In short. Generator loading is the running load as a share of the set’s rating. Too high leaves no headroom for motor starts, load steps, derating and growth. Too low, for long periods, causes wet stacking, carbon build-up and poor fuel efficiency. A good design picks a healthy loading band for normal operation, keeps real spare capacity for steps and, in parallel plants, for the loss of a set, and plans loaded running when the site load is small.
Who this page is for: For facility managers, plant engineers and buyers checking whether a generator is right-sized for its load profile.
Key facts
- Loading (%) = running kW ÷ rated kW × 100; check kVA against the alternator rating too.
- Spare capacity = rating − running load; it must cover the largest step and motor start.
- Long periods below about 30% load risk wet stacking; follow the engine maker’s minimum.
- Read a load profile: minimum, average and peak, and how long the load sits in each band.
- In redundant plants, spare capacity includes the loss of a set.
- Periodic load-bank runs clear light-load deposits.
Loading terms
Worked example: reading a load profile (illustrative)
A 625 kVA (500 kW) set serves a site whose load varies between 80 kW at night and 360 kW at the daytime peak, at a power factor near 0.8.
| Check | Working | Result |
|---|---|---|
| Peak loading | 360 ÷ 500 | 72%: 140 kW of headroom |
| Peak kVA | 360 ÷ 0.8 = 450 kVA, ÷ 625 | 72% of alternator rating |
| Largest motor start | From the load list | Its running kW must fit the 140 kW headroom; its starting kVA is checked against the dip limit with 450 kVA already running |
| Night loading | 80 ÷ 500 | 16%: light-load risk if the set runs long hours at night |
The set is well sized for the peak, but if it runs through long outages at night, it spends hours far below its comfortable band. The remedies are a monthly loaded run or a load-bank test, a smaller second set for night duty, or storage to carry the light hours. See load bank testing and light load and wet stacking.
Do not size only for the peak and ignore the minimum. A set that spends most of its running hours at very light load builds carbon and unburnt fuel in the engine and exhaust, which shortens its life and can stop it delivering full power when the peak arrives.
Loading by duty
| Duty | Typical thinking |
|---|---|
| Emergency standby | Moderate loading, short runs, large headroom for starts |
| Prime power | A band that allows for variable load over long hours, within the maker’s prime rating |
| Continuous | Steady loading at the level the maker recommends |
| Parallel plant | Run only as many sets as keep each in a healthy band |
See prime power and standby power.
Why not run at the limit
- No headroom for motor starts and load steps.
- No margin for derating on hot days or for ageing.
- More engine stress and shorter life.
- No room for growth.
Load profile worksheet
| Item | Value | Example: 250 kVA set (illustrative) |
|---|---|---|
| Set rating (kW and kVA) | 250 kVA; 200 kW | |
| Minimum, average and peak load (kW) | 40, 110 and 150 kW | |
| Hours per year below 30% load | About 60 hours a year at night | |
| Headroom at peak (kW) and largest step | 50 kW at peak; largest step a 30 kW pump | |
| Remedy for light load, if needed | Monthly loaded run, or a second smaller set for night duty |
Reading the calculator’s defaults
The calculator opens with a 250 kVA set rated at 0.8 power factor carrying 150 kW at a load power factor of 0.85:
| Line | Working | Result |
|---|---|---|
| Rated kW | 250 kVA × 0.8 | 200 kW |
| Engine loading | 150 ÷ 200 | 75% |
| Alternator loading | 150 ÷ 0.85 = 176.5 kVA; ÷ 250 | about 71% |
| Spare | 200 − 150; 250 − 176.5 | 50 kW and about 74 kVA |
The higher of the two percentages governs, here the engine at 75%, inside the band most engine makers favour for long runs. The 50 kW of spare power is what must absorb the next motor start or block load.
What light load costs in fuel
Using the typical diesel curve the site’s calculators use, fuel in litres per hour is about 0.04 × rated kW + 0.22 × load kW. For the 200 kW set:
| Load | Fuel | Litres per kWh |
|---|---|---|
| 20 kW (10%) | about 12.4 L/h | about 0.62 |
| 50 kW (25%) | about 19 L/h | about 0.38 |
| 100 kW (50%) | about 30 L/h | about 0.30 |
| 150 kW (75%) | about 41 L/h | about 0.27 |
At a tenth of its rating the set burns more than twice the diesel for every unit of electricity it delivers. The fixed losses of a large engine are paid whatever the load, which is why a small night load on a big set is expensive as well as harmful.
Hours, not only percentages
The question that matters is how many running hours the set spends in each band over a year. A standby set that runs mostly during short daytime outages at 60 to 75% is healthy. The same set running long night outages at 10% spends most of its life in the band that causes wet stacking. The load profile worksheet below asks for hours below 30% for this reason.
