In short. Planning a rental generator answers four questions before the set arrives: how much power, for how long, how it connects, and who looks after fuel and support. Size from the real running load and the largest motor start, and pick the next standard rental size or two smaller sets for resilience. Work out the diesel for the whole hire from the load and the hours. Then prepare a safe connection through a changeover and agree fuel, attendance and terms in writing.
Who this page is for: For plant managers, event organisers, contractors and facility teams planning a hire for a shutdown, event, construction job or emergency.
Key facts
- Size from the running load and the largest motor start, not from the equipment nameplates.
- Plan running at about 70 to 80% of the set’s rating.
- Fuel for the hire = litres per hour at your load × running hours.
- Connect only through a changeover or a prepared connection point; never back-feed the grid.
- For critical loads, two smaller sets give resilience that one large set cannot.
- Agree fuel, operator, cables and transport in writing before delivery.
The six planning steps
| Step | Decide | Typical output |
|---|---|---|
| 1. Duty | Purpose, dates, hours per day, steady or variable load | A clear running profile |
| 2. Size | Running kW, largest motor and starter, power factor, derating | A standard rental rating, or two sets |
| 3. Fuel | Litres per hour at the expected load, total hours | Total litres and a refuelling plan |
| 4. Connection | Where and how the set connects to the site | Changeover, cable route, earthing |
| 5. Site readiness | Space, access, ventilation, exhaust, noise, permissions | A position agreed with the site |
| 6. Support | Operator, alarm monitoring, refuelling responsibility | Written responsibilities for the hire |
Step 2 in practice: sizing a rental set
Rental fleets come in standard sizes, so round up to the next one. As a rough guide a set starts a direct-on-line motor of about 10% of its kVA in kW, and a star-delta motor of about 30%. If one motor forces a much larger set, a soft starter or star-delta starter is usually cheaper than the extra kVA for the whole hire. See the generator size chart.
Step 3 in practice: fuel for the hire
Typical consumption at 75% load is about 21 L/h for a 125 kVA set, 42 L/h for 250 kVA and 81 L/h for 500 kVA. The full table is in the DG fuel consumption chart. A 250 kVA set running 10 hours a day for six days at 75% load needs about 42 × 60 ≈ 2520 litres. That is more than a typical base tank holds, so plan a bulk tank or daily refuelling.
Worked example: a factory shutdown (illustrative)
A factory needs 180 kW running for eight days, two shifts of eight hours, while its transformer is replaced. The largest motor is a 45 kW pump on a star-delta starter.
| Step | Working | Result |
|---|---|---|
| Size from running load | 180 ÷ 0.75 ÷ 0.8 = 300 kVA | 320 kVA set |
| Motor check | A 320 kVA set starts about 96 kW on star-delta | 45 kW passes |
| Load on the set | 180 kW of 256 kW | About 70% |
| Fuel rate | 180 kW × about 0.27 L/kWh | About 49 L/h |
| Hours | 16 h × 8 days | 128 h |
| Fuel for the hire | 49 × 128 | About 6300 litres: bulk tank plus scheduled deliveries |
| Connection | Changeover panel at the main LV board | Prepared before delivery |
Everything that could stop the job on day one, such as size, fuel, connection and position, is settled before the set arrives.
Step 4 in practice: connecting safely
| Method | Notes |
|---|---|
| Prepared connection point or inlet | Fastest and safest; install in advance for recurring hires |
| Rental changeover or ATS panel | Prevents back-feeding the grid; suitable for most hires |
| Temporary cables to a distribution board | Needs isolation, correctly rated cables and protection |
| Parallel with the grid | Only with the utility’s approval and synchronising equipment |
Never connect a rental generator to a building through a plug or a direct link without a changeover. Back-feeding the grid can kill people working on the lines. Use a changeover, earth the set and its neutral correctly, and fit earth-fault or RCD protection.
Agreeing the hire
With Reddy Generators the hire rate covers the generator. Transport is at actual cost and in the customer’s scope, and cables and an operator are charged extra if you need them. Fuel is on the customer’s account, and service during the hire is agreed for each job. See generator on rent in Hyderabad and the rental rates guide.
Rental planning worksheet
| Item | Value | Example: factory shutdown on this page (illustrative) |
|---|---|---|
| Purpose, dates and hours per day | Transformer replacement; 8 days; two 8-hour shifts | |
| Running load (kW) and largest motor with starter | 180 kW; 45 kW pump on star-delta | |
| Set size chosen (kVA), one set or two | 320 kVA, one set | |
| Fuel rate (L/h) and total litres | About 49 L/h; about 6300 litres | |
| Connection method and cable route length | Changeover panel at the main LV board; route length measured on site | |
| Position, access, exhaust direction and permissions | Agreed with the site before delivery; exhaust away from air intakes | |
| Who provides fuel, operator and monitoring | Fuel on the customer’s account; operator extra if required; daily log |
Reading the calculator’s default answer
The calculator opens with a site whose peak is 120 kW at 0.85 power factor, hired for 30 days at 12 hours a day, with an average load of 60% of the peak. Each line of its answer comes from a simple step:
| Step | Working | Result |
|---|---|---|
| Load kVA at 80% loading | 120 ÷ 0.85 ÷ 0.8 | 176.5 kVA |
| Engine kW at 80% loading | 120 ÷ 0.8 rated power factor ÷ 0.8 | 187.5 kVA, which governs |
| Rental set | Next common rating | 200 kVA (160 kW) |
| Average load | 120 kW × 60% | 72 kW |
| Fuel rate | 0.04 × 160 + 0.22 × 72 | about 22.2 L/h |
| Fuel per day and for the hire | 22.2 × 12 h; × 30 days | about 267 litres; about 8006 litres |
| Hours between refuelling | 400 litres × 90% ÷ 22.2 | about 16.2 hours |
Sixteen hours of running from a 400-litre base tank means a top-up roughly every working day and a half. For a month-long hire that settles the fuel plan: a bunded day tank or scheduled deliveries, not a can at a time.
