In short. Maximum demand is the highest load a system actually draws. It is almost always less than the connected load, because loads do not all run at once or at full rating. A demand percentage for each load turns the connected list into an estimate of maximum demand. Adding power factors gives the kVA the generator must supply. Good estimates avoid an oversized, lightly loaded generator. Careless ones cause overloads.
Who this page is for: For facility managers, electricians and consultants estimating maximum demand from a load list before sizing a generator or transformer.
Key facts
- Connected load: everything added up at its rating.
- Demand percentage: how much of its rating a load draws at the peak.
- Diversity here: maximum demand ÷ connected load.
- kVA combines kW and kVAr, not kVA figures added row by row.
- Measured data beats assumed percentages.
- Motors started direct-on-line need a separate starting check.
Worked example: the calculator’s default list
| Load | Connected | Demand % | At maximum demand |
|---|---|---|---|
| Lighting and sockets | 15 kW | 70% | 10.5 kW |
| 4 air conditioners × 5.5 kW | 22 kW | 80% | 17.6 kW |
| 2 pump motors × 7.5 kW | 15 kW | 100% | 15.0 kW |
| Lift | 11 kW | 60% | 6.6 kW |
| Total | 63 kW (72.6 kVA) | 79% overall | 49.7 kW (57.3 kVA, power factor 0.87) |
Sizing on 63 kW connected would have put the set further from its working load. With 15% growth, 80% planned loading and a 0.8 rated power factor, the calculator suggests 100 kVA. See generator capacity checks and load lists.
Do not apply low demand percentages to loads that really do run together, such as pumps, cooling or process lines. Where in doubt, measure the peak before reducing it.
Typical demand percentages (confirm by measurement)
| Load type | Typical range |
|---|---|
| Lighting | 70–100% |
| Air conditioning in hot weather | 80–100% |
| Duty pumps | 100% |
| Lifts | 40–70% |
| Workshop sockets | 30–60% |
Using measured data
A week of logged demand at the main incomer, taken in the hottest or busiest season, gives the most reliable maximum demand. Compare it with the calculated figure; if they differ widely, correct the demand percentages before sizing. See load-list generator sizing.
Demand sheet
The demand sheet for the same pharmaceutical formulation block, taken straight from the load list on the connected-load page. The worked example above is a small building whose demand comes out at 79% of connected; this is a process plant, where most of the percentages are 100 and the overall figure still lands at 71 — for a reason that has nothing to do with diversity at all.
| Load | kW connected | Demand % | kW at peak |
|---|---|---|---|
| CH-01 chiller | 168 | 95% | 160.0 |
| CH-02 chiller, standby | 168 | 0% | 0 |
| AHU-01 to AHU-06 air handling | 142 | 100% | 141.9 |
| P-01, P-02 chilled water pumps | 49 | 100% | 49.5 |
| AC-01 compressed-air plant | 81 | 85% | 68.5 |
| PW-01 purified water system | 33 | 70% | 23.3 |
| PR-01 granulation and coating | 98 | 60% | 58.7 |
| L-01 clean room lighting and small power | 70 | 90% | 63.0 |
| UPS-01 input, 120 kVA unit | 100 | 100% | 100.0 |
| W-01 workshop, canteen and external | 55 | 40% | 22.0 |
| Total | 965 | 71% overall | 687 kW, 768 kVA at power factor 0.894 |
Twenty-nine points of diversity, and fifteen of them are one machine that will never run. Take CH-02 out of the sheet and the remaining nine loads give 687 kW of demand against 797 connected, which is 86% — well above the 79% in the example on this page, and exactly what a plant full of chillers, clean room air and pumps ought to look like.
The 71% figure is arithmetically correct and badly misleading, because it averages a standby machine at nought with nine loads that nearly all run flat out. Anyone carrying 71% forward as a rule of thumb for the next pharmaceutical block would size it about a sixth light.
That is the practical rule this sheet exists to enforce: a standby unit belongs on the demand sheet at 0%, not left off it, and the overall percentage has to be quoted with and without it. Left off, the connected total stops matching the load list and the switchboard sizing loses its basis. Counted at anything above nought, the generator grows for a machine that only starts when its twin has already stopped.
Of the nine running loads, four sit at 100% or 95%, and none of them is negotiable. Clean room air handling runs at whatever air change rate the room classification demands, every hour the room is in use; a chilled water pump either circulates or it does not; the UPS draws its input whether the building is busy or empty. The only genuine diversity on this site is in the last four rows — the purified water skid at 70%, the granulation line at 60%, the lighting at 90% and the workshop at 40% — and together they account for 89 kW of the 110 that diversity actually removes.
The 60% against PR-01 is the one row on the sheet that should be measured rather than assumed, and it is marked that way for a reason. Granulation and coating run in campaigns: during a campaign the line is close to 100%, and between campaigns it is near nought.
A sixty percent annual average is a true statement about the year and a false statement about any particular hour, and a generator is sized for the hour. The honest way to use it is to size for the campaign case — which would add about 39 kW, taking the peak to 726 — and then confirm by logging a campaign week before the order is placed.
