In short. Automatic load shedding protects the generators when demand exceeds what is running. Loads are sorted into priorities, and the lowest are dropped first, fast enough that the remaining sets do not trip. It is needed whenever generator capacity is less than the full demand, or when losing one set would overload the rest. It works only if the loads to be shed are on feeders that can be switched separately.
Who this page is for: For facility managers, plant engineers and consultants planning how generator supply is protected from overload.
Key facts
- Priority order: life safety, then critical, then production, then comfort.
- Shed on loss of a set, overload or falling frequency.
- A signal on loss of a set is the fastest trigger.
- Shedding must act before the remaining sets trip on overload.
- Restore shed loads in steps once capacity returns.
- Test shedding with a real set trip, not only on paper.
Worked example: two 500 kVA sets, 400 kW each (illustrative)
| Priority | Load | Both sets (800 kW) | One set lost (400 kW) |
|---|---|---|---|
| 1 Life safety | 60 kW | On | On |
| 2 Critical (UPS input and recharge) | 140 kW | On | On |
| 3 Production | 300 kW | On | 160 kW kept, 140 kW shed |
| 4 Comfort cooling | 400 kW | Shed | Shed |
| Running load | 500 kW (63%) | 360 kW (90%) |
When one set trips, the remaining set sees 500 kW against its 400 kW rating. The shed signal from the tripped set drops 140 kW of production straight away, before frequency falls far. See multi-generator plants and generator transient studies.
Do not rely on falling frequency alone to shed load after a set trips. By the time frequency has fallen, the remaining set may already be tripping. Use a direct signal from the tripped set as well.
Shedding triggers
| Trigger | Speed | Use |
|---|---|---|
| Loss of a set (breaker signal) | Fastest | Sudden capacity loss |
| Generator kW above a threshold | Seconds | Gradual overload |
| Underfrequency | Fast backup | Anything the others miss |
Priority sheet
That same block’s feeders in shedding order. The sets are the two 500 kVA machines rated 400 kW each from the example above, carrying a larger and more awkward load list. The fourth column is the one that decides whether the priority order can actually be executed, and on this site it is where the scheme fails.
| Feeder | kW | Priority | Can it be switched separately? |
|---|---|---|---|
| Fire pump and alarm system | 30 | 1 — life safety, never shed | Yes, own breaker |
| UPS input: theatres, IT and data room cooling | 287 | 2 — critical, never shed | Yes, own breaker |
| Lifts, one of four | 22 | 3 — essential | Yes |
| Ward lighting and sockets | 95 | 4 — essential, last of the essentials to go | No — shares a board with theatre support, which must not be shed |
| Sterilising and kitchen | 88 | 5 — shed stage 2 | Yes |
| Administration air conditioning | 60 | 6 — shed stage 1, first to go | Yes |
Do the subtraction. Total load is 582 kW. Everything that can be shed — stages 1 and 2, the air conditioning and the kitchen — comes to 148 kW. Shed all of it and 434 kW remains. Against both sets, 800 kW, that is comfortable. Against one set, 400 kW, it is 34 kW over, and the surviving set will run in overload until something trips.
Row four is why. The next load in priority order is the ward lighting at 95 kW, which would bring the remainder to 339 kW and solve the problem outright — and it cannot be shed, because it shares a board with theatre support circuits that must stay live. The priority order is correct on paper and unexecutable in copper.
The fix is a board alteration, not a control setting: split the ward lighting from the theatre support circuits so that stage 3 can drop 95 kW. Until that is done, no amount of configuring the shedding scheme will make one set carry this building, and the scheme will keep operating exactly as designed while the set overloads.
This is the arithmetic that should be done on the day the priorities are written, and it is a subtraction anyone can do. It was found here by deliberately failing a set during an integrated test — nine seconds of a 400 kW machine carrying 434 kW — which is a far more expensive way to discover it.
How much load must go when one set is lost
When one generator in a plant trips, the remaining sets inherit its load at once. If they cannot carry it, load must be shed, and the amount depends on two things only: how many sets were running and how heavily they were loaded. The share of the total load that must be removed to bring the remaining sets back to their full rating is one minus the remaining sets’ capacity divided by the load they now face.
| Sets running | Loaded at 60% | Loaded at 70% | Loaded at 80% | Loaded at 90% |
|---|---|---|---|---|
| 2 | 16.7% | 28.6% | 37.5% | 44.4% |
| 3 | None | 4.8% | 16.7% | 25.9% |
| 4 | None | None | 6.3% | 16.7% |
Three sets of 400 kW carrying 1000 kW are each about 83% loaded; losing one leaves 800 kW of capacity facing 1000 kW, so at least 200 kW, a fifth of the load, must be shed. The figures bring the survivors only to full rating, with nothing in hand, so the first shedding block should be larger than the table’s figure by a margin that leaves the remaining sets comfortably loaded. The table also shows why a plant with more sets, each less heavily loaded, needs to shed far less when one is lost: the shedding scheme and the loading policy are two halves of the same decision.
How fast the shedding has to happen
When a set trips, the survivors are suddenly overloaded and their speed starts to fall. The initial rate of fall is about the overload, as a share of the remaining capacity, multiplied by 50 Hz and divided by twice the inertia constant. In the example above, the two remaining sets face a 25% overload; with an inertia constant of about one second, the frequency starts falling at about 6.25 Hz per second, and would reach 47.5 Hz, a common under-frequency trip point, in about 0.4 seconds if nothing were done.