Cables for the hire
A 200 kVA set at 415 V gives about 278 A at full rating. Screened with the cable calculator at a 0.8 grouping and installation factor, 150 mm² copper is the minimum for a single run, with a voltage drop of about 1.15% over 60 metres. Its derated rating, about 284 A, leaves almost no margin, so 185 mm² is the practical choice, with about 0.99% drop. The route, the connection lugs and the protection at both ends are agreed before the hire starts, and cables are charged extra if the customer needs them supplied.
One set or two for a month-long hire
A single 200 kVA set carrying a 20 kW night and weekend load runs at 12.5% of its kW rating for long periods, which leads to wet stacking. Two 100 kVA sets give the same 200 kVA for the daytime peak at 75% loading, and one can run alone at night at 25%, with the other available as cover for servicing. The second set adds a connection and either a changeover between sets or a paralleling panel, so the choice depends on how much the load varies and how critical the supply is.
Fuel during the hire
Fuel is on the customer’s account. The plan for a long hire covers who orders and receives diesel, where it is stored, and how levels are recorded. A daily log of running hours and litres added, checked against the expected rate of about 22 L/h for the default case, shows quickly if fuel is going somewhere other than the engine. See fuel theft and refuelling control. Every set is load-bank tested before it is supplied for hire.
Before the set arrives: site checklist
- A level, firm position the delivery vehicle can reach, clear of drains and away from building air intakes.
- The changeover or connection point installed, labelled and tested, with the incoming supply isolated and locked during connection.
- An earth electrode or earthing point for the set and its neutral, tested before energising.
- A fuel delivery route and storage position agreed with the site’s safety officer.
- Contact names for the site, the electrician and the fuel supplier, written on the handover sheet.
At the end of the hire
The set is stopped, isolated and disconnected only after the permanent supply is restored and checked, and the changeover is returned to its normal position. Final running hours and fuel level are recorded on the handover sheet with any alarms seen during the hire, so the bill, the fuel account and the condition of the set are all settled from the same record.
Daily checks during the hire
- Fuel level, litres added and running hours written in the log.
- Oil level, coolant level and any leaks under the set.
- Load on the panel meter compared with the plan, so an unplanned addition is noticed.
- Alarms or shutdowns since the last check, with their cause.
Five minutes a day keeps a month-long hire uneventful. On longer hires the set is serviced on the same standard as a permanent set: oil and filters every 250 to 500 running hours or six months, whichever comes first.
Common mistakes
- Sizing from equipment nameplates instead of the real load.
- No fuel plan beyond the base tank.
- Undersized or unprotected temporary cables.
- No changeover arrangement.
- Leaving the position and permissions until the set arrives.
What to send us
Send the load or equipment list, the dates and hours, the site location and photographs of the connection point. WhatsApp 98852 01608 or use the enquiry form. Get price for your hire.
Evidence note. Fuel and sizing figures are typical values for illustration. Each hire is sized and confirmed for the actual site.
Questions engineers ask
How often must a rental generator be refuelled?
Divide the usable fuel in the tank by the litres per hour at your load. For the default case, 400 litres at 90% usable and about 22.2 L/h give about 16 hours of running, so a site running 12 hours a day tops up roughly every day and a half.
What cable does a 200 kVA rental generator need?
About 278 A flows at full rating on 415 V. Screening at a 0.8 installation factor gives 150 mm² copper as the minimum for a single run, with little margin, so 185 mm² is the practical choice for routes up to about 60 metres. The maker tables confirm the final size.
How do I choose rental generator size?
From the running load, the largest motor start and the power factor, at about 80% loading, then the next standard size. For a 120 kW peak at 0.85 the engine check gives 187.5 kVA, so a 200 kVA set, with the motor start checked separately.
Can a rental generator connect to my building directly?
Only through a proper changeover or an approved connection arrangement, with the set and neutral earthed and earth fault protection fitted. A direct link without a changeover can back-feed the DISCOM network and endanger people working on the lines. The connection point is prepared and tested before the set arrives.
Who supplies fuel?
Fuel is on the customer account. Before the hire starts, agree who orders and receives the diesel, where it is stored, how often the set is topped up and who records the level, with a daily log of hours and litres so any unusual use shows at once.
Do I need two smaller units?
For critical use, or where the load falls a long way at night, two units give redundancy and keep each set loaded. Two 100 kVA sets cover a 120 kW peak at 75%, and one runs alone at night, while a single 200 kVA set would run at about 12%.
Figures are illustrative. Rental terms and technical arrangements are confirmed per project.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.