In short. Most emission control retrofits succeed or fail at installation. The exhaust route, supports, expansion joints, insulation, sensors, controls and any urea system must be designed together. The result must then be proved by measuring back-pressure and temperature at stepped loads. A short, simple exhaust run with proper supports protects the engine and the device.
Who this page is for: For facility managers, contractors and engineers planning or supervising the fitting of an emission control device.
Key facts
- Support the device on its own frame, not on the engine outlet.
- Use flexible joints near the engine and supports that allow expansion.
- Keep the exhaust run short with few bends.
- Insulate and guard hot surfaces; route the discharge away from air intakes.
- Wire alarms to the generator controller and site monitoring.
- Commission at stepped loads and record the results.
Worked example: back-pressure at commissioning (illustrative)
| Exhaust route | Length and bends | Back-pressure at full load | Engine limit |
|---|---|---|---|
| As first installed | 14 m, 6 bends | 9.5 kPa | 10 kPa: almost no margin |
| After re-routing | 9 m, 3 bends | 7.2 kPa | 10 kPa: margin for filter loading |
The original route would have reached the limit within weeks as the filter loaded. The commissioning record shows the improvement. See back-pressure budget and operation and maintenance.
Do not hang the device from the turbocharger or exhaust manifold. Its weight and thermal growth can crack engine parts.
Signals to connect
| Signal | Use |
|---|---|
| Inlet and outlet temperature | Cleaning control and protection |
| Differential pressure across the filter | Filter loading |
| Engine running and load | Control logic |
| Device alarms | Warn, reduce load or stop, as agreed with the engine maker |
Commissioning steps
- Cold checks: supports, joints, wiring, insulation.
- Run at 25, 50, 75 and 100% load; record back-pressure and temperature.
- Test alarms and their responses.
- Confirm the filter cleaning behaviour.
- Hand over operating limits and records.
Commissioning record
| Load | Back-pressure | Inlet temperature | Outlet temperature |
|---|---|---|---|
| 25% | |||
| 50% | |||
| 75% | |||
| 100% |
The back-pressure budget, and why it is measured at full load
Every retrofitted emission control device adds resistance to the exhaust, and the engine has a published limit on how much resistance it will tolerate. The whole of a retrofit’s mechanical risk sits in the gap between those two numbers, so the budget is worked out before anything is ordered, not discovered at commissioning.
The engine’s limit is a single figure from its manual — commonly between 50 and 100 mbar for sets in this class. Against it sit three contributions: the existing silencer and pipework, the new device when it is clean, and the same device when it has loaded with soot and is due for cleaning. The third of those is the one that decides whether the retrofit is viable, because it is the condition the set spends most of its life approaching.
One measurement decides the whole budget, and it is the one most often taken wrongly. Exhaust back-pressure rises with the square of exhaust flow, and exhaust flow follows engine load. A reading taken at three-quarter load therefore has to be multiplied by about 1.78 to give the full-load figure — (1 ÷ 0.75)². Measuring at the load the set happens to be carrying on the day and treating that as the number understates the real figure by nearly four fifths, which is more than the entire margin on most installations. The reading is taken at full load, on a load bank if the site load will not reach it.
The budget below is for set A of the fleet described across this section, a 500 kVA set going down the retrofit route. Its engine limit is 75 mbar and its existing exhaust measured 28 mbar at full load, not at the three-quarter load the site normally runs.
| Contribution | Clean condition | At the cleaning threshold | What sets the figure |
|---|---|---|---|
| Existing silencer, 18 m of pipe and two bends | 28 mbar | 28 mbar | Measured at full load. Unchanged by the retrofit unless pipework is altered |
| Retrofitted device | 22 mbar | 45 mbar | Supplier figure clean; the threshold is the differential the device is allowed to reach before cleaning |
| Total against the engine | 50 mbar | 73 mbar | Sum of the two rows above |
| Engine limit | 75 mbar | 75 mbar | Engine manual, at the set’s rated speed and load |
| Margin | 25 mbar | 2 mbar | Limit minus total |
Read the last column of that table and the commissioning scheme writes itself. With 25 mbar of margin when clean and 2 mbar at the cleaning threshold, the cleaning interval cannot be a calendar. It has to be a differential pressure switch across the device, set at the 45 mbar threshold and wired to an alarm the operator sees, because the margin at that point is smaller than the measurement uncertainty of the gauge. A site running this installation on a six-monthly cleaning schedule would spend part of every cycle over the engine’s limit without anything telling it so — and over-pressure shows up as lost power, high exhaust temperature and turbocharger distress, none of which points obviously back at the exhaust.
What the pipework has to provide, and the three things that go wrong
A device that fits the budget on paper still has to be installed in a way that keeps it there. Three mechanical details account for most of the retrofits that come back.
- Support and expansion. The device is heavy and it sits on a line that grows when it heats up. It carries its own support off the structure, not off the engine’s exhaust outlet, and there is a flexible section between the engine and the device so that expansion and engine movement are absorbed rather than transmitted. A device hung from the manifold cracks the manifold.
- Drainage and condensate. Any horizontal run collects condensate on cooling, and a device is a low-velocity volume that collects more. The line falls away from the engine, and the lowest point has a drain that somebody can actually reach. Water sitting in the device corrodes the substrate from the inside and shows up months later as an unexplained rise in pressure drop.
- Access for cleaning. The cleaning operation is the one that will be done most often, by whoever is on site. If the device can only be removed by cutting pipework or by dismantling a canopy panel that is bolted behind a wall, it will not be cleaned on schedule — and the budget above depends entirely on it being cleaned on schedule. Clearance to withdraw the element, in the direction it withdraws, is checked with a tape before the device is positioned.
