RECD, Dual Fuel or DG Replacement Decision Tool

How to compare retrofitting emission control (RECD), dual-fuel conversion and replacing a diesel generator: compliance, cost, performance, availability, risk and the data needed to decide.

In short. An older diesel generator that must meet tighter emission or operating rules has three broad paths: fit a retrofit emission control device (RECD), convert it to dual fuel, or replace it. The right choice depends on what the current rules require for that set’s size and location, on the engine’s age and condition, on gas availability, and on how many hours it runs. Start with the rules, because they change, then compare the options on a common basis.

Who this page is for: For owners, facility managers and consultants deciding what to do with existing diesel sets under emission and operating restrictions.

Key facts

  • An RECD is after-treatment fitted to the exhaust to cut particulate and other emissions.
  • Dual fuel replaces part of the diesel with gas; the engine still needs diesel to ignite.
  • Replacement gives a set built to current emission standards.
  • Retrofits suit engines with useful life left; worn engines are better replaced.
  • Check back-pressure limits, space, approvals and the engine maker’s position before retrofitting.
  • Verify the current rules for your set’s capacity band and location before deciding.

The three options

OptionWhat it doesTypical fitWatch for
RECD retrofitExhaust after-treatment to cut particulatesSound engines where rules require lower emissionsBack pressure, cleaning and regeneration, approval status
Dual-fuel conversionSubstitutes part of the diesel with gasSites with reliable gas supply and suitable enginesSubstitution rate, response to load steps, gas safety
ReplacementNew set to current standardsOld, worn or wrongly sized setsCapital cost, downtime, disposal of the old set

Worked example: three sets, three answers (illustrative)

SetSituationDecisionReason
A: 500 kVA, 6 years old, standby, about 100 h a yearEngine in good condition; rules require lower particulate emissions for its bandRECD retrofitPlenty of life left; low hours make conversion savings negligible
B: 750 kVA, 9 years old, prime power, about 3000 h a year, piped gas on siteGood engine, long running hoursDual-fuel conversion, checked for step responseHigh hours turn gas substitution into real savings and lower particulate emissions
C: 320 kVA, 18 years old, oil consumption high, oversized for today’s loadWorn engine, poor loadingReplace with a correctly sized, current-standard setRetrofitting a worn, oversized engine spends money on the wrong asset

The same rules produce three different answers once age, hours, condition and gas supply are on the table. See replacement vs retrofit.

Do not choose a retrofit or conversion before checking the current rules for your set’s capacity band and location, and the engine maker’s position. A device that is not accepted, or that pushes back pressure beyond the engine’s limit, solves nothing.

Decision factors

  • Rules: which apply to the set, its band and location, now. See GRAP and DG restrictions.
  • Engine age and condition: oil consumption, blow-by, service history.
  • Duty: standby hours versus prime-power hours.
  • Fuel: gas availability and supply security.
  • Performance: power, load-step response, back pressure.
  • Space and integration: room for devices and gas trains.
  • Downtime: temporary power during works. See rental power.

Option comparison sheet

FactorRECDDual fuelReplace
Meets current rules?   
Suits engine condition and hours?   
Performance effects   
Space, approvals, downtime   

Applying the tool across a fleet

Most owners face this choice for several sets at once, and the right answer usually differs from set to set. Screening the fleet in one table shows where each route fits and avoids applying one solution everywhere. The illustrative fleet below has four sets of different ages and duties.

SetRating and ageHours a yearGas availableEngine conditionLikely route
A500 kVA, 6 years2500NoGoodApproved RECD, keep in service
B500 kVA, 8 years3000YesGoodTrial dual fuel, then decide
C250 kVA, 18 years1200NoWornReplace with a compliant set
D160 kVA, 10 years40NoFairDocument and test; minimal change

Set A runs many hours, has a sound engine and no gas, so an approved retrofit device on the exhaust is the practical route. Set B also runs many hours and has gas, so a dual-fuel trial is worth the effort. Set C is old and worn, and spending on a device for it would extend a poor machine, so replacement is the sound choice. Set D runs only for tests and short outages, so its emissions are small in total and good records may be all the rules require.

What to check before choosing an RECD

  • The device approval covers the exact engine model and rating.
  • Exhaust back pressure with the device stays within the engine maker limit, including when the device needs cleaning.
  • Space, support and access for the device and its maintenance.
  • Exhaust temperature at the typical load suits the device; light-load running can block filters.
  • Monitoring of back pressure, with an alarm before the limit is reached.
  • The effect on warranty and insurance, confirmed in writing.

What to check before choosing dual fuel

  • An approved conversion kit for the engine model.
  • Reliable gas supply at the pressure and flow the engine needs at its highest gas share.
  • Enough running hours at middle and high load for the diesel saving to matter, since substitution is low at light load.
  • Engine condition: compression, injectors and turbocharger in good order.
  • Gas safety: detection, ventilation, shut-off valves and a safe pipe route.
  • Measured emissions after conversion, because some pollutants can rise.