The last cell converts the answer into the quantity a generator is actually bought in. Applying each load’s own power factor to its diversified kilowatts and combining the totals as a vector gives 768 kVA at a power factor of 0.894. Dividing 687 kW by a blanket 0.8 instead, as is often done, would have given 859 kVA — 91 kVA of plant bought to correct a power factor the site does not have. The sheet’s own power factors are better information than a rated figure borrowed from the generator’s nameplate.
One habit makes the whole sheet defensible later. Date it, and record alongside it what the main incomer was actually reading that month. On this site the logged maximum over the preceding year was 702 kW against the sheet’s 687, a 2% difference, which is close enough to leave the percentages alone and good enough to put in the report. Had the log said 850, the sheet would have been wrong and no amount of care in the later sizing would have recovered it.
How diversity differs between building types
Diversity reflects how loads overlap in time, and that depends on how a building is used. Residential blocks have high diversity because households use appliances at different times. Offices have less, because lighting, computers and cooling all run through the same working hours. Hospitals and data centres have little diversity in their critical loads, which run all the time. Factories vary widely: a single-shift plant with interlocked processes may run most of its connected load together, while a jobbing workshop rarely does. The calculator factors are a starting point; the use pattern of the actual building decides the final value.
Measuring demand on an existing site
- Install a three-phase logger at the main incomer, recording kW, kVA and power factor at 15-minute or shorter intervals.
- Record for at least two to four weeks, covering busy and quiet days.
- Note events during the recording, such as production changes, outages or unusual weather.
- Read the highest demand, the typical daily profile and the lowest regular load.
- Compare the measured peak with the diversity calculation and investigate any large gap.
The utility maximum demand reading is also useful, but it shows only the highest average over the billing interval, not the shape of the load.
Maximum demand in kW and kVA
The same load has a higher demand in kVA than in kW unless the power factor is close to one. A site with 400 kW of maximum demand at 0.85 power factor draws about 470 kVA. Generators, transformers and cables are sized on kVA and current, so a diversity result in kW is converted using the expected power factor before it is used for sizing.
What diversity does not cover
Diversity describes steady running demand. It does not reduce the starting current of the largest motor, the restart surge when all loads return after an outage, or harmonic heating from non-linear loads. These are checked separately after the diversified demand is known, and they often decide the generator size more than the demand itself.
Linking demand to the supply contract
The contract demand agreed with the distribution company should reflect the realistic maximum demand plus planned growth. Setting it far above actual demand can mean paying for unused capacity, while setting it too low can bring penalties when demand is exceeded. A diversity calculation checked against measured data gives a sound basis for that figure and for the generator that backs it up.
Reviewing the contract demand after a year of logged data, and again after major load changes, keeps it aligned with how the site actually uses power.
Common mistakes
- Sizing on connected load.
- Adding kVA row by row.
- Low percentages on loads that run together.
- Ignoring motor starting.
What to send us
Send your load list or a demand log. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. The worked example uses the calculator’s default list.
Questions engineers ask
Why does diversity vary between building types?
Because it reflects how loads overlap in time. Homes have high diversity as households use appliances at different times, offices less because loads share working hours, and hospitals and data centres little in their critical loads. The actual use pattern decides the final factor, not only typical tables.
How do I measure maximum demand on an existing site?
Log kW, kVA and power factor at the main incomer in 15-minute or shorter intervals for two to four weeks covering busy and quiet days, note unusual events, then read the peak, daily profile and lowest regular load and compare them with the diversity calculation.
How is maximum demand converted from kW to kVA?
Divide kW by the power factor. A site with 400 kW of maximum demand at 0.85 power factor draws about 470 kVA. Generators, transformers and cables are sized on kVA and current, so the conversion is done before the result is used for any equipment sizing or contract demand.
Does diversity reduce motor starting requirements?
No. Diversity covers steady running demand only. The starting current of the largest motor, the restart surge when loads return after an outage, and harmonic heating are checked separately after the diversified demand is known, and they often set the generator size more than the steady demand itself.
What is the difference between demand factor and diversity factor?
Demand factor compares maximum demand to connected load for one group. Diversity factor compares the sum of group maxima to the maximum of the combined group. Both reflect the fact that not every load runs at full output at the same time, and both are taken from measured data where possible.
Can I use diversity for generator sizing?
Carefully. Outage restart can bring loads on together, so test the assumption for that case. After an outage, air-conditioning, pumps and refrigeration can all restart together when generator supply arrives, removing the diversity seen in normal running. Staggered restart timers protect the generator and let the diversified figure be used safely.
Where do typical factors come from?
Design codes, handbooks and experience. They are starting points; measured data is better. Logged demand from the actual site, or a similar site, over a representative period shows the real diversity, including seasonal peaks, so the factors used are supported by evidence rather than copied from a table.
Should I add growth after diversity?
Yes. Apply growth to the diversified demand, with a clear assumption. State the growth allowance as a percentage or as named future loads, and record where it came from, so that a later reviewer can see what margin was included and whether the site has since grown into it.
Figures are illustrative. Use measured data and applicable codes for design.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.