In short. Generator capacity is the largest of three checks. First, can it carry the running load with margin? Second, can it start the largest motor or take the biggest load step within voltage and frequency limits? Third, if redundancy is needed, can the remaining sets carry the critical load with one out? The calculator above handles the running check from a load list. The other two checks need their own tools, and either can set the final size.
Who this page is for: For owners, facility managers and consultants making a first estimate of generator size.
Key facts
- Running check: maximum demand plus growth, at a planned loading.
- Check both engine kW and alternator kVA; the larger governs.
- Transient check: the largest motor start or load step.
- Redundancy check: capacity with one unit out.
- The final size is the largest of the three.
- Round up to a standard rating.
Worked example: the three checks on the default list
| Check | Working | Result |
|---|---|---|
| Running, alternator | 57.3 kVA × 1.15 growth ÷ 0.8 loading | about 82 kVA |
| Running, engine | 49.7 kW × 1.15 ÷ 0.8 rated power factor ÷ 0.8 loading | about 89 kVA |
| Transient: 11 kW lift started direct-on-line | About 15 kVA running × about 6.5 | about 100 kVA at start; holding the dip to 15% with 0.22 transient reactance needs about 125 kVA |
| Redundancy | Not required here | One set |
| Result | Largest check, rounded up | 100 kVA if the lift has a drive or soft starter; 125 kVA if it starts direct-on-line |
The engine kW check, not the alternator kVA, sets the running size here, because the load power factor (0.87) is higher than the 0.8 rated power factor, so the engine reaches its kW limit before the alternator reaches its kVA limit. See motor starting and number of generators.
Do not stop at the running check. A single motor started direct-on-line can need a larger set than all the running load put together.
Things that change the answer
| Factor | Effect |
|---|---|
| High site temperature or altitude | Output derating |
| UPS and drive loads | Harmonics; larger alternator may be needed |
| Large single loads | Load-step limit |
| Long light-load hours | Avoid oversizing |
Capacity sheet
| Check | Required kVA | Example: default load list (illustrative) |
|---|---|---|
| Running, alternator | About 82 kVA | |
| Running, engine | About 89 kVA, which governs | |
| Largest motor or step | About 125 kVA if the 11 kW lift starts direct on line; 100 kVA with a drive | |
| Redundancy | Not required here; one set |
From design kVA to a standard rating
The default list has a maximum demand of 49.7 kW and 57.3 kVA. With 15% growth the design load is about 57.2 kW and 65.9 kVA, and because the load power factor (0.87) is above the 0.8 rated power factor, the engine kW is the tighter limit. Laid against the common ratings near the answer:
| Set | Rated kW at 0.8 | Engine loading at 57.2 kW | Verdict |
|---|---|---|---|
| 82.5 kVA | 66 kW | 87% | Above the 80% target |
| 100 kVA | 80 kW | 71% | Fits the running check |
| 125 kVA | 100 kW | 57% | Needed if the lift starts direct on line |
| 140 kVA | 112 kW | 51% | Oversized for this list |
The calculator’s 100 kVA answer is the running check. The motor-starting check then decides between 100 and 125 kVA, and it is usually cheaper to fit a drive or soft starter on the lift than to buy and run the larger set for its whole life.
Derating for a Hyderabad summer
Ratings are stated at reference conditions, and the air inside a canopy in May is hotter than the street. If a datasheet derates 2% for every 5 °C above 40 °C and the canopy air reaches 50 °C, the 100 kVA set gives about 96 kVA. The design load of 65.9 kVA is then about 69% of what is available, so the choice still holds. On a list that already sits near 80%, the same derating pushes the answer up one rating, which is why the site temperature is part of every capacity check. See the derating calculator.
The block load after a transfer
When the mains fails and the changeover closes, every load that was running arrives on the set together. On the default list that is about 49.7 kW in one step, or 62% of a 100 kVA set’s 80 kW, which is near the one-step limit many turbocharged engines publish. Staggering the restart with timers in the AMF or changeover panel splits it into easy steps:
| Step | Loads | kW added | Percent of 80 kW |
|---|---|---|---|
| 1, at transfer | Lighting and sockets, air conditioning | about 28 kW | 35% |
| 2, after a few seconds | Two pump motors | 15 kW | 19% |
| 3, after a few more seconds | Lift | about 6.6 kW running | 8% |
Each step is well inside the engine’s acceptance, and voltage and frequency recover before the next one arrives. See the load step screening tool.
The redundancy check, worked
Suppose the same list served a clinic, where the whole load must survive one set being out. Two routes meet the same requirement:
| Arrangement | Installed | With one set out | Loading |
|---|---|---|---|
| 2 × 100 kVA (N+1) | 200 kVA | One set, 80 kW | 57.2 kW = 71% |
| 3 × 50 kVA (N+1) | 150 kVA | Two sets in parallel, 80 kW | 57.2 kW = 71% each |
Three smaller sets install less capacity for the same cover, but need synchronising panels and load sharing, and the lift start must be checked against the two sets that remain online. Two larger sets are simpler and need only a changeover between them. The choice is made on cost, space and how the site is operated. See the N+1 capacity calculator.
