Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Legacy DG Compliance & Modernisation

How to approach older diesel generators facing emission rules: inventory, classification, options (retrofit, dual fuel, replace, restrict use), documentation and a phased modernisation plan.

In short. Older generators on one site rarely need the same action. Start with an inventory of every set: age, rating, hours, location and condition. Match each set to the rules that apply to it, then choose to retrofit, convert, replace, restrict use or simply document it. A phased plan deals with urgent cases first and keeps backup power available throughout.

Who this page is for: For owners and facility managers of campuses, plants and estates with several older generators.

Key facts

  • Inventory every set before deciding anything.
  • Rules can depend on size, age, location and use.
  • Confirm the current notifications for each location.
  • Urgent cases first; low-use standby sets last.
  • Never remove backup before its replacement is proven.
  • Keep a record for each set.

Worked example: a campus with six sets (illustrative)

SetSituationActionPhase
DG-1, 500 kVAUnder local restrictions now; 1800 h a yearRetrofit device1, urgent
DG-2, 320 kVAUnder local restrictions now; worn engineReplace1, urgent
DG-3, 250 kVA900 h a year; sound engineRetrofit device2
DG-4, 250 kVA700 h a year; sound engineRetrofit device2
DG-5, 160 kVAStandby, 40 h a yearDocument and monitor3
DG-6, 62.5 kVALoad moved to another setRetire2

Phasing spread the cost over two years and kept every critical building backed up during the work. See route comparison and documentation.

Do not take a set out of service for retrofit or replacement until the loads it backs up have another source in place.

Inventory fields

FieldWhy
Make, model, kVA, engine yearRule category and options
Hours and typical loadValue of each option
LocationLocal restrictions
Condition: smoke, oil use, faultsRetrofit or replace
Loads servedPhasing and backup

See emission rules overview and battery storage to cut running.

Fleet plan sheet

The phased plan for the same seven-set fleet — a pharmaceutical contract manufacturer with three units, a warehouse and a site office, which is a different and more spread-out estate than the single campus in the example above. That matters for the last column rather than the first: on a campus one set can usually back up another, and here the sets are in different buildings. The second column is written as what has to be confirmed, not as a rule, because the rule that applies is a question of the order in force on the day the work is committed.

SetRule that appliesActionPhaseBackup during work
A, 500 kVA, Unit 1To be confirmed for this rating and location before the device is ordered. Evidence to assemble: rating plate, engine year, emission certificate, hours logFit emission control. Measure before and after, at the same reference load1Set B carries Unit 1 alone, with the two non-essential boards off for the window
B, 500 kVA, Unit 1As A. The route also depends on what the post-overhaul measurement showsOverhaul. Then measure, then decide on a device separately1Set A carries Unit 1 alone, same restriction. A and B are never both out
G, 1010 kVA, Unit 3To be confirmed for both the existing and the replacement rating, which may not fall in the same categoryReplace with a set sized for the load that is there. Retain G for redeployment2Rental set on a temporary changeover. There is no second set at Unit 3
C, 320 kVA, Unit 2To be confirmed, and for dual fuel also whether an approval path exists for the conversion at this locationDual fuel, subject to the gas supply being confirmed in writing2Rental set. Set D cannot carry Unit 2 on its own
D, 250 kVA, Unit 2To be confirmed for the replacement rating. The existing set is being removed, not modifiedReplace, smaller, and move its board onto C where the distribution allows2Set C carries Unit 2
E, 200 kVA, warehouseTo be confirmed, and recorded. No change is proposed, so this is a documentation exerciseKeep. Record the certificate, the hours and the service history3Not applicable. Nothing is taken out of service
F, 125 kVA, site officeTo be confirmed. At 60 hours a year this set is most likely to be affected by a use restriction rather than a device requirementKeep, document and restrict use to what the rules allow3Not applicable. The site office accepts an outage
     
     

The phasing falls out of the last column rather than out of urgency, and that is the opposite of how these plans are usually built. Unit 1 goes first because A and B can cover for each other, so phase 1 needs no rental set and no loss of cover — the only constraint is that the two are never out together, which is written into the row rather than left to the programme.

Unit 2 and Unit 3 go second because both need hired-in supply, and putting them in one phase means one mobilisation rather than two. The warehouse and the site office go last because nothing is being done to them except paperwork.

The second column is deliberately not a list of rules, and that is the most important thing on this sheet. What applies to a set depends on its rating, its installation date, its location and its duty, and the orders change — so a published plan that printed a rule against each line would be wrong within a season and would be quoted long after.

What the column can usefully hold is the evidence: the rating plate, the engine year, the emission certificate and the hours log, assembled per set, so that whoever checks the rule has everything needed to answer it in one place. On this fleet that exercise found two gaps before any rule was consulted at all — no emission certificate on file for Set D, and an hours log for Set F that had not been written up since 2019.

