In short. This tool turns a load list into an agreed priority order. For every load, ask what happens if it loses power for a second, a minute and an hour; combine the consequence with the tolerable gap to give a tier; and let each support load inherit the tier of what depends on it. The resulting single page decides which loads sit on UPS, which on the generator, the restart order and the shed order, so it is worth getting operations and safety owners to sign it.
Who this page is for: For facility managers, operations heads and engineers turning a load list into UPS, generator, restart and shedding decisions.
Key facts
- Tier = consequence of loss combined with tolerable gap.
- Three or four tiers are usually enough; more becomes hard to maintain.
- Support loads (cooling, ventilation, pumps, control power) inherit the tier of the load they serve.
- Tier totals size the UPS, the generator and the shedding scheme.
- The owner of the process decides the consequence; engineering turns it into design.
- Review the tiers when operations change.
The scoring matrix
| Consequence of loss | Tolerable gap | Tier | Supply |
|---|---|---|---|
| Safety or legal duty | Seconds or less | 1 | Never shed; fastest support |
| Data loss or major process damage | None to seconds | 1 | UPS, then generator |
| Serious production or service loss | Minutes | 2 | Generator, staged restart |
| Moderate, deferrable loss | Hours | 3 | Shed, restore later |
| Comfort or convenience | Hours or more | 4 | Shed first |
Worked example: a pharmaceutical store and packing unit (illustrative)
| Load | kW | If lost for an hour | Tier |
|---|---|---|---|
| Cold rooms and their motors | 90 | Stock spoils | 2 (cold rooms hold temperature for minutes) |
| Temperature monitoring and records | 3 | Regulatory gap in records | 1, on UPS |
| Packing line | 120 | Lost production, recoverable | 3 |
| Fire alarm, emergency lighting, security | 12 | Safety risk | 1 |
| Office air conditioning | 60 | Discomfort | 4 |
| Cold-room condenser fans (support load) | 8 | Refrigeration units trip on high pressure | 2, inherited |
Tier 1 totals about 15 kW (a small UPS), tiers 1 and 2 about 113 kW (the generator’s core load), and the packing line and offices are shed or restored when capacity allows. The condenser fans were first listed as tier 4 “fans”; without the inheritance rule, the cold rooms would have tripped on their first outage. See load classification.
Do not classify loads by their names alone. Trace what each critical load depends on, lift those support loads to the same tier, and have the process owner confirm the result.
Method
- Start from the load list. See load list.
- Define consequence categories: safety, regulatory, process damage, revenue, comfort.
- Set each load’s tolerable gap.
- Assign the tier and apply inheritance.
- Sum kW by tier for UPS and generator sizing.
- Set the restart and shed order. See load shedding.
- Get sign-off and set a review date.
Priority register
The signed register for the same pharmaceutical formulation block. The worked example above is a pharmaceutical store and packing unit whose inheritance rule rescues a set of condenser fans; this register covers a formulation block with clean rooms, and its inherited load is not a fan but the compressed-air plant — a machine the site’s own load list had already classified as a utility.
| Load | kW | Consequence | Tolerable gap | Tier | Depends on / supports |
|---|---|---|---|---|---|
| Environmental monitoring and batch records | 8, behind UPS-01 | A gap in the batch record. The batch cannot be released without an explanation | None | 1 | Supported by UPS-01 |
| UPS-01 input, 120 kVA unit | 100 | Everything behind it falls | None | 1 | Supports monitoring, records and the clean room controls |
| L-01 clean room lighting and small power | 70 | Operators stop work in a room with a batch open in it | 10 s | 1 | Supports every room in production |
| AHU-01 to AHU-06 air handling | 132 | Pressure cascade lost. The rooms need requalification before the batch continues | 30 s | 1 | Depends on chilled water and on instrument air |
| AC-01 compressed-air plant | 75 | Instrument air lost. The AHU dampers and the chilled-water control valves fail closed, so the rooms lose pressure within about four minutes with the fans still turning | 4 min | 1, inherited | Supports AHU-01 to AHU-06 and the chilled water loop |
| CH-01 chiller | 160 | Temperature and humidity drift out of the room limits | 15 min | 2 | Supports the air handling |
| P-01, P-02 chilled water pumps | 45 | Same as the chiller, immediately | 15 min | 2, inherited | Supports CH-01 |
| PR-01 granulation and coating | 90 | Lost production, recoverable. No product at risk once the line is stopped cleanly | 30 min | 3 | — |
| PW-01 purified water system | 30 | Cleaning and changeover delayed | Hours | 3 | — |
| W-01 workshop, canteen and external | 55 | Discomfort | A shift | 4 | — |
| Tier totals | 757 | — | — | Tier 1: 377. Tier 2: 205. Tier 3: 120. Tier 4: 55 | Agrees with the load list’s running total |
The inheritance rule moved 75 kW from tier 3 to tier 1 and nobody on the site had seen it coming. The load list, written first and perfectly correctly, had three loads marked critical — the air handling, the clean room lighting and the UPS — totalling 302 kW. Tracing what those three depend on adds the compressed-air plant, because every AHU damper and every chilled-water control valve on this site is pneumatic and fails closed. Lose instrument air and the rooms lose their pressure cascade in about four minutes while the fans are still running and every electrical indication is normal. Tier 1 is 377 kW, not 302.