Why bigger is not safer
Choosing 160 kVA “to be safe” on this list leaves the engine at about a third of its 128 kW in the day and under 10% on a 10 kW night load. Diesel engines run that lightly for long periods do not reach working temperature, so unburnt fuel and carbon build up in the exhaust, known as wet stacking. The right size carries the design load at a healthy loading, starts the largest motor and survives the summer derating, with nothing extra.
When the alternator governs instead
The default list has a good power factor, so the engine sets the size. A site dominated by motors behaves differently. Take 60 kW of maximum demand at 0.7 power factor, with the same 15% growth and 80% loading:
| Check | Working | Result |
|---|---|---|
| Alternator | 60 ÷ 0.7 = 85.7 kVA; × 1.15 ÷ 0.8 | about 123 kVA |
| Engine | 60 × 1.15 ÷ 0.8 rated power factor ÷ 0.8 | about 108 kVA |
| Result | Larger check, next common rating | 125 kVA |
Here the alternator reaches its kVA limit first, so correcting the power factor or choosing a set with a larger alternator are both valid answers. The calculator runs both checks for every list and reports whichever governs.
Drives and UPS on the list
Variable-speed drives and UPS rectifiers draw distorted current, which heats the alternator and distorts the voltage other equipment sees. Where they form a large part of the load, often taken as more than about a third, the alternator is chosen a size larger than the kW alone requires, or a permanent magnet generator excitation system is specified so the voltage regulator is not disturbed. Drives with input filters or active front ends reduce the problem at its source.
What a capacity calculator cannot see
- Unbalance: heavy single-phase loads on one phase can overload that phase while the three-phase total looks comfortable.
- Regenerative lifts: a descending loaded lift can push energy back into a lightly loaded set and trip it.
- Future large motors: a planned chiller or pump can change the motor-starting check more than any growth allowance.
- Duty: a prime-power site with no grid is sized on the prime rating, not the standby rating.
Each of these is checked against the actual site before the rating is fixed, and the decision, with the figures behind it, is written into the capacity sheet below so the next person can see why the set is the size it is.
Different sites, different governing checks
| Site | Check that usually governs | Why |
|---|---|---|
| Office or apartment block | Engine kW on running load | Good power factor; lifts usually on drives |
| Workshop with many motors | Alternator kVA | Low power factor at part load |
| Pumping station | Largest motor start | One large pump dominates the list |
| Hospital or data room | Redundancy | The critical load must survive one set out |
| Remote site with no grid | Prime rating and light-load hours | Continuous duty and a large day to night swing |
Knowing which check is likely to govern tells you where to spend effort in the survey: the motor list and starters at a pumping station, the phase readings and power factor in a workshop, and the critical load register at a hospital.
Before ordering
- The load list is measured or confirmed, not copied from nameplates.
- Running, starting and redundancy checks are all recorded, with the one that governs marked.
- Site temperature and altitude derating are applied from the maker’s datasheet.
- The restart sequence after transfer is agreed and set in the panel.
Reviewing the size as the site changes
A capacity check is a snapshot. When a large motor, an air-conditioning plant or a new production line is added, the load list is updated and all three checks are run again before the new equipment is connected to the generator-backed board. Sites that skip this step find out at the next outage, when the set that was right two years ago trips on a load it was never sized for.
Common mistakes
- Running check only.
- kVA checked but not engine kW.
- No growth allowance.
- Derating ignored.
What to send us
Send your load list with motor sizes and starting methods. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. The worked example uses the calculator’s default list; final sizing needs a full check.
Questions engineers ask
Why does the restart after a mains failure matter for generator size?
Because every running load arrives on the set together when the changeover closes. On the default list that is about 62% of a 100 kVA set in one step. Timers in the AMF or changeover panel that bring loads back in stages keep each step small and avoid a larger set.
Is one larger set or several smaller sets better for N+1?
Both can meet N+1. Two 100 kVA sets give simple changeover between them; three 50 kVA sets install less capacity for the same cover but need synchronising, load sharing and a motor-start check on the sets left online. Cost, space and operation decide. Check light-load running too.
What target loading should I use?
Many designs aim for about 70 to 80% of rating at the design load, which leaves room for starting, summer derating and growth. On the default list a 100 kVA set carries the 57.2 kW design load at about 71% of its 80 kW engine rating.
Do I size for the largest motor start?
You must check it. On the default list a 100 kVA set carries the running load, but an 11 kW lift started direct on line needs about 125 kVA to hold the voltage dip near 15%. A drive or soft starter on the lift keeps the 100 kVA answer.
How does redundancy change the size?
It adds units so that the critical load is carried with one unit out. For the default list, two 100 kVA sets or three 50 kVA sets both carry 57.2 kW with one set out of service at about 71% loading, with different costs and controls.
Is one big generator or several better?
It depends on redundancy needs, the load profile and space. Several units add resilience and keep loading healthy at night, but need synchronising and load sharing. One unit is simpler, yet runs very lightly when the load falls and gives no cover during servicing or a breakdown.
Figures are illustrative. This is a screening method, not a final design.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.