Gas Generator Systems

How gas generator sets work and where they fit: spark-ignited gas engines, fuel supply and gas train, load response, derating, heat recovery, safety, maintenance and comparison with diesel.

In short. A gas generator uses a spark-ignited engine on natural gas, biogas or a similar fuel. It suits sites with reliable gas, steady load and often a use for waste heat. Compared with diesel, it usually accepts smaller load steps, needs a safe gas train and detection, and depends on the gas supply. For critical standby, it is often paired with a diesel set or battery support.

Who this page is for: For owners and consultants considering gas generators for prime power, combined heat and power or backup.

Key facts

  • Spark ignition, not compression ignition.
  • Load steps are usually smaller than a diesel set can take.
  • Waste heat from exhaust and cooling water can often be used.
  • Gas train: filtering, regulation and safety shut-off.
  • Gas detection, ventilation and review of nearby electrical equipment.
  • Derating applies in heat and at altitude.

Gas and diesel compared

ItemGas setDiesel set
Fuel supplyPipeline, compressed gas or biogasTank on site
Load stepsUsually smaller; check the data sheetUsually larger
Heat recoveryOften worthwhilePossible
Standby useDepends on gas reliabilityCommon

Worked example: starting a 600 kW load (illustrative)

ItemGas setDiesel set
Set rating1250 kVA (1000 kW at 0.8 power factor)1250 kVA (1000 kW at 0.8 power factor)
Assumed first load step from the data sheetabout 20% of ratingabout 50% or more
Steps needed for 600 kW3 steps of about 200 kWabout 2 steps
Time between stepsuntil frequency and voltage recoveruntil frequency and voltage recover

The plant added a step sequencer for the gas set and kept a diesel set for loads that need power within seconds. See generator load steps and cleaner-fuel options.

Do not size a gas set as if it takes load steps like a diesel set. Use the gas set’s own data and plan the steps.

Heat recovery

A gas engine turns a share of its fuel energy into electricity and rejects much of the rest as heat in the exhaust and cooling water. Where the site needs steam, hot water or cooling, recovering that heat can make the gas set clearly worthwhile. Size the heat recovery to the site’s real heat demand.

Gas set sheet

ItemValue
Gas source and pressure 
Steady and peak load 
Largest load step 
Heat demand on site 

Reading the load-step data

A gas engine runs with a throttled mixture of gas and air, and its turbocharger must build boost before it can burn more fuel. A sudden load therefore drops the speed further and recovers it more slowly than on a diesel engine of the same rating, where the injection pump can add fuel almost instantly. Makers state the acceptable load steps for each model, often as a sequence such as a first step, a second step and so on, each followed by a recovery time, together with the frequency and voltage dip that results.

In the worked example the first step is assumed at about 20% of rating, so 600 kW of load comes on in three steps of about 200 kW with recovery between them. The loads that cannot wait, such as controls and safety systems, belong in the first step; process motors follow in the order the plant can accept. Where a single motor is larger than an acceptable step, it needs a soft starter or drive, or it stays on another source.

StepLoads (illustrative)Approximate load after step
1Controls, lighting, safety systems, small motors200 kW
2Process pumps on soft starters400 kW
3Cooling plant and remaining process loads600 kW

Gas supply and the gas train

The gas supply is designed from the engine side backwards. The data sheet states the gas flow at full load, the inlet pressure range the engine accepts and the permitted rate of pressure change. The gas train between the supply and the engine normally includes a manual isolating valve, a filter, a pressure regulator, two automatic shut-off valves in series with leak or valve-proving checks where the design calls for them, pressure switches and the engine gas mixer or regulator. Each component is sized for the full-load flow with the pressure still within the engine range during a load step, when the demand rises suddenly.

For pipeline gas, the supplier confirms the available pressure and flow, and the meter and service line are sized for the engine demand on top of any other use on site. For biogas, the gas is cleaned of moisture and hydrogen sulphide before it reaches the engine, and its methane content is monitored, because a fall in methane content reduces output and can stop the engine. For compressed or liquefied gas delivered to site, the store must supply the full-load flow at its lowest working pressure.

Rating, gas quality and derating

The output of a gas engine depends on the gas it burns. The maker states the rating for a gas of defined heating value and knock resistance, often expressed as a methane number, and gives reductions for gas of lower quality, for high intake air temperature and for altitude.

A gas engine rated at 1000 kW on pipeline natural gas may give noticeably less on biogas or on a hot afternoon, and the load plan uses the figure for the worst gas and the hottest day that the site expects. The generator itself is rated in kVA at a stated power factor, and both the engine kW and the alternator kVA are checked against the load.

Room safety, ventilation and detection

A gas generator room is designed so that a leak is detected, diluted and isolated before it can ignite. The main measures are:

  • Gas detection placed to suit the gas: natural gas rises, so detectors are high in the room; heavier gases need detectors near the floor.
  • Ventilation that provides combustion air for the engine and dilution air for any leak, with its failure monitored and linked to the gas valves.
  • Automatic gas shut-off on detection, on ventilation failure, on fire detection and on emergency stop.
  • A review of electrical equipment near the gas train and in the room, so that equipment in any area where gas may be present is suitable for that area.
  • Gas pipework pressure tested after installation and after modification, with joints in the room kept to a minimum.

