Generator Rental Size and Fuel Calculator

How to plan a rental generator: sizing from the real load, runtime and fuel, connection method, cabling, protection and what to prepare so temporary power arrives and works first time.

In short. Planning a rental generator answers four questions before the set arrives: how much power, for how long, how it connects, and who looks after fuel and support. Size from the real running load and the largest motor start, and pick the next standard rental size or two smaller sets for resilience. Work out the diesel for the whole hire from the load and the hours. Then prepare a safe connection through a changeover and agree fuel, attendance and terms in writing.

Who this page is for: For plant managers, event organisers, contractors and facility teams planning a hire for a shutdown, event, construction job or emergency.

Key facts

  • Size from the running load and the largest motor start, not from the equipment nameplates.
  • Plan running at about 70 to 80% of the set’s rating.
  • Fuel for the hire = litres per hour at your load × running hours.
  • Connect only through a changeover or a prepared connection point; never back-feed the grid.
  • For critical loads, two smaller sets give resilience that one large set cannot.
  • Agree fuel, operator, cables and transport in writing before delivery.

The six planning steps

StepDecideTypical output
1. DutyPurpose, dates, hours per day, steady or variable loadA clear running profile
2. SizeRunning kW, largest motor and starter, power factor, deratingA standard rental rating, or two sets
3. FuelLitres per hour at the expected load, total hoursTotal litres and a refuelling plan
4. ConnectionWhere and how the set connects to the siteChangeover, cable route, earthing
5. Site readinessSpace, access, ventilation, exhaust, noise, permissionsA position agreed with the site
6. SupportOperator, alarm monitoring, refuelling responsibilityWritten responsibilities for the hire

Step 2 in practice: sizing a rental set

Set size (kVA) ≈ running kW ÷ 0.75 ÷ 0.8, then checked against the largest motor start

Rental fleets come in standard sizes, so round up to the next one. As a rough guide a set starts a direct-on-line motor of about 10% of its kVA in kW, and a star-delta motor of about 30%. If one motor forces a much larger set, a soft starter or star-delta starter is usually cheaper than the extra kVA for the whole hire. See the generator size chart.

Step 3 in practice: fuel for the hire

Total litres = litres per hour at the expected load × hours per day × days

Typical consumption at 75% load is about 21 L/h for a 125 kVA set, 42 L/h for 250 kVA and 81 L/h for 500 kVA. The full table is in the DG fuel consumption chart. A 250 kVA set running 10 hours a day for six days at 75% load needs about 42 × 60 ≈ 2520 litres. That is more than a typical base tank holds, so plan a bulk tank or daily refuelling.

Worked example: a factory shutdown (illustrative)

A factory needs 180 kW running for eight days, two shifts of eight hours, while its transformer is replaced. The largest motor is a 45 kW pump on a star-delta starter.

StepWorkingResult
Size from running load180 ÷ 0.75 ÷ 0.8 = 300 kVA320 kVA set
Motor checkA 320 kVA set starts about 96 kW on star-delta45 kW passes
Load on the set180 kW of 256 kWAbout 70%
Fuel rate180 kW × about 0.27 L/kWhAbout 49 L/h
Hours16 h × 8 days128 h
Fuel for the hire49 × 128About 6300 litres: bulk tank plus scheduled deliveries
ConnectionChangeover panel at the main LV boardPrepared before delivery

Everything that could stop the job on day one, such as size, fuel, connection and position, is settled before the set arrives.

Step 4 in practice: connecting safely

MethodNotes
Prepared connection point or inletFastest and safest; install in advance for recurring hires
Rental changeover or ATS panelPrevents back-feeding the grid; suitable for most hires
Temporary cables to a distribution boardNeeds isolation, correctly rated cables and protection
Parallel with the gridOnly with the utility’s approval and synchronising equipment

Never connect a rental generator to a building through a plug or a direct link without a changeover. Back-feeding the grid can kill people working on the lines. Use a changeover, earth the set and its neutral correctly, and fit earth-fault or RCD protection.

Agreeing the hire

With Reddy Generators the hire rate covers the generator. Transport is at actual cost and in the customer’s scope, and cables and an operator are charged extra if you need them. Fuel is on the customer’s account, and service during the hire is agreed for each job. See generator on rent in Hyderabad and the rental rates guide.

Rental planning worksheet

ItemValue Example: factory shutdown on this page (illustrative)
Purpose, dates and hours per day  Transformer replacement; 8 days; two 8-hour shifts
Running load (kW) and largest motor with starter  180 kW; 45 kW pump on star-delta
Set size chosen (kVA), one set or two  320 kVA, one set
Fuel rate (L/h) and total litres  About 49 L/h; about 6300 litres
Connection method and cable route length  Changeover panel at the main LV board; route length measured on site
Position, access, exhaust direction and permissions  Agreed with the site before delivery; exhaust away from air intakes
Who provides fuel, operator and monitoring  Fuel on the customer’s account; operator extra if required; daily log

Reading the calculator’s default answer

The calculator opens with a site whose peak is 120 kW at 0.85 power factor, hired for 30 days at 12 hours a day, with an average load of 60% of the peak. Each line of its answer comes from a simple step:

StepWorkingResult
Load kVA at 80% loading120 ÷ 0.85 ÷ 0.8176.5 kVA
Engine kW at 80% loading120 ÷ 0.8 rated power factor ÷ 0.8187.5 kVA, which governs
Rental setNext common rating200 kVA (160 kW)
Average load120 kW × 60%72 kW
Fuel rate0.04 × 160 + 0.22 × 72about 22.2 L/h
Fuel per day and for the hire22.2 × 12 h; × 30 daysabout 267 litres; about 8006 litres
Hours between refuelling400 litres × 90% ÷ 22.2about 16.2 hours

Sixteen hours of running from a 400-litre base tank means a top-up roughly every working day and a half. For a month-long hire that settles the fuel plan: a bunded day tank or scheduled deliveries, not a can at a time.

