Load Shedding Planner

How to decide whether load shedding is needed and plan it: capacity shortfall cases, shed tiers, triggers, staged shedding and restoration, with a worked shortfall example.

In short. A load-shedding plan answers three questions. In which situations can the available generation be less than the load? How large is the shortfall in each? Which loads go first, and on what signal? List the cases first: all sets running, one set lost, and only a small standby set. Then the plan becomes a set of shedding stages, each with its own trigger and restore order.

Who this page is for: For facility managers and engineers preparing a load-shedding scheme for generator supply.

Key facts

  • Work out the shortfall case by case.
  • Aim to keep running sets at or below about 90% after shedding.
  • Loads to shed must be on feeders that can be switched separately.
  • Faster triggers for bigger shortfalls.
  • Restore in steps, highest priority first, and bring large self-starting motors back one at a time.
  • Test with a controlled set trip.

Worked example: three 500 kVA sets (400 kW each), 1050 kW load (illustrative)

CaseAvailableKeep at about 90%ShedTrigger
All three sets1200 kW1050 kW (88%)NothingNone
One set lost800 kW720 kW330 kW: comfort cooling and part of productionBreaker signal from the tripped set, with under-frequency as backup
Only a separate 250 kVA emergency set (200 kW)200 kW180 kWAll except life safety and criticalSource selection at changeover

In this example, comfort cooling and two production lines are on separate feeders, so each stage can be switched. See priority control and multi-generator dispatch.

Do not plan shedding on a board where essential and non-essential loads share feeders. Without separate switching, there is nothing that can be shed.

Stages and restoration

StageLoadsRestored
1Comfort coolingLast
2Non-critical productionSecond, after remaining production
3Remaining productionFirst of the shed loads
Never shedLife safety and criticalNot applicable

See restart sequencing.

Shortfall sheet

The shedding cases for the same pharmaceutical formulation block: 687 kW of diversified demand carried by three 750 kVA sets, two duty and one spare. The worked example above sheds comfort cooling and production from a 1050 kW load; this site has almost no comfort load to give away, and the sheet exists to show what happens when the easy stages run out.

CaseAvailable kWLoad kWShed kW
Normal. Mains healthy—687Nothing
Mains lost, both duty sets on the bus1200, target 1080 at 90%687 (57% of the pair)Nothing
One duty set lost. The spare takes about 25 s to start and synchronise600, target 540 at 90%687147. Tiers 4 and 3 together give only 104
Same case, after shedding every tier 3 and tier 4 load there is600583 (97% of one set)104, and still 43 kW short of the target
Same case, chiller shed as well to reach the target600423 (70%)264, and a 15-minute clock starts on the clean rooms
Spare fails to start too. Mains gone, one set only, indefinitely600423264 held. Batch decision inside 15 minutes
    
    

Row three is the whole sheet. Everything the site is willing to shed comes to 104 kW, and a single set is 147 kW short. Tier 4 is 22 kW of workshop, canteen and external lighting. Tier 3 is 82 kW of granulation and purified water. Shed all of it, instantly and without argument, and the remaining load still sits at 583 kW on a 600 kW engine — 97%, with no margin for the compressed-air plant to restart and nothing left to give. A plant with a comfortable shedding scheme has a large tier 4; this one does not, because a clean room has no comfort load.

The next thing to shed is the chiller, and that is a different kind of decision. It takes the load to 423 kW and 70%, which is comfortable, and it starts a fifteen-minute clock on the rooms’ temperature and humidity. Nobody wants the load-shedding relay making that choice at two in the morning, so on this site the chiller is shed by the scheme and the operator is alarmed at the same instant, with a written instruction to decide within ten minutes whether to abandon the batch or to restore the chiller and accept the overload.

Those twenty-five seconds in row three are the figure the whole arrangement turns on. The spare set starts, runs up, checks synchronism and closes, and for that quarter of a minute the site is genuinely on one machine. Twenty-five seconds is shorter than the chiller matters over, so the honest scheme sheds tiers 4 and 3 immediately, accepts 97% for the duration, and does not touch the chiller unless the spare has failed to arrive. Shedding the chiller the instant a set trips would cost a batch every time a breaker operated spuriously.

Row two is the case that should be read for reassurance and usually is not. Both duty sets carry the whole site at 57%, so an ordinary mains failure needs no shedding at all. The shedding scheme exists entirely for the second failure, not the first, and that is worth saying out loud to an operations team that assumes a transfer and a shed are the same event. On this site they are not: the plant has run on generator for four years without ever shedding a load.

One structural warning, which is the panel above this sheet made concrete. All of this depends on tier 3 and tier 4 being switchable separately, and on this site they are: the workshop and external lighting sit on their own sub-board, and granulation and purified water each have their own feeder. Had the canteen shared a feeder with the clean room lighting — which is exactly how buildings get wired when nobody asks — the 104 kW in row three would have been zero and the sheet would have had nothing to offer but the chiller.

