GRAP & Temporary DG Operating Restrictions

How to plan for stage-based and temporary restrictions on generator use: classify loads, set up alternatives, maintain compliance records and run drills so critical supply survives a restriction.

In short. In Delhi-NCR, the Graded Response Action Plan (GRAP) brings in curbs in stages as air quality worsens, and generator use is one of the activities it regulates. Under the current schedule, regulated operation of diesel generator sets starts from the first stage, with rules that depend on the set’s capacity. Restrictions can arrive with little notice. Sites that cope well have already classified their loads, arranged a permitted source for critical loads, kept their documents ready and tested the switchover before the notice comes.

Who this page is for: For facility managers, hospitals, housing societies, data rooms and factories in Delhi-NCR, and for companies with NCR sites managed from elsewhere, that depend on diesel generators.

Key facts

  • GRAP has four stages tied to the air quality index: Stage I (Poor, 201 to 300), Stage II (Very Poor, 301 to 400), Stage III (Severe, 401 to 450) and Stage IV (Severe Plus, above 450).
  • Stages are cumulative: the actions of earlier stages continue when a higher stage is invoked.
  • Under the schedule revised in late September 2026, regulated operation of generator sets applies from Stage I across NCR.
  • The rules are set by capacity band; small portable sets are generally not permitted except for prescribed emergency services.
  • Always read the current order: stages, bands and permitted technologies can change.
  • Keep a dated log of every generator run during a restriction, with the reason.

Stages at a glance

StageAir quality categoryAQI bandWhat it means for generator users
IPoor201 to 300Regulated operation of generator sets begins, by capacity band
IIVery Poor301 to 400Stage I rules continue, with wider curbs on other activities
IIISevere401 to 450Earlier rules continue, with further curbs on other activities
IVSevere PlusAbove 450All earlier rules continue, with the strictest curbs on other activities

The capacity bands in the current schedule are 800 kW (1000 kVA) and above, 41 kW (51 kVA) up to 800 kW, 19 kW (about 24 kVA) up to 41 kW, and portable sets below 19 kW. What each band may run, and on which technology, is set out in the current direction. Check it before planning. See Delhi-NCR DG regulatory intelligence.

Plan before the notice

ItemAction
Generator inventoryEvery set’s kVA, capacity band, fuel type, any retrofit emission control device, and certificates
Load classesCritical, essential and deferrable. See load shedding
Permitted source for critical loadsA compliant set, a gas or dual-fuel set, storage, or a second utility feeder
DocumentsCertificates, emission test reports, approvals, kept ready for inspection
ContactsPollution control authority, utility, service partner, rental supplier
ConsumablesFuel, filters, urea where fitted, gas supply

Worked example: a hotel’s restriction plan (illustrative)

A hotel has a 500 kVA diesel set and a peak demand of 380 kW. At 400 kW, the set falls in the 41 to 800 kW band. Its restriction plan classifies the loads as follows.

ClassLoadskWSource during a restriction
CriticalFire and life-safety systems, IT and front office, cold storage, emergency lighting60Battery storage for short outages; a permitted source for longer ones
EssentialLifts, water pumps, corridor lighting, kitchen120Permitted source; lifts limited to fewer cars
DeferrableLaundry, comfort cooling in public areas, non-essential plant200Shed during outages

The permitted source therefore needs to carry about 180 kW, not the full 380 kW. A rented compliant set, or storage plus a smaller compliant set, does the job. A drill before the season proves the switchover. See DG plus BESS and rental power.

Do not assume an exemption. Read the current order, confirm which band your set falls into and what it may run on, and keep the documents that prove it. A plan built on last year’s rules can leave critical loads without a permitted source.

When a restriction starts

  1. Read the order and confirm which sets and bands are covered.
  2. Move deferrable loads off generator supply.
  3. Switch critical and essential loads to the permitted source.
  4. Log every generator run: date, time, duration and reason.
  5. Tell occupants what will change, such as reduced lift service.
  6. When the restriction is lifted, return to normal and review the log.

Engineering options

OptionStrengthWatch for
Battery storageCarries critical loads through short outages with no generator runningAutonomy is limited; size for the realistic outage
Gas or dual-fuel setsCleaner operation; may be treated differently under the orderGas supply and the current rules for each band
Retrofitted emission control devicesCut particulate emissions from existing setsApproval status and maintenance. See cleaner-fuel systems
Rental of compliant setsFast, no capital outlayBook before the season; demand peaks when stages rise
Second utility feederRemoves most generator runningAvailability and cost from the utility

Drills

Run a table-top exercise each year before the winter season: walk through a restriction with the people who would handle it, then test the switchover on load. A plan never tested on load is an assumption. See load bank testing.

Restriction playbook worksheet

ItemValue or owner
Each set: kVA, capacity band, fuel, emission device 
Critical load (kW) and its permitted source 
Essential load (kW) and its permitted source 
Deferrable load (kW) to shed 
Owner who reads the order and triggers the plan 
Date of the last drill 

The levers, in the order they cost least

When a restriction notice lands, the site has four ways to reduce generator running and they differ by a factor of many in cost and in lead time. Worked in the wrong order, the expensive one gets used because the cheap ones were never set up. The order below is the one to prepare in, which is the opposite of the order they get reached for.