That single line changes four other documents. The restart sequence has to bring the motor back before the air receiver empties rather than at its old place in the order. The shedding scheme can no longer treat it as a tier-3 utility. The black-start assessment has to ask where instrument air comes from when nothing is running. And the air receiver itself, which nobody had ever sized for anything but pressure stability, becomes the thing that buys the clean rooms their four minutes.
The second inheritance, in row seven, is the ordinary kind and worth noting for contrast. The chilled water pumps are tier 2 because the chiller is tier 2, and that is obvious the moment anybody asks. The motor is the hard case precisely because the dependency runs through a different utility: air, not water, and air is not on the electrical single-line diagram at all. A register built only from the electrical drawing cannot find it.
The tier column adds to 757 kW, which is the same figure the load list reaches for its nine running loads by a completely different route — nameplates and duty rather than consequence and dependency. Two documents, two methods, one number. When they disagree it is almost always because a load has been classified without being counted, or counted without being classified, and the reconciliation is quicker than finding the error later.
The fourth column is where engineering stops and the business starts. Thirty seconds against the air handling and fifteen minutes against the chiller are not electrical quantities; they came from the quality department, and they are the reason the dip limit on this site is 10% rather than the 15 to 20% general guidance allows. Four minutes against the motor came from a measurement — the receiver was timed with the motor isolated and the dampers watched until the first room dropped below its differential. An engineer who fills in that column alone has produced an opinion.
One warning the register carries on its face. Tier 1 at 377 kW is more than half of what one 750 kVA set can carry, and the UPS behind row one covers monitoring and controls only, not the fans. The register does not say the site is well protected; it says precisely what would survive, for how long, and what each of those answers depends on. That is a different and more useful thing than a column of labels.
Agreeing tiers in a short workshop
Tiers are best agreed with the people who run the site, not set by the electrical designer alone. A short workshop with operations, safety, IT and facilities staff goes through the load list, asks what happens if each load stops for a minute, an hour and a day, and records the agreed tier and the reason. Disagreements are settled by the consequences, written down, not by who argues hardest.
Linking tiers to sources
| Tier | Typical source arrangement |
|---|---|
| No break allowed | UPS backed by generator |
| Short break acceptable | Generator, restored first |
| Longer break acceptable | Generator, restored in later stages |
| Can wait for mains | Shed on generator |
Worked example: settling a disputed load (illustrative)
At a factory, the canteen manager wants the cold room on the top tier, while engineering sees it as deferrable. The workshop asks how long the cold room holds temperature with doors closed. The answer is about four hours. The load is placed in a later restoration stage, with a rule that it returns within two hours, and a temperature alarm is added. Both sides accept the result because it rests on a measured fact.
When to review the register
Review after any new equipment, change of use, incident where a load was shed unexpectedly, or at least yearly. Each review records what changed and why, so the register stays a reliable basis for generator, UPS and shedding design.
A copy of the current register is kept with the generator and UPS records, so anyone testing the system can see which loads should come back first.
Common mistakes
- Too many tiers.
- Support loads left in a low tier.
- No owner sign-off.
- Never revisiting the tiers.
What to send us
Send your load list and how long each area can be without power. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. The example is illustrative; each site’s tiers follow its own risks and regulations.
Questions engineers ask
How should load criticality tiers be agreed?
In a short workshop with operations, safety, IT and facilities staff, going through the load list and asking what happens if each load stops for a minute, an hour and a day. The agreed tier and reason are recorded, and disputes are settled by written consequences.
Which power source suits each criticality tier?
Loads allowing no break go on UPS backed by generator, loads accepting a short break are restored first on generator, loads accepting a longer break come back in later stages, and loads that can wait for mains are shed while the site runs on generator.
How can a disputed load priority be settled?
With a measured fact. In the illustrative factory, a cold room holding temperature for about four hours with doors closed was placed in a later restoration stage with a rule to return within two hours and a temperature alarm, which both sides accepted because the decision rested on evidence.
When should a load priority register be reviewed?
After new equipment, a change of use, any incident where a load was shed unexpectedly, and at least yearly. Each review records what changed and why, and a current copy is kept with the generator and UPS records for anyone testing the system, so test results can be checked against the agreed order.
Who decides the tier?
The process or facility owner with safety and engineering input. Engineering explains what each tier costs to protect and what failures it covers, safety confirms the life-safety loads, and the owner signs the final list, so that the classification carries authority when budgets and priorities are set.
How many tiers should I use?
Three or four is usually enough. More becomes hard to maintain. A common set is no-break loads on UPS, short-break loads on generator, deferrable loads that can wait, and loads shed first during a shortfall. Each tier has a clear definition and example loads, so everyone classifies the same way.
Can tiers change?
Yes. Revisit when operations change. New equipment, a changed process or a new use of a room can move a load to a higher or lower tier. Review the list at least yearly with the operations owner, and update the supply arrangements and shedding scheme to match.
What about loads of unknown criticality?
Ask operations. Treat unknown loads cautiously until classified. Until a load is classified, treat it as more critical rather than less, so it is not shed or left without supply by mistake. Trace each unknown circuit to its equipment and owner, and record the agreed tier in the load register.
This guide gives general principles. Classification must be agreed for your facility.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.