plant | Supply and return temperatures, chiller and pump states | Whether cooling restarted and how long it was lost |
| Rooms with critical equipment | Air temperature at the equipment inlets | The thermal effect of any cooling interruption |
All instruments and all device event logs must agree on the time, so their clocks are set from one reference before the test and their offsets recorded. A test record in which the generator’s log and the UPS log disagree by thirty seconds cannot show which came first, and the question “which came first” is usually the one that matters.
Readiness before the first scenario
An integrated test deliberately causes failures on a live critical system, and its own preparation decides whether it finds weaknesses or creates an outage. A short readiness check, signed before the first scenario, sets the conditions under which the test may start and the conditions under which it stops.
| Before starting, confirm | Stop the test if |
|---|---|
| Every redundant element is in service and healthy | Any redundant element is lost and not restored within an agreed time |
| The business owners have agreed the window and know what may happen | The business owner asks for it to stop |
| Each scenario has a written recovery step, tested on paper | A scenario’s result is not understood before the next begins |
| People are at their stations with radios, and roles are clear | Communication with any station is lost |
| Fuel, spares and the service providers are on hand | Any safety concern is raised by anyone present |
The stop conditions are as important as the start conditions. A test that continues after an unexpected result, on the assumption that it will be understood later, can stack a second failure on top of an unexplained first one. Stop, restore, understand, and only then continue.
Using load banks so the test is realistic
A new facility often has little of its final load installed when it is tested, and an integrated test at a fraction of the design load proves little about behaviour at full load. Load banks fill the gap. Placed in the rooms where the real equipment will stand and fed from the real distribution, they load the UPS, generators and cabling to the design figure, and their heat loads the cooling to its design figure too, so that the test proves the cooling as well as the electrical system.
Resistive load banks alone test real power; adding reactive load banks brings the power factor close to that of the final load, which matters for generator voltage behaviour and for UPS and transformer loading. On an existing site, where the real load is running, load banks can top up the load towards design figures for the duration of the test. Either way, the heat from the banks must be planned for: a room loaded to its design heat with the cooling not yet proven is a room that may overheat during the very test meant to prove it.
Deciding what to re-test after a change
Every change to a critical system raises the question of how much must be tested again. Re-running the whole integrated test after every small change is impractical; re-testing nothing is how redundancy quietly disappears. A simple classification settles it.
| Change | Examples | Re-test |
|---|---|---|
| Like-for-like replacement | A battery block, a fan, a breaker of the same type and setting | The item’s own functional test |
| Setting or firmware change | A transfer delay, a protection setting, a controller update | Every scenario that uses that setting or controller |
| New or modified equipment | An added UPS module, a new generator, a new distribution board | Every scenario involving that path, at its new load |
| Change to the architecture | A new source, a changed changeover arrangement, a new tie | The full integrated test |
Record each change with its classification and the tests that followed it, in the same register as the original test results. Over the years the register becomes the evidence that the system tested at commissioning is still the system in service.
Common mistakes
- Testing components but never the whole chain.
- Criteria written after the test.
- No failure injection.
- Instruments not time-synchronised.
What to send us
Send the single-line diagram, the control description and the scenarios you need to prove. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. The scenario and results are illustrative; each project sets its own criteria.
Questions engineers ask
When should an integrated systems test be stopped?
When a redundant element is lost and not restored within the agreed time, when a scenario result is not understood before the next would begin, when communication with any station is lost, when the business owner asks, or when anyone raises a safety concern. Stopping, restoring and understanding the result before continuing prevents a second failure being stacked on an unexplained first one. Agree and sign these conditions before the first scenario.
What needs re-testing after a change to a critical power system?
It depends on the change. A like-for-like replacement needs its own functional test. A setting or firmware change needs every scenario that uses that setting or controller. New or modified equipment needs every scenario involving its path at the new load. A change to the architecture, such as a new source or changeover arrangement, needs the full integrated test. Record each change, its class and the tests that followed it in one register.
What is an integrated systems test?
A test of the whole power chain together, including sources, transfer, UPS, controls and recovery, to prove they work as one system. Mains failure is simulated, and the test follows the sequence from UPS bridging, through generator start and transfer, to retransfer and recovery, recording every timing and event.
How often should IST be repeated?
After significant changes and at intervals agreed with operations, balancing risk and the value of the evidence. Each repeat is planned with a written procedure, verified redundancy, rollback steps and the affected users informed, and its results are compared with the previous test, so that any drift in timing or behaviour is found and corrected early.
Is a load bank test enough?
It proves capacity and stability but not the full transfer and control sequence. A load bank shows the generator can carry its rated load and hold voltage and frequency, but it does not prove that the changeover, UPS, controls and real loads work together. Both tests are needed for a critical site.
Who should witness tests?
Representatives of the owner, operations, the designer and equipment suppliers. Each witness checks the parts they are responsible for, and the signed record lists every step, the expected and actual result and any fault found, so the test is accepted on evidence and the open items are tracked to closure.
This guide gives general principles. Test plans must be developed for the specific installation.