That timescale decides the method. Shedding triggered by an under-frequency relay, with its own measuring time and breaker opening time, may be too slow for a large loss on a small plant. Faster schemes act on the cause rather than the symptom: the opening of a generator breaker, or a trip signal from a generator’s protection, sends a direct command to open the planned shedding block at once, before the frequency has fallen far.
Under-frequency shedding then remains as a backup for losses the direct scheme does not see. Check the opening times of the breakers or contactors that do the shedding; a shunt-tripped breaker that takes a tenth of a second is fast enough, while a motorised breaker that takes a second is not.
Confirming that the load really went
A shedding command is only half the scheme; the other half is knowing that the load actually disconnected. A breaker whose shunt trip has failed, or whose control circuit was isolated during maintenance and never restored, receives the command and does nothing, and the plant collapses while the controller believes it has shed.
Each shedding device should report its position back to the controller through an auxiliary contact, and the controller should compare the load actually removed with the load it intended to remove. If a block fails to open, the scheme should move at once to the next block. Test every shedding device individually at least once a year by commanding it to open and confirming both the position feedback and the change in measured load.
Rules for operators during and after shedding
After an automatic shed, the people who own the shed loads will want them back, and they will ask the person nearest the switchboard. The rules for what that person may do should be written in advance and displayed beside the controls.
Typical rules are these: no shed load is restored by hand while the plant is short of capacity; loads are restored in the planned order, by the controller or by procedure; the reason for the shed is found before the tripped set is restarted and loaded; and every shed and restoration is logged with the time and the person responsible. Without such rules, the most persuasive load owner, not the most important load, gets supply back first, and a plant that survived the loss of a set is overloaded again by hand ten minutes later.
Common mistakes
- Mixed feeders that cannot be shed.
- Frequency-only shedding.
- Shed loads restored all at once.
- Never tested with a set trip.
What to send us
Send the generator ratings and feeder list with loads. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Values are illustrative.
Restoration, where shedding schemes usually fail
Shedding is the half that gets designed. Restoration is the half that gets left to whoever is on shift, and it is where a scheme that worked perfectly causes a second outage.
The failure is simple to describe. Capacity returns — the second set runs, or the mains comes back — and 148 kW of shed load is restored at once. Every motor in it starts simultaneously, so the inrush is several times the running figure, the frequency dips, and the shedding scheme sees an overload and sheds again. On a bad arrangement that oscillates: shed, restore, shed, restore, with the critical load riding on a bus that is being disturbed every few seconds.
What a sound restoration sequence does:
- Wait for stable capacity, not merely for a breaker to close. Frequency and voltage within band for a set period — a few seconds — before anything is restored.
- Restore in the reverse of the shed order, in stages, with a gap. The last thing shed is the first thing back, and each stage gets long enough to settle before the next: typically ten to twenty seconds, set from the largest motor in the stage rather than picked round.
- Size each stage by its starting demand, not its running load. A 60 kW air conditioning stage whose motors start direct on line can ask for three or four times that at the instant of restoration. Two stages of 30 kW are often safer than one of 60.
- Hold the headroom check at every stage. If restoring the next stage would take the remaining capacity below the margin, the scheme waits rather than trying and failing.
- Make manual restoration possible and documented. Somebody will have to do this by hand one day, and the order matters just as much when a person is doing it.
Test it the same way the shedding was tested: fail a set with the building on load, let the scheme shed, then bring the set back and watch the restoration. Both halves on one test run. A scheme proved only on the shedding half is half proved, and the untested half is the one that runs while everyone is relieved that the first half worked.
Questions engineers ask
How much load must be shed when one generator trips?
One minus the remaining capacity divided by the load. Three 400 kW sets carrying 1000 kW lose one and leave 800 kW facing 1000 kW, so at least 200 kW, a fifth of the load, must go. Two sets at 80% load must shed 37.5%; four sets at 80% only about 6.3%. These figures bring the survivors only to full rating, so make the first shedding block larger to leave a margin.
How do I know a shedding command actually worked?
Through position feedback and measured load. Each shedding breaker or contactor should report its position to the controller through an auxiliary contact, and the controller should compare the load actually removed with the load it meant to remove, moving at once to the next block if one fails to open. Test every shedding device individually at least once a year by commanding it open and confirming both its position signal and the drop in measured load.
What is the difference between static and dynamic shedding?
Static shedding acts on known capacity and events. Dynamic shedding reacts to measured frequency, catching unforeseen conditions. Most critical sites use both: static shedding for planned conditions such as one generator out of service, and dynamic shedding as the safety net when frequency falls unexpectedly.
How fast must shedding be?
For generator loss it must act before the remaining units stall. That is often within a fraction of a second, so dedicated fast logic is used. Slower shedding, over seconds, suits gradual overloads where the remaining sets can carry the load briefly before it is reduced.
Can shedding be fully automatic?
Usually yes for the first response. Restoration may be automatic or operator-supervised. Restoration is staged, adding loads in priority order only when spare capacity is confirmed, so that the system does not overload again. Each shedding event is logged with its cause and timing for review afterwards.
How often should the priority list be reviewed?
Whenever loads change, and at least periodically as part of design review. The list states each load, its priority, the shedding stage and the reason, and it is agreed with the operations owner. Testing the shedding scheme on load confirms that the right loads drop in the right order.
This guide gives general principles. Settings must be developed and tested for the actual system.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.