The safety arrangements are documented on a cause-and-effect chart that lists each detector and switch, and the action it causes, and every line of the chart is tested at commissioning.

Gas sets for standby duty

A gas set used as the only standby source depends on the gas network staying available when the electricity network fails. Where that cannot be assured, critical loads are given a second path, such as a diesel set, a battery system or a UPS that covers the start and the slower load acceptance of the gas engine. Starting time also matters: a gas engine usually needs a purge and ignition sequence and may take longer than a diesel set to accept load. The time from mains failure to each load being supplied is measured during commissioning and compared with what the loads can tolerate.

Sizing heat recovery to the real demand

Heat recovery is sized from the site heat demand over the day and the year, not from the heat the engine can give. A hot water system that can use only half of the recoverable heat for much of the year should be sized for that half, with the rest rejected through the radiator. Oversized recovery equipment costs more, runs at poor efficiency and can force the engine to dump heat it was meant to recover. The engine must also keep its own cooling within limits when the heat demand drops suddenly, so a dump radiator or bypass is part of the design.

Commissioning checks

CheckRecord
Gas train pressure and leak testTest pressure, duration, result
Gas pressure at the engine inlet on load and during stepsLowest pressure recorded against the engine range
Load steps in the planned sequenceFrequency and voltage dip and recovery for each step
Full-load runOutput, exhaust and coolant temperatures, gas flow
Detection, ventilation and fire interlocksEach line of the cause-and-effect chart proved
Heat recovery under changing heat demandEngine cooling held within limits

Choosing between gas and diesel for a site

Site conditionLeans towardsReason
Long running hours, steady load, reliable pipeline gasGasFuel and heat recovery benefits accumulate with hours
Standby only, a few hours a yearDieselFuel stored on site; fast start and large load steps
Large motors started direct on lineDiesel, or gas with soft startingGas engines accept smaller steps
Biogas available from a process on siteGasUses a fuel that would otherwise be flared or wasted
Critical load with gas supply riskGas with diesel or battery backupNo single fuel failure removes the supply

Maintenance differences

A gas engine has an ignition system in place of injectors, so spark plugs, ignition coils and leads become routine wear parts, and spark plug condition is often the first sign of a combustion problem. Valve recession and oil condition are watched closely, because gas engines run hot and dry valve seats, and the oil is chosen to the maker specification for gas engines, which differs from diesel engine oil. Oil analysis at regular intervals is common on long-running gas sets. The gas train itself has filters to change, regulators to check and safety valves to test, each at the interval its maker states.

The starting sequence

A gas engine start normally includes a purge of the intake and exhaust, opening of the gas valves only once the engine is cranking and the ignition is active, and a check that the engine has fired within a set time. If it has not, the gas is shut off and the purge repeated before another attempt. These steps add seconds that a diesel start does not need, and they are part of the time to supply that the loads must tolerate.

Common mistakes

  • Diesel-style load steps assumed.
  • Gas set as the only critical backup.
  • Heat recovery oversized.
  • Gas safety left to the end.

What to send us

Send gas availability, loads and heat needs. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Values are illustrative; use the gas set’s data sheet.

Questions engineers ask

Why does a gas engine accept smaller load steps than a diesel engine?

A gas engine runs on a throttled gas and air mixture and needs its turbocharger to build boost before it can burn more fuel, so a sudden load drops the speed further and recovers it more slowly. A diesel engine can add fuel almost instantly through injection. The maker states the acceptable steps for each model.

Does gas quality affect the output of a gas generator?

Yes. The rating is stated for a gas of defined heating value and knock resistance. Biogas or gas with a lower methane number gives less output, and high intake temperature and altitude reduce it further. The load plan uses the output for the worst gas and the hottest day the site expects.

Can a gas set be standby?

Yes, if the gas supply stays available when the electricity network fails, or if enough gas is stored on site. Because gas engines usually start and accept load more slowly than diesel sets, critical loads that need power within seconds are often given a second path, such as a diesel set, a battery system or a UPS.

How are step loads handled?

From the maker data for the specific engine. The loads are arranged into a sequence of steps that each stay within the acceptable step, with recovery time between them, and the most important loads come first. Large motors use soft starters or drives, and the sequence is proved during commissioning with the frequency and voltage recorded.

Is gas cheaper?

Compare the cost per kilowatt-hour at your own gas and diesel prices, including the gas engine efficiency at your real load, the value of any heat recovered, and the maintenance cost of each option. The answer differs from site to site and changes with fuel prices, so it is worked out for the actual running hours.

What about safety?

Gas detection placed to suit the gas, ventilation with its failure monitored, automatic shut-off valves linked to detection, fire and emergency stop, suitable electrical equipment near the gas train, and trained staff. The arrangements are listed on a cause-and-effect chart and every line is tested at commissioning and at regular intervals.

General guidance only. Use maker data.