In short. After a changeover or outage, loads should come back in planned steps, not all at once. Each step must stay within what the generator can pick up, and the next step should wait until voltage and frequency recover. The order follows priority: critical and safety loads first, then the loads that protect equipment, then production, then comfort. Restart timers on chillers and motors must be built into the plan.
Who this page is for: For facility managers, plant engineers and commissioning engineers setting up restart after a power cut.
Key facts
- Restore in steps that the generator can accept.
- Wait for voltage and frequency to recover between steps.
- Critical and safety loads first; comfort loads last.
- Large motors in their own steps, with soft starting where possible.
- Allow for restart timers on chillers and motors.
- Restart control power must itself be on UPS.
Worked example: a 500 kVA set (400 kW) (illustrative)
| Step | Time | Loads | Added | Running total |
|---|---|---|---|---|
| 1 | 0 s | UPS input (ramped), safety lighting | 120 kW | 120 kW (30%) |
| 2 | 10 s | Cooling water pumps | 100 kW | 220 kW (55%) |
| 3 | 20 s | Process loads | 80 kW | 300 kW (75%) |
| 4 | after restart timer, about 5 min | Chiller | 40 kW | 340 kW (85%) |
Before staging, all 340 kW restarted together, and the set tripped on underfrequency twice in one year. With four steps the largest step is 120 kW. See load shedding and generator load steps.
Do not let every motor restart the moment power returns. A generator that starts well can still trip when all loads hit it in the same second.
How steps are made
| Method | Notes |
|---|---|
| Timers on feeder breakers or contactors | Simple; fixed delays |
| Plant control system restart sequence | Flexible; needs UPS-backed control power |
| Generator controller load management | Steps based on measured load |
See break classes and black start.
Restart sequence sheet
| Step | Delay | Loads | kW | Total as % of set |
|---|---|---|---|---|
| 1 | ||||
| 2 | ||||
| 3 |
How much a motor start asks of the generator
The size of each restoration step is set less by the running load it adds than by the starting demand of the largest motor in it. A motor starting direct on line draws about six times its running current at a low power factor for several seconds, and the generator sees that as a large, mostly reactive kVA step. The starting method changes the step dramatically.
| Starting method, 30 kW motor | Starting current, as a multiple of running | Starting kVA seen by the generator |
|---|---|---|
| Direct on line | About 6 | about 230 kVA |
| Soft starter, set to limit current | About 3 | about 115 kVA |
| Star-delta | About a third of direct on line | about 77 kVA |
| Variable-speed drive | About 1, ramped | about 38 kVA |
The running kVA of a 30 kW motor at a power factor of about 0.86 and an efficiency of about 0.91 is about 38 kVA, and the table multiplies from there. On a 500 kVA set, a direct-on-line start of this motor is a step of nearly half the set’s rating on its own, while the same motor on a drive is a gentle ramp. Before writing a restart sequence, list every motor that will restart with its starting method and starting kVA; the largest of those figures, not the running total, decides which loads can share a step.
Cold load pickup: why the load after an outage is larger than before it
A building that has been without power for an hour does not come back at the load it had before. Air conditioners, refrigeration, water heaters and pumps controlled by thermostats or level switches have all drifted away from their set points during the outage, and they all call for full output at once when power returns.
In normal running they cycle independently, so only some are on at any moment; after an outage, that diversity is lost. A group of forty air-conditioning units that draws 60 kW in normal running, because only some are running at any time, can draw 100 kW or more for the first minutes after restoration, with every unit starting at once.
The effect grows with the length of the outage and fades over the following half hour or so as units reach their set points and begin cycling again. Restoration plans that add up the normal running load step by step therefore underestimate the real load, sometimes by half. Three remedies help: restore thermostatic loads in several smaller groups with longer delays between them; use the building management system to stagger their restart after a supply return; and, where neither is possible, size the restoration steps on the full connected load of each thermostatic group rather than its normal running figure.
Restoring in the order the loads depend on each other
Restoration order is often written as a list of priorities, critical first and comfort last, but priority alone is not enough. Some loads cannot work until others are running, and restoring them in the wrong order wastes generator capacity or, worse, starts equipment that then trips on its own protection.
| Restore first | Then | Why |
|---|---|---|
| Control power, building management, fire systems | Everything controlled by them | Equipment needs its controls before it can start safely |
| Cooling for the UPS and battery rooms | Recharge of the UPS batteries at full rate | A hot battery room limits charging and shortens battery life |
| Chilled water pumps and cooling towers | Chillers | A chiller started without flow trips on its own protection |
| Ventilation fans | Equipment in the ventilated spaces | Heat or fumes build up before the fans are running |
| Water pressure pumps | Processes and services that use water | Starting them dry or without pressure causes faults |
Draw the dependencies as a simple chart beside the restart sequence sheet, and check each step against it: no load should be restored before the loads it depends on are running and settled.