One rule in the last column is absolute and is the reason the column exists: no set comes out of service until the loads it backs up have another source that has been proved on load. “Proved” means the rental set has carried the real load, not that it has been delivered and started. The row for G says there is no second set at Unit 3, which is exactly the kind of fact that is obvious on the sheet and invisible in a programme bar chart — and it is why G is in phase 2 with a hire budget rather than in phase 1 with the others.

A condition assessment for each older set

Before deciding what to do with an older generator, find out what condition it is really in. A short assessment by a service engineer gives a factual basis for every later choice.

  • Engine: starting, smoke, blow-by, oil consumption, cylinder pressure tests where needed, oil analysis.
  • Cooling: radiator condition, coolant quality, hoses and pump.
  • Alternator: insulation resistance, bearing noise, winding temperature at load.
  • Controls: panel condition, protection functions, availability of spares for the controller.
  • Fuel system: tank condition, water and sludge, injector performance.
  • Performance: a load-bank test at rated output, recording voltage, frequency and temperatures.

Matching each set to a route

Condition and useUsual route
Sound engine, low hours, standby useKeep, service thoroughly and modernise controls if spares are scarce
Sound engine, local rules need lower particulatesRetrofit emission control device, with backpressure checked
Worn engine but valuable alternator and baseEngine overhaul, or refurbishment of the whole set
Poor condition, high hours, heavy dutyReplace with a CPCB IV+ set
Surplus to needsSell or part-exchange against a new or refurbished set

Worked example: prioritising a fleet of six sets (illustrative)

A company has six older sets across three sites. Two are standby sets at offices with low hours and sound engines: they are kept, serviced and given new controllers. One factory set runs daily, smokes under load and fails its load-bank test: it is replaced first. Two sets at a warehouse are sound but must meet a local particulate rule: they receive retrofit devices after a backpressure check. The sixth set is surplus after a site closure and is taken in part exchange. The plan spreads spending over two years, with the riskiest set dealt with first and every site keeping backup throughout.

Refurbished sets as a middle route

Where a replacement is needed quickly or budgets are tight, a refurbished set can be a sound option. Reddy Generators refurbished sets are totally or partially rebuilt, load-bank tested before sale and carry a six-month warranty, with rubber and plastic parts, consumables, fuel damage and overload excluded. Used sets sold as they are come with an inspection report instead of a warranty. Whether a refurbished or used set can be installed at a site depends on the emission rules that apply to that installation, which are confirmed before purchase.

Keeping power during the work

Replacement, overhaul and retrofit all take a set out of service. A rental set connected through a prepared changeover point keeps the site protected. The rental rate covers the generator, transport is at actuals and in the customer scope, cable and an operator are extra if required, fuel is on the customer account, and every rental set is load-bank tested before dispatch.

Common mistakes

  • Replacing everything at once.
  • No inventory.
  • Backup removed before the new source works.
  • Low-use sets left undocumented.

What to send us

Send your list of sets with ages, hours and locations. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. The example is illustrative.

Questions engineers ask

What should a condition assessment of an old generator cover?

Engine starting, smoke, blow-by, oil use and oil analysis; cooling system condition; alternator insulation and bearings; control panel condition and spares; fuel tank and injectors; and a load-bank test at rated output recording voltage, frequency and temperatures. The results decide whether to keep, retrofit, overhaul or replace.

How should a company prioritise upgrades across several old sets?

Assess every set, then deal with the riskiest first. In the illustrative fleet, a failing daily-duty set is replaced first, sound standby sets get new controllers, sets facing a particulate rule receive retrofit devices, and a surplus set is taken in part exchange, with backup kept throughout.

Is a refurbished generator a good alternative to a new one?

It can be. Reddy Generators refurbished sets are totally or partially rebuilt, load-bank tested before sale and carry a six-month warranty excluding rubber and plastic parts, consumables, fuel damage and overload. Whether one suits a site depends on the emission rules that apply to that installation, confirmed before purchase.

Can an old generator be part-exchanged?

Yes. Reddy Generators buys used generators and takes sets in part exchange against a new or refurbished set. A surplus or worn set can therefore help fund its replacement, and the site can plan the changeover with a rental set covering the gap if needed.

Do all old sets need replacement?

Not necessarily. The rules that apply depend on the set, its age, its rating and its location, and the right route depends on its duty and condition. Some sets continue as they are, some need an approved retrofit or new controls, and some are better replaced. Each set is assessed on its own facts.

What about backup during work?

Plan a temporary supply for the critical loads before any set is taken out of service. A rental set connected through a prepared connection point and changeover covers the work period, and it is load-bank tested before dispatch so the site is never left relying on an untested source. See rental power.

How do I keep records?

One file per set, holding the nameplate details, purchase and type-approval documents, installation approvals, service history, load-bank and emission test results, and every modification with its date. Keep the working copy on site and a scanned copy off site, so the history survives a fire, a flood or a change of staff.

Where do I start?

With the inventory: list every set with its rating, engine model, age, running hours, duty, location and condition, and note the rules that apply to each. That single list shows which sets need action first, which can continue as they are, and where a common solution saves cost across the fleet.

General guidance only. Confirm current rules.