What to check before choosing replacement

  • Whether the present rating still fits the load, or a different size is better.
  • Foundation, room, ventilation and exhaust arrangements for the new set.
  • Temporary power while the old set is removed and the new one commissioned.
  • The value of the old set if sold or exchanged after inspection.
  • Approvals needed for the new installation before it is connected.

A simple scoring aid

Where the choice is close, give each route a score from 1 to 5 against compliance certainty, life-cycle cost, reliability, disruption during the change and effort to maintain afterwards, with weights agreed beforehand. The scores do not make the decision on their own, but they make the reasoning visible and easy to review when rules or fuel prices change. A route that fails on compliance certainty is set aside whatever its other scores.

Keeping supply during the change

Retrofit, conversion and replacement all take a set out of service for some time. For critical loads a rental set is connected through a prepared connection point and changeover. The rental rate covers the generator; transport is at actuals and in the customer scope, cable and an operator are extra if required, fuel is on the customer account, and every rental set is load-bank tested before dispatch.

Evidence the decision should rest on

EvidenceWhy it matters
Running hours and load profile per setShows where emissions and fuel actually arise
Engine condition testsDecides whether investing in the set is sensible
Applicable notification for each setSets which routes are permitted
Device or kit approval documentsConfirms the route is allowed for that engine
Gas supply data where relevantShows whether dual fuel can deliver its saving
Measured emissions after any changeProves the result rather than assuming it

Kept together in the set file, this evidence lets the decision be explained to an inspector, an insurer or a future owner, and reviewed quickly when rules, fuel prices or the duty of the set change. A decision that cannot be traced to evidence is the one most likely to be reversed at cost later.

Planning the work over time

Few owners can change every set at once, so the routes are placed on a timeline. Sets facing the earliest compliance deadline or the poorest condition go first, followed by those where fuel savings repay the work soonest, and finally sets with low hours where records are the main task. Each change is scheduled away from the season of highest outage risk, with rental cover booked in advance where critical loads are involved. A one-page plan showing each set, its route, the target date and the evidence still needed keeps the programme on track and makes progress visible to management and inspectors alike.

As each set completes its route, its entry in the plan is updated with the date, the measured result and the evidence filed, so the plan doubles as a record of what the fleet has achieved and what remains to be done before the next rule change or inspection.

Common mistakes

  • Deciding before checking the current rules.
  • Retrofitting a worn engine.
  • Converting a low-hour standby set for fuel savings.
  • Ignoring back pressure and step response.

What to send us

Send each set’s kVA, age, running hours, condition, location and whether gas is available. WhatsApp 98852 01608 or use the enquiry form. See also the lifecycle decision framework.

Evidence note. The examples are illustrative; current regulations and makers’ approvals govern each decision.

Questions engineers ask

Should every set in a fleet take the same emissions route?

Rarely. Each set has its own age, condition, hours, duty and gas availability. In the illustrative fleet, a sound long-running set takes an approved RECD, a long-running set with gas trials dual fuel, a worn old set is replaced, and a standby set with few hours is documented and tested.

What makes an RECD unsuitable for a particular set?

No approval for that engine model, exhaust back pressure that would exceed the engine limit when the device needs cleaning, too little space or support, or long light-load running that keeps exhaust temperatures too low and blocks the filter. A worn engine also makes the investment unwise, so condition is checked first.

When is dual fuel worth considering?

When an approved kit exists for the engine, reliable gas is available at the pressure and flow needed, and the set runs many hours at middle and high load where substitution is meaningful. A trial on one set with measured diesel, gas and emissions confirms the result before the fleet decision.

How do I keep the site supplied while a set is retrofitted or replaced?

Connect a rental set through a prepared connection point and changeover, and test it on the site load before the old set is disconnected. The rental rate covers the generator; transport is at actuals, cable and operator are extra if required, fuel is on the customer account, and each set is load-bank tested.

What does RECD stand for?

Retrofit Emission Control Device, an after-treatment system fitted to an existing engine’s exhaust. It reduces particulate emissions from the exhaust without replacing the engine. Its approval must cover the engine model, and it adds back pressure and maintenance that are checked against the engine maker limits.

Is dual fuel always cheaper to run?

Only where gas is available and cheaper per unit of energy and the set runs enough hours to benefit. Compare the cost per kWh on diesel and on dual fuel at the real load, including the conversion, gas supply arrangements and extra maintenance, and remember that substitution falls at light load, so standby sets with few hours rarely benefit.

How do I know which rules apply?

Check the latest notifications from the relevant authorities for your location and duty. They change. Keep a dated copy of the notification that applies to each set with the set records, and recheck before any investment decision, because a rule change can alter which option is permitted or which is the most economic.

Will a retrofit affect warranty?

It can. Check with the manufacturer first. Fitting a device or conversion kit can affect the engine warranty, the insurance of the plant and any service agreement. Get written confirmation from the engine maker or the kit supplier before work starts, and keep it with the set documents.

Regulations change. Verify current requirements with the authorities before deciding.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.