In short. A 2000 kVA generator delivers 2782 A per phase at 415 V, three-phase, at 0.8 power factor — which is 1600 kW and 1200 kVAr. At 400 V the same set delivers 2887 A and at 433 V it delivers 2667 A, because current rises as voltage falls for the same kVA. Connected at 11 kV it draws only 105 A. At this size the current is no longer a cable question: 2782 A sets the breaker frame, the busbar, the fault level and very often the decision to generate at medium voltage or to split the load across sets in parallel.
Quick answers for a 2000 kVA set
- Full-load current at 415 V: 2782 A per phase
- Real power at 0.8 PF: 1600 kW
- Reactive power at 0.8 PF: 1200 kVAr
- Usual breaker frame: 3200 A air circuit breaker, set above 2782 A
- At 11 kV: 105 A per phase
- Per kVA at 415 V: about 1.39 A, so 2000 × 1.39 ≈ 2782 A
All figures are at the rated power factor of 0.8 and assume a three-phase, four-wire set. Always confirm against the nameplate of the actual machine.
Full-load current at each supply voltage
| Supply voltage | Full-load current (A) | Against 415 V | Where it applies |
|---|---|---|---|
| 380 V 3-phase | 3039 | +9.2% | Older and some imported equipment |
| 400 V 3-phase | 2887 | +3.8% | Nominal European voltage; many nameplates |
| 415 V 3-phase | 2782 | reference | Standard Indian LV supply |
| 433 V 3-phase | 2667 | −4.2% | No-load and lightly loaded alternator setting |
| 3.3 kV 3-phase | 350 | −87.4% | HV alternators feeding large motors |
| 6.6 kV 3-phase | 175 | −93.7% | Process plants with 6.6 kV distribution |
| 11 kV 3-phase | 105 | −96.2% | Medium-voltage connection, campuses and utility-side switchgear |
Nothing about the engine changes between these rows. Only the alternator winding, or a step-up transformer after it, changes the voltage — and with it the current every downstream component has to carry.
How the 2782 A is worked out
For a three-phase set the full-load current is
I = kVA × 1000 ÷ (√3 × V)
With 2000 kVA at 415 V:
- √3 × 415 = 1.732 × 415 = 718.80
- 2000 × 1000 = 2,000,000 VA
- 2,000,000 ÷ 718.80 = 2782 A
The kW and kVAr come from the power factor, not from the formula: 2000 × 0.8 = 1600 kW of real power, and 2000 × 0.6 = 1200 kVAr of reactive power. The set delivers 2782 A at its rated kVA whatever the power factor of the load. What the power factor changes is how much of that current does useful work — at 0.7 PF the same 2782 A carries only 1400 kW, and the engine is under-used while the alternator is fully loaded.
Where a 2000 kVA set is used
2000 kVA sits at the top of what is normally built as a single low-voltage machine. It appears in large process plants, hospital and campus central plant rooms, data facilities, malls and commercial towers with heavy chiller load, and as backup for a whole substation. It is also the size at which most designers stop and ask whether one machine is the right answer at all, or whether two or three smaller sets in parallel, or generation at 11 kV, would serve the site better.
Reading the 2782 A figure properly
At 415 V, 2782 A is past the point where cable is the natural choice. A 3200 A air circuit breaker, a 3200 A busbar trunking run from the alternator to the main panel, and a panel busbar rated for the fault level are the usual arrangement. If cable is used instead, it means ten or more large single-core runs per phase, with the grouping derating, terminations and support work that go with them.
The fault level matters as much as the running current. A large alternator with a subtransient reactance in the usual 12 to 15% range can deliver roughly 18.5 to 23 kA in the first cycles of a three-phase fault at its terminals — and more where sets are paralleled or the mains can feed in during a closed transition. The breaker, busbar and panel must be rated for the prospective fault at that point, not only for 2782 A.
Standby, prime or continuous: the same set, three different figures
A nameplate reading 2000 kVA does not say how long the set may hold it. The international rating definitions separate three duties, and the same machine carries a different figure in each:
| Duty | What it allows | Typically for this machine | Current at 415 V |
|---|---|---|---|
| Standby | Mains failure only, limited hours a year, no overload | 2000 kVA, 1600 kW | 2782 A |
| Prime | Unlimited hours at a varying load | about 1800 kVA, 1440 kW | about 2504 A |
| Continuous | Unlimited hours at a constant load, base load duty | about 1400 to 1600 kVA | about 1948 to 2226 A |
The percentages differ between manufacturers and engines, so the third and fourth columns show the usual pattern rather than a specification: prime is commonly around 90% of the standby rating and continuous around 70 to 80%. The nameplate and the engine maker’s rating sheet govern.
Two quotations for “a 2000 kVA set” can therefore describe different engines. If one is a standby rating and the other a prime rating, the prime-rated machine is the larger engine. Ask which duty the figure belongs to before comparing anything else.
What the site does to the 2782 A
Published ratings are quoted at reference conditions. A plant room in Telangana or Andhra Pradesh in May is hotter than the reference, and a machine of this size moves a great deal of cooling and combustion air — any shortfall shows up directly as lost output.
- Ambient temperature. What counts is the air entering the engine and the radiator, which in a closed room can be well above the outside shade temperature.
- Altitude. Small for most of our region, but not always zero.
- Air and exhaust restriction. Undersized louvres, hot-air recirculation, a dirty radiator, or a long exhaust run with too many bends.
A derate in the region of 5 to 10% is common once a set is installed in regional summer conditions. On this machine that is 1800 to 1900 kVA, or 2504 to 2643 A at 415 V. These figures show the size of the effect; the engine maker’s derating curve for the actual engine is what a design should use.