The timers already inside the equipment
Many loads restart on their own schedule regardless of the restoration plan. Chillers and packaged air conditioners have anti-short-cycle timers that hold them off for a few minutes after power returns, and then all start together when the timers expire. UPS rectifiers walk in over seconds. Variable-speed drives with automatic restart pick up spinning motors when power returns, or wait for a set delay. Lifts return to a home floor. Fire pumps start on pressure. Each of these behaviours is a step on the generator, and none of them appears in a restoration sequence unless someone has looked for it.
The way to find them is to walk the site with the equipment list and ask, of every large item, what it does when power returns and after how long. The answers often reveal several large loads that all restart at the same moment, two or three minutes after the transfer, when their identical factory timers expire together. Staggering those timers, by setting each a different delay, is often the simplest fix available, needing nothing but an afternoon.
Keeping earlier steps on line while later ones start
Each step dips the generator voltage for a moment, and loads already restored feel that dip. Motor contactors hold in only above a certain voltage, and a deep dip from a later motor start can make contactors restored in an earlier step drop out, so a step meant to add load ends with less load than before. Undervoltage releases on breakers, motor protection relays with undervoltage settings, and some drives that trip on a dip all behave the same way.
The remedies sit on both sides. On the generator side, smaller steps and gentler starting methods keep the dips shallower. On the load side, contactors with a hold-in supply from a UPS-backed control circuit, undervoltage releases with a short time delay, and drives set to ride through a brief dip keep the earlier steps on line. The restart test recording shows the problem plainly: a step after which the current on the generator falls instead of rising is a step that knocked something else off.
When the mains returns: the sequence runs twice
With an open-transition changeover, the return from generator to mains is a second, short interruption, and every load that is not on a UPS drops out and has to restart again. If the restart is automatic, the whole sequence runs a second time, now on the mains, which can usually take larger steps but still sees every built-in timer and cold-load effect again, only less severely after a short break.
Plan for it: either repeat the sequence with shorter delays suited to the mains, or use a closed-transition changeover where the supply authority allows it, so that the return to mains causes no break at all and nothing has to restart.
Testing the sequence before it is needed
A restart sequence written on paper is a hypothesis. The only proof is a test on the generator, with the real loads, recorded with an instrument that shows the generator’s frequency and voltage through every step. The record shows at once whether each step was within the set’s ability, whether any step coincided with an unexpected built-in restart, and how long the whole restoration took. Run the test after any significant change to the load, and keep the recording with the sequence sheet; the first real outage after a change in the load is the worst time to discover that the sequence no longer fits.
How long a full restoration should take
The total time from the generator taking load to the last step being restored is the sum of the steps’ delays, and it is worth working out in advance, because it is the time the most deferrable loads spend waiting and the time staff will ask about. With the first step at the moment of transfer, six steps 30 seconds apart finish two and a half minutes later; a plan that then waits five minutes before the thermostatic groups, to let the cold load fall away, takes about seven and a half.
Neither is long, but both are much longer than people expect who are used to the mains returning everything at once. Display the expected time beside the sequence sheet at the generator panel and the building management workstation, so that a restoration in progress is not mistaken for a fault and interrupted by someone switching loads on by hand.
Common mistakes
- Everything restarts together.
- Steps larger than the set accepts.
- Restart timers ignored.
- Sequence not repeated on return to mains.
What to send us
Send your load list with motor sizes and the generator rating. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Values are illustrative; step sizes must suit the set’s data sheet.
Questions engineers ask
Why is the load higher after an outage than before it?
Because thermostatic loads lose their diversity. Air conditioners, refrigeration, water heaters and level-controlled pumps drift from their set points during the outage and all call for full output when power returns. A group of air-conditioning units drawing 60 kW in normal running can draw 100 kW or more for the first minutes after restoration. Restore such loads in smaller groups with longer delays, or size the steps on their full connected load.
In what order should loads be restored after an outage?
In the order the loads depend on each other, not just by priority. Restore control power, building management and fire systems first, then cooling for the UPS and battery rooms, then chilled water pumps before chillers, ventilation before the equipment in ventilated spaces, and water pressure pumps before the services that use water. No load should be restored before the loads it depends on are running and settled.
Why did the generator trip after power came back?
Most often because the combined restart load of motors, transformers, chargers and thermostatic loads arrived in one step and exceeded what the set can accept, so the frequency fell far enough to trip it. Sequencing the loads into steps within the set capability, with recovery time between them, fixes this.
How long should delays between steps be?
Long enough for voltage and frequency to recover fully before the next step, which depends on the set, the step size and the loads. Set the delays by testing on site with a recorder on the generator output, and allow longer delays for groups of thermostatic loads that return with full demand after an outage.
Does a soft starter help?
Yes. A soft starter reduces the starting current and the voltage dip of a motor, so larger motors can be started on the generator and the restart can be completed in fewer steps. A variable speed drive does the same with even lower starting current, but adds harmonic current that the generator must be able to carry.
Should restoration be automatic?
For unattended and critical sites, usually yes, because an automatic sequence restores loads in the same tested order every time, whatever the hour. Provide an operator override for unusual situations, log every step with its time, and test the full sequence on load at least once a year.
This guide gives general principles. Sequences must be tested on the real system.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.