Cables for the hire

A 200 kVA set at 415 V gives about 278 A at full rating. Screened with the cable calculator at a 0.8 grouping and installation factor, 150 mm² copper is the minimum for a single run, with a voltage drop of about 1.15% over 60 metres. Its derated rating, about 284 A, leaves almost no margin, so 185 mm² is the practical choice, with about 0.99% drop. The route, the connection lugs and the protection at both ends are agreed before the hire starts, and cables are charged extra if the customer needs them supplied.

One set or two for a month-long hire

A single 200 kVA set carrying a 20 kW night and weekend load runs at 12.5% of its kW rating for long periods, which leads to wet stacking. Two 100 kVA sets give the same 200 kVA for the daytime peak at 75% loading, and one can run alone at night at 25%, with the other available as cover for servicing. The second set adds a connection and either a changeover between sets or a paralleling panel, so the choice depends on how much the load varies and how critical the supply is.

Fuel during the hire

Fuel is on the customer’s account. The plan for a long hire covers who orders and receives diesel, where it is stored, and how levels are recorded. A daily log of running hours and litres added, checked against the expected rate of about 22 L/h for the default case, shows quickly if fuel is going somewhere other than the engine. See fuel theft and refuelling control. Every set is load-bank tested before it is supplied for hire.

Before the set arrives: site checklist

  • A level, firm position the delivery vehicle can reach, clear of drains and away from building air intakes.
  • The changeover or connection point installed, labelled and tested, with the incoming supply isolated and locked during connection.
  • An earth electrode or earthing point for the set and its neutral, tested before energising.
  • A fuel delivery route and storage position agreed with the site’s safety officer.
  • Contact names for the site, the electrician and the fuel supplier, written on the handover sheet.

At the end of the hire

The set is stopped, isolated and disconnected only after the permanent supply is restored and checked, and the changeover is returned to its normal position. Final running hours and fuel level are recorded on the handover sheet with any alarms seen during the hire, so the bill, the fuel account and the condition of the set are all settled from the same record.

Daily checks during the hire

  • Fuel level, litres added and running hours written in the log.
  • Oil level, coolant level and any leaks under the set.
  • Load on the panel meter compared with the plan, so an unplanned addition is noticed.
  • Alarms or shutdowns since the last check, with their cause.

Five minutes a day keeps a month-long hire uneventful. On longer hires the set is serviced on the same standard as a permanent set: oil and filters every 250 to 500 running hours or six months, whichever comes first.

Common mistakes

  • Sizing from equipment nameplates instead of the real load.
  • No fuel plan beyond the base tank.
  • Undersized or unprotected temporary cables.
  • No changeover arrangement.
  • Leaving the position and permissions until the set arrives.

What to send us

Send the load or equipment list, the dates and hours, the site location and photographs of the connection point. WhatsApp 98852 01608 or use the enquiry form. Get price for your hire.

Evidence note. Fuel and sizing figures are typical values for illustration. Each hire is sized and confirmed for the actual site.

Questions engineers ask

How often must a rental generator be refuelled?

Divide the usable fuel in the tank by the litres per hour at your load. For the default case, 400 litres at 90% usable and about 22.2 L/h give about 16 hours of running, so a site running 12 hours a day tops up roughly every day and a half.

What cable does a 200 kVA rental generator need?

About 278 A flows at full rating on 415 V. Screening at a 0.8 installation factor gives 150 mm² copper as the minimum for a single run, with little margin, so 185 mm² is the practical choice for routes up to about 60 metres. The maker tables confirm the final size.

How do I choose rental generator size?

From the running load, the largest motor start and the power factor, at about 80% loading, then the next standard size. For a 120 kW peak at 0.85 the engine check gives 187.5 kVA, so a 200 kVA set, with the motor start checked separately.

Can a rental generator connect to my building directly?

Only through a proper changeover or an approved connection arrangement, with the set and neutral earthed and earth fault protection fitted. A direct link without a changeover can back-feed the DISCOM network and endanger people working on the lines. The connection point is prepared and tested before the set arrives.

Who supplies fuel?

Fuel is on the customer account. Before the hire starts, agree who orders and receives the diesel, where it is stored, how often the set is topped up and who records the level, with a daily log of hours and litres so any unusual use shows at once.

Do I need two smaller units?

For critical use, or where the load falls a long way at night, two units give redundancy and keep each set loaded. Two 100 kVA sets cover a 120 kW peak at 75%, and one runs alone at night, while a single 200 kVA set would run at about 12%.

Figures are illustrative. Rental terms and technical arrangements are confirmed per project.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.