Worked example
The same 2000 kVA, connected two ways.
- At 415 V: 2782 A. A 3200 A breaker and a 3200 A busbar trunking run to the main panel. If cable were used, ten runs per phase would carry 278 A each before any grouping derating — thirty large cables plus neutral and earth.
- At 11 kV: 105 A. One cable per phase and an 11 kV panel with a breaker of modest current rating.
- The ratio: 2782 ÷ 105 = 26.5 times the current for the same power. Losses rise with the square of current, so the same conductor at 415 V would dissipate about 700 times what it does at 11 kV.
That is why long runs at this rating go to medium voltage, and why a 2000 kVA set placed next to its main LV panel can still stay at 415 V.
One 2000 kVA set, two 1000 kVA sets, or 11 kV? A decision table
| Consideration | Points to one set at 415 V | Points to two sets in parallel | Points to 11 kV |
|---|---|---|---|
| Distance to the load centre | Short, set beside the main panel | Short to medium | Long, or across a campus |
| Need for redundancy | Low — an outage of the set is acceptable | High — one set carries essential load during servicing | Depends on the number of sets |
| Load profile | Mostly near full load when running | Varies widely; one set can stop at light load | Large and spread out |
| Largest motor started direct on line | Large — one big machine holds the dip better | Small or soft-started | HV motors already on site |
| Existing 11 kV switchgear and licensed HV staff | No | No | Yes |
| Plant room space | One large footprint | Two footprints plus a synchronising panel | Set plus transformer or HV alternator and HV panel |
No single row decides it. Where three or more answers fall in one column, that arrangement usually wins on installed cost and on how the site actually runs.
Common mistakes with a 2000 kVA set
- Rating the breaker and busbar for 2782 A but not for the fault level. The prospective fault current at the panel, with any paralleled sets and mains contribution, decides the breaking capacity and the busbar bracing.
- Treating 2000 kVA as simply a larger 1500 kVA. At 2782 A the arrangement changes in kind: busbar trunking instead of cable, and a real choice between one set, sets in parallel, and medium voltage.
- Comparing quotations without the duty. A 2000 kVA standby rating and a 2000 kVA prime rating are different engines.
- Sizing on kVA alone. At a load power factor of 0.9, 2000 kVA would be 1800 kW — more than the engine’s 1600 kW. Both limits apply, and the lower one binds.
What to send us
If you are deciding whether a 2000 kVA set is the right size, these five things let us answer properly rather than guess:
- Maximum demand in kW and the power factor it was measured at. Against this set the limits are 1600 kW and 2000 kVA.
- The largest motor, its rating, and how it is started: direct on line, star-delta, soft starter or variable speed drive.
- The supply voltage on the nameplate — 380, 400, 415 or 433 V. It moves the current from 2667 A to 3039 A for the same set.
- The distance from the set to the main panel and whether the site already has 11 kV switchgear.
- How the set will be used: standby for a few hours a month, prime power for shifts, or continuous.
Next step: work your own load through the generator kVA and kW sizing calculator, then send an enquiry with the five items above and we will confirm the rating in writing.
Questions engineers ask
What is the full-load current of a 2000 kVA generator?
2782 A per phase at 415 V, three-phase, at 0.8 power factor, which is 1600 kW. At 400 V it is 2887 A, at 433 V it is 2667 A, and at 11 kV the same set draws only 105 A.
What breaker does a 2000 kVA generator need?
A 3200 A air circuit breaker, set above the 2782 A full-load current at 415 V, with a breaking capacity chosen for the prospective fault current at the panel. The fault level, not only the running current, decides the final selection.
How many kW is a 2000 kVA generator?
1600 kW at the standard rated power factor of 0.8. The set must stay within both 1600 kW and 2000 kVA; whichever the load reaches first is the limit.
Should a 2000 kVA generator be connected at 415 V or 11 kV?
A set beside its main LV panel feeding an all-LV load usually stays at 415 V with busbar trunking. Long runs, campuses, sites with existing 11 kV switchgear, or plans to add more sets point to 11 kV, where the same power is 105 A instead of 2782 A.
Is one 2000 kVA set better than two 1000 kVA sets?
One set takes less space and holds a large direct-on-line motor start better. Two 1000 kVA sets in parallel give redundancy and run more efficiently at part load, but need a synchronising and load-sharing panel. Where one set must carry the essential load alone during servicing, each set is sized for that load.
Full-load current at other ratings
- 5 kVA — 7.0 A at 415 V
- 7.5 kVA — 10.4 A at 415 V
- 10 kVA — 13.9 A at 415 V
- 12.5 kVA — 17.4 A at 415 V
- 15 kVA — 20.9 A at 415 V
- 20 kVA — 27.8 A at 415 V
- 25 kVA — 34.8 A at 415 V
- 30 kVA — 41.7 A at 415 V
- 40 kVA — 55.6 A at 415 V
- 45 kVA — 62.6 A at 415 V
- 50 kVA — 69.6 A at 415 V
- 62.5 kVA — 87.0 A at 415 V
- 75 kVA — 104 A at 415 V
- 82.5 kVA — 115 A at 415 V
- 100 kVA — 139 A at 415 V
- 125 kVA — 174 A at 415 V
- 250 kVA — 348 A at 415 V
- 320 kVA — 445 A at 415 V
- 750 kVA — 1043 A at 415 V
- 1010 kVA — 1405 A at 415 V
- 1250 kVA — 1739 A at 415 V
- 1500 kVA — 2087 A at 415 V
- Every rating from 7.5 to 3000 kVA — the full chart
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 22 November 2026.