LeverWhat it removesLead time to be readyWhat it costs during a restrictionWhat it needs set up in advance
1. Shed what does not need to runGenerator load, so fewer sets and lower loadingWeeks, once the priority list existsNothing, if the list was agreed with the departments beforehandA load priority register, and a contactor or breaker that can actually drop each tier
2. Ride through short events on a batteryStarts, and all the short runsMonthsNothing. The battery does it unattendedBattery sized from the outage profile, and a control that knows when to hand over
3. Run on the cleaner fuel routeDiesel burnt, not hours runMonths, and longer for a gas connectionFuel cost difference, and the operator attention two fuels needConversion done and accepted, gas supply contracted, operators trained
4. Stop the set and accept the outageAll generator runningNoneThe whole cost of the load being downNothing — which is exactly why it is the lever sites end up using

Read the last two columns together. Lever 4 needs no preparation and costs the most; levers 1 to 3 cost little or nothing in the moment and all need preparation. That asymmetry is the whole reason restriction seasons hurt: the cheap responses have lead times measured in weeks and months, and the notice arrives in days. Every hour of preparation done out of season converts a lever that is unavailable into one that is free to use.

The fleet under a restriction, set by set

Restrictions do not apply evenly across a fleet, because the sets differ in what they are for and in what has been done to them. Taking the four sets described across this section, a restriction stage that limits generator running produces four different answers on the same site on the same day.

SetNormal dutyWhat it can do under restrictionLoad it can still carryThe gap this exposes
A, 500 kVA, retrofitted2500 h a year at 300 kWRun, with the retrofit as the justification and its records to hand300 kW, unchangedOnly that its pressure trend and cleaning record must be current, not six months old
B, 500 kVA, dual fuel3000 h a year at 300 kWRun on the gas-substituted route, at the substitution the acceptance test proved300 kW, if gas is availableA gas supply interruption during a restriction leaves it with no compliant route at all
C, 250 kVA, awaiting replacement1200 h a year at 100 kWLittle. An old set with no aftertreatment is the first thing a restriction stopsTreat as unavailableIts 100 kW has to be covered by shedding or by A and B, and that has to be planned, not discovered
D, 160 kVA, standby only40 h a year, untested under loadStart for a genuine outage, but it has no evidence of capabilityUnproven — which is not the same as 128 kWA set whose file shows only no-load running is the weakest position to be inspected in

The fourth column is the one to total before a season rather than during it. A and B together carry 600 kW. C is unavailable and its 100 kW must come off the load or move onto A and B, which have the capacity for it. D contributes nothing that can be relied on until it has been load-bank tested. So this site’s restriction-season capability is 600 kW against a normal generator load of 700 kW, and the 100 kW difference is exactly the shedding that lever 1 has to deliver — which is a number, agreed with the departments it comes from, rather than a decision to be made at the time.

Two exceptions are worth noting. Life-safety loads are treated separately in most restriction regimes, and a site that has not identified which of its circuits are genuinely life-safety will find itself arguing the point under pressure; that identification is a drawing exercise done calmly, in advance. And a set that is being replaced, as C is, is worth replacing before a restriction season rather than after it, because the compliance position of a current-category set arrives with the machine and needs no evidence assembled at all.

Common mistakes

  • Relying on last season’s rules.
  • No load classification, so the permitted source is sized for the whole site.
  • Booking rental sets after the stages rise.
  • No operating log during restrictions.
  • Untested switchover to the permitted source.

What to send us

Send your generator inventory, load list and site location. WhatsApp 98852 01608 or use the enquiry form.

Evidence note. Stage bands and capacity bands reflect the schedule in force at the time of this update. Orders change; the current official order governs.

Questions engineers ask

What can a site actually do when a restriction notice arrives?

Four things, and three of them need preparation. Shedding load that does not need to run costs nothing in the moment but needs a priority register and breakers that can drop each tier. Riding short events on a battery costs nothing but takes months to install. Running a cleaner fuel route needs the conversion already accepted. Stopping the set needs no preparation at all, which is why unprepared sites end up using it.

Why plan restriction response out of season?

Because the cheap levers have lead times measured in weeks and months and the notice arrives in days. The asymmetry is the whole problem: the response that needs no preparation is the one that costs the most. Every hour spent out of season converts a lever that would be unavailable into one that is free to use when it is needed.

How do restrictions affect different generators on the same site differently?

Entirely differently, because the sets differ in what has been done to them. A retrofitted set can run on the strength of its records. A dual fuel set can run on its substituted route if gas is available. An old set with no aftertreatment should be treated as unavailable. And a standby set whose file shows only no-load running has no evidence of capability at all, which is the weakest position to be inspected in.

Where are the current restrictions?

In the official orders issued by the authorities for the region, which can change at short notice and differ by stage of restriction. Verify the current order directly at its source before planning operation, keep a dated copy with the site records, and recheck whenever a new stage is announced for the area.

Do UPS and batteries count?

They help for short durations. A UPS or battery system can carry critical loads through short outages without running the generator, which reduces the hours the set needs during a restriction. For longer outages a permitted source is still needed, so the plan states which loads the batteries carry and for how long.

Can I rent compliant sets?

Often yes. Check that the rental set meets the specification the restriction requires, such as the emission stage, any approved retrofit device or the fuel type, and keep its documents on site for inspection. Every rental set is load-bank tested before dispatch, and its compliance papers are confirmed before it is booked.

Do I need to log operation?

It is good practice and often required. Record every start and stop with the date, time, duration, load and reason, so the operation can be shown to match what the restriction permits. A clear log also supports any request for an exemption, such as running for essential services during a grid failure.

General guidance only. Verify with official notices.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.