Where the light hours are many, the remedies are, in rough order of cost: a planned loaded run, often monthly; a periodic load-bank test at a substantial share of rating, commonly 50 to 75% for an hour or more as the engine maker recommends; a smaller second set for night duty; or a battery that carries the light hours so the set can stop.
Spare capacity in a parallel plant
Three 500 kVA sets, each 400 kW, share a 700 kW load. With all three running, each carries about 58%. If one trips, the remaining two carry 700 kW between them, about 88% each: acceptable for the time it takes to restart or replace the third set, but with little room for any further step. If the load had been 850 kW, losing a set would overload the other two, so the power management system must shed the lowest-priority loads at once. Spare capacity in a redundant plant is therefore checked with one set out, not only with all running.
Spare capacity is not the same as step capability
Fifty kilowatts of spare capacity does not mean the set can take a 50 kW block load cleanly. Turbocharged engines accept only a part of their rating in one step before frequency and voltage dip beyond limits, and a motor started direct on line draws several times its running current. The spare capacity check confirms there is room; the load-step and motor-starting checks confirm the set can reach it smoothly.
Loading after summer derating
Loading is measured against what the set can give on the day, not only its nameplate. If the datasheet derates the 200 kW set by 4% in a hot canopy, it gives about 192 kW, and the 150 kW load becomes about 78% rather than 75. A set already near 80% at nameplate can be pushed past its comfortable band on the hottest afternoons, which is when outages and air-conditioning load are both at their peak.
Reading the controller’s load history
Most modern controllers log kW, kVA, power factor and running hours, and many record time spent in load bands. Downloading that history before deciding on a remedy replaces assumptions with facts: how many hours were really spent below 30%, how high the peaks reached, and whether the light-load hours cluster at night or at weekends. Where the controller keeps no history, a portable logger on the generator output for a few weeks gives the same picture.
One set or two for a wide load range
| Arrangement | At 40 kW night load | At 150 kW day peak |
|---|---|---|
| One 250 kVA set (200 kW) | 20%: light-load risk | 75% |
| Two 125 kVA sets (100 kW each) | One set at 40% | Both at 75% |
Two sets keep the engine loading healthy across the day and give cover during servicing, but add a synchronising panel or a changeover between sets and a second engine to maintain. The choice rests on how wide the load swing is and how many hours the site runs at each end of it.
When to review the loading
Loading drifts as a site changes. A new chiller, a production line moved to another building or tenants who now run their own backup can push the set up towards its limit or down into the light-load band without anyone noticing until an outage. A yearly review of the controller’s history against the worksheet below, and a fresh check whenever a large load is added or removed, keeps the set inside its healthy band and shows early when a second set, a smaller set or a battery would serve the site better.
A short written note with each review, stating the loading found, the hours below 30% and the action taken, builds a history that makes the next decision quicker and gives the maintenance team the evidence to justify a load-bank test or a second set.
Common mistakes
- Sizing for connected load, giving a set that always runs light.
- Checking kW but not kVA.
- No plan for long light-load periods.
- Forgetting the failed-set case in parallel plants.
What to send us
Send the set rating and a load log, or the load list with operating hours. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. The light-load threshold is a common guide; the engine maker’s minimum-load guidance governs.
Questions engineers ask
How much more fuel does a generator use per unit at light load?
On a typical diesel curve, a 200 kW set uses about 0.27 litres per kWh at 75% load but about 0.62 litres per kWh at 10%, more than twice as much for every unit delivered, because the fixed losses of the engine are paid whatever the load.
How is spare capacity checked in a parallel plant?
With one set out. Three 400 kW sets sharing 700 kW run at about 58% each, and if one trips the other two carry about 88% each. A larger load would overload the remaining sets, so the power management system must shed low-priority loads at once.
What loading is best for a diesel generator?
Many makers favour a moderate to high band for long runs, roughly 30 to 80%, avoiding long periods at very light load. The default case, 150 kW on a 200 kW set, sits at 75%. Follow the engine maker guidance for the actual model and duty rating.
What is wet-stacking?
Unburnt fuel and soot that accumulate in the exhaust and engine when a diesel runs for long periods at light load, because the cylinders never reach working temperature. It shows as black dribbling at exhaust joints and smoke on load, and it reduces power and engine life.
How do I deal with light load?
Plan a loaded run, often monthly, or a periodic load-bank test at a substantial share of rating as the engine maker recommends. Where light hours are many, a smaller second set for night duty or a battery that carries those hours lets the large set stop.
Does spare capacity include the failed-unit case?
For redundant plants, yes. The remaining units must carry the load when one is out. Three 400 kW sets on a 700 kW load run at about 88% each with one tripped, which is acceptable for a short time but leaves little room for any further load step.
Figures are illustrative. Follow the manufacturer’s rating definitions and loading guidance.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.