The compressed-air plant is not in the shed list at any stage, and the priority register is why. It looks like a utility, it is rated at 75 kW, and on most sites it would be the first thing a scheme reaches for. Here it carries the clean rooms’ pressure cascade through the pneumatic dampers, so shedding it buys four minutes and then costs the batch anyway. A shedding scheme written from the load list rather than from the register would have taken it out at stage one.

Classifying loads for shedding

Each feeder is given a priority by asking what happens if it stops for a minute, for an hour and for a day. The answers place it in a shedding group and decide whether it is restored automatically or by an operator.

PriorityEffect of lossExamplesShedding
1Risk to life, safety or serious damageFire pumps, emergency lighting, critical process controlsNever shed
2Major loss of production or productMain process lines, cold storageShed only as a last stage
3Inconvenience or short delayOffice cooling, secondary pumpsMiddle stages
4Little effect over hoursComfort heating or cooling in stores, battery charging, yard lighting by dayFirst stage

Frequency-based and power-based shedding

Frequency-based shedding acts when frequency falls, which works on any source but responds only after the shortfall has begun. Power-based shedding measures the load against the capacity of the running sets and trips loads as soon as a set is lost or load exceeds a limit, which is faster and gentler on the remaining engines. Many generator plants use power-based shedding as the first line and frequency-based shedding as a back-up.

Generator-specific points

  • A generator cannot accept unlimited load steps, so restoration groups must fit within the load acceptance of the running sets.
  • After a transfer from grid, all loads may try to restart at once; shedding groups double as restart groups.
  • Shedding should act before generator protection trips the set, so settings are coordinated.
  • Where sets run in parallel, the loss of the largest set defines the worst shortfall.

Restoration rules

Restoration is slower than shedding. Each group returns only when frequency and voltage have recovered, enough capacity is running and a short stable period has passed. Groups come back in priority order with a delay between them, so the system is never asked to accept everything at once. Where an operator restores loads manually, the order is posted in the control room.

Testing and records

Test each stage at commissioning and at least once a year by simulating a source loss or a low frequency signal, checking that the right breakers open in the right time and that restoration follows the planned order. Record the results, and repeat the test after any change to loads, sets or settings.

A short example of shedding stages on two sets (illustrative)

Two 500 kVA sets give 800 kW together and carry a 700 kW plant load. If one set trips, 400 kW remains against 700 kW. The power-based scheme sheds priority 4 and priority 3 loads totalling 320 kW within a second, leaving 380 kW on the running set. Priority 2 loads stay on, and the tripped set is restarted and synchronised before any shed load returns.

Common mistakes

  • Only the normal case considered.
  • Mixed feeders.
  • Slow triggers for large shortfalls.
  • Everything restored at once.

What to send us

Send generator ratings and your feeder list with loads. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Values are illustrative.

Questions engineers ask

How are loads prioritised for a shedding scheme?

By asking what happens if each feeder stops for a minute, an hour and a day. Loads that risk life or serious damage are never shed, major production loads go last, and loads with little effect over hours are shed first and restored last, in planned groups.

What is the difference between frequency-based and power-based load shedding?

Frequency-based shedding acts after frequency has started to fall and works on any source. Power-based shedding compares load with running capacity and trips loads as soon as a set is lost, which is faster and gentler on the engines. Many plants use power-based first and frequency-based as back-up.

How should shed loads be restored on generators?

Slowly and in priority order. Each group returns only when frequency and voltage have recovered, enough capacity is running and a short stable period has passed, with a delay between groups so every step fits within the load acceptance of the running sets and nothing trips again.

What happens in a two-set plant when one generator trips?

In the illustrative case, two sets giving 800 kW carry 700 kW. When one trips, 400 kW remains, so the scheme sheds 320 kW of lower-priority load within a second, leaving 380 kW on the running set until the tripped set is restarted and synchronised.

When is load shedding not needed?

When any credible failure still leaves enough capacity for the entire load. That usually needs larger N+1 capacity. Where that spare capacity costs more than the consequence of shedding low-priority loads, a shedding scheme is the more economic way to keep critical loads supplied after a unit trips.

How much load should I shed?

At least the shortfall, with margin, for each case. For example, if three 500 kVA sets carry 1200 kVA and one trips, the remaining 1000 kVA is 200 kVA short, so at least 200 kVA plus a margin is shed at once, with the lowest-priority loads dropped first.

Is manual shedding acceptable?

For slow events perhaps, but generator trips need fast automatic action. When a running set trips, the remaining sets slow down within a second or two, far faster than an operator can react, so automatic shedding on frequency or breaker status is used, with manual shedding kept for slow overloads.

How do I test the scheme?

Simulate each case, including a unit trip, and record the response. Record the frequency dip, the loads shed, the time taken and the restoration sequence, and compare them with the design. Repeat after any change to the loads, the sets or the controller settings, since a scheme can quietly drift out of date.

Figures are illustrative. Shed lists must be validated with operations.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.