Two exceptions are worth noting. On an acoustic-enclosed set there may be no room inside the canopy for the device at all, and mounting it outside the enclosure changes both the pipework length in the budget above and the noise performance the enclosure was bought for, so both have to be re-checked rather than assumed. And where a set already runs close to its back-pressure limit before any retrofit — which the first row of the budget will reveal — the honest answer is that the exhaust system has to be improved first, by shortening the run or going up a pipe size, and the device fitted afterwards.
Proving it at commissioning: five readings, and the one that must be repeated
A retrofit is signed off against measurements, not against a delivery note, and the measurements have to be taken in a specific order because each one qualifies the next. The set is brought to full load on a load bank, held until exhaust temperature stabilises, and then the readings are taken together and written on one sheet with the load beside them. Taken at different loads on different days they prove nothing, because every figure in the list depends on load.
| Order | Reading | Where it is taken | Set A, at full load | Why it has to be this one |
|---|---|---|---|---|
| 1 | Electrical load, kW and amps | Set controller and a clamp meter as a check | 400 kW, 696 A at 415 V | Every other reading is only meaningful against the load it was taken at |
| 2 | Back-pressure upstream of the device | Tapping between engine and device | 28 mbar | Isolates the existing exhaust from the new device, so a later rise can be attributed correctly |
| 3 | Differential across the device | The device’s own two tappings | 22 mbar | This is the clean baseline the cleaning threshold is measured against for the rest of the set’s life |
| 4 | Exhaust temperature at the device inlet | Thermocouple in the inlet flange | Recorded and retained | Decides whether the device reaches its working temperature on this set’s real duty |
| 5 | Alarm and trip proving | Pressure switch and any device alarm contact | Alarm at 45 mbar, verified by simulation | The budget depends on the alarm, so an unproven alarm leaves the installation unprotected |
Reading 3 is the one that must be repeated, and this is the part most commissioning records miss. A clean baseline taken once is a single point; the figure that matters operationally is how fast the differential climbs from it.
Taking the same reading again after the first 50 and the first 200 hours of normal duty turns the baseline into a loading rate, and the loading rate is what sets the real cleaning interval for this set on this site — which will not be the interval in the device’s leaflet, because that was written for an assumed duty. A set at 75% load on clean fuel loads slowly; the same device on a lightly loaded set loads several times faster, because unburnt fuel rather than ash is what fills it.
Reading 4 deserves the same follow-up for a different reason. The device has a temperature window below which it does not work as intended, and the inlet temperature at full load is the best case. If the set’s ordinary duty is well below full load, the inlet temperature in service will be lower than the commissioning figure, and a device that was proved at 400 kW may spend its working life below its window.
That is a duty problem rather than an installation problem, and the time to find it is at commissioning, while a load-bank is still on site and the question can be answered by loading the set to its real operating point and taking the reading again.
Finally, the sheet is kept with the set’s file rather than with the installer’s paperwork. The commissioning readings are the only baseline the site will ever have, and the first time anybody needs them — a year later, when the differential has risen and nobody knows whether that is normal — the question cannot be answered without them.
Common mistakes
- Long exhaust runs with many bends.
- Device weight on the engine.
- Alarms not wired to anything.
- No stepped-load commissioning record.
What to send us
Send the room layout, exhaust route and engine data. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Values are illustrative.
Questions engineers ask
How much back-pressure does a retrofitted emission control device add?
Typically around 20 mbar when clean, rising to roughly twice that by the time it is due for cleaning. What matters is the total against the engine’s published limit: an engine limited to 75 mbar whose existing exhaust already consumes 28 mbar has 47 mbar for the device, which is adequate when clean and leaves only 2 mbar at a 45 mbar cleaning threshold.
At what load should exhaust back-pressure be measured?
At full load, on a load bank if the site load will not reach it. Back-pressure rises with the square of exhaust flow, so a reading taken at three-quarter load has to be multiplied by about 1.78 to give the full-load figure. Treating a part-load reading as the answer understates it by nearly four fifths, which is more than the entire margin on most installations.
Should the cleaning interval for a retrofitted device be a calendar interval?
Not where the back-pressure margin is small. If the total at the cleaning threshold leaves only a couple of millibars below the engine’s limit, the trigger has to be a differential pressure switch across the device wired to an alarm, because the margin is smaller than the measurement uncertainty of a gauge. A site on a six-monthly schedule would spend part of every cycle over the engine’s limit with nothing telling it so.
Can the old silencer stay?
It depends on the layout and the back-pressure. Where the device includes its own silencing, the old silencer may be removed; where it stays, the combined back-pressure of the device and silencer must remain within the engine limit, measured at full load after installation. The noise at the boundary is checked as well.
Who supports the weight?
Dedicated supports or a frame, never the engine outlet or the turbocharger. A flexible connection isolates the device from engine vibration and allows for thermal expansion, so the weight and movement of the device do not crack the turbocharger housing or the exhaust manifold over time.
Is a shutdown needed?
Usually yes. Plan the work in a window when the set is not needed, and arrange a backup source such as a rental generator for critical loads. The installation, the controls integration and a full-load test with back-pressure and temperature readings are completed before the set returns to service.
What records to keep?
The commissioning data including back-pressure and exhaust temperature at each load, the controller settings and alarm limits, the type-approval certificate covering the engine, the installation drawing, and every alarm, cleaning and maintenance event afterwards. These records support compliance and show clearly when service is due.
General guidance only. Follow device maker instructions.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.