Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Islanding and Microgrid Readiness Checker

A structured way to judge whether a site can operate as an island or microgrid: sources, load balance, control, protection, grid interface, reserve and the gaps to close before attempting it.

In short. A site is ready to run separated from the grid only when four things are in place. There must be a controller that manages all sources and the grid breaker, and protection that disconnects safely from the grid. Solar output must be curtailable so it never pushes reverse power into the running generators. And the neutral must be earthed on the island side. The decision tool above shows which of these are missing.

Who this page is for: For owners and engineers of sites with generators, solar and batteries who want to run as an island.

Key facts

  • A controller must manage sources, load and the grid breaker.
  • Loss-of-mains protection separates the site safely.
  • Solar must be curtailed so generators stay above minimum load.
  • Reverse power from solar can trip generators.
  • If the separation point disconnects the transformer’s neutral earth, provide one on the island side.
  • The utility’s approval is usually needed.

Worked example: a campus with generators and solar (illustrative)

ItemValueIssue
Generators2 × 500 kVA (400 kW each)—
Solar600 kWp, about 450 kW at midday—
Midday island load350 kWSolar alone exceeds the load
Without curtailmentGenerators pushed into reverse powerSets trip; island collapses
With curtailmentOne set kept at about 30% (120 kW); solar limited to about 230 kWStable

The site also needs loss-of-mains protection on the grid breaker and a neutral earth for island operation. See islanded operation and microgrids.

Do not run solar and generators together in an island without curtailment. Surplus solar pushes reverse power into the generators and trips them.

Typical gaps

GapFix
No master controllerMicrogrid or generator-solar controller
No loss-of-mains protectionProtection on the grid incomer
Solar cannot be limitedInverter curtailment linked to the controller
No neutral earth when separatedEarth on the island side

See earthing and neutral.

Readiness sheet

ItemIn place?
Controller 
Loss-of-mains protection 
Solar curtailment 
Island neutral earth 

Checking the power balance in the example

An island has no grid to absorb a surplus or cover a shortfall, so every kilowatt produced must be consumed at that instant. At midday the campus load is 350 kW and the solar plant could deliver about 450 kW. A generator set must stay above its minimum stable load, here taken as about 30% of its 400 kW rating, or 120 kW, to avoid light-load running and reverse power. The solar output is therefore limited to 350 − 120, or 230 kW, and only one generator runs.

QuantityWorkingValue
Island load at middayMeasured350 kW
Minimum generator output30% × 400 kW120 kW
Solar allowed350 − 120230 kW
Solar curtailed450 − 230220 kW
Spinning reserve on the running set400 − 120280 kW, to cover a cloud or a load step

The reserve matters as much as the balance. If a cloud removes the 230 kW of solar in a few seconds, the running set must pick up that step at once. A step of 230 kW on a 400 kW set is more than half its rating, which many diesel sets cannot accept in one step without a deep frequency dip. The controller therefore either keeps the solar share lower, keeps a second set running, or uses a battery to cover the fast change.

What the controller has to do

  • Detect loss of the grid and open the grid breaker, or receive the trip from the loss-of-mains protection.
  • Start the generators, synchronise them and share load between them.
  • Limit solar inverter output so the generators stay above their minimum load and never see reverse power.
  • Shed or restore loads in priority order when the sources cannot meet demand.
  • Resynchronise the island to the grid when it returns, close the grid breaker and return the generators and solar to their normal settings.

Each function is listed in the control philosophy, with the signal it uses, the action it takes and the time it allows, and each is tested before the site depends on it.

Loss-of-mains protection

When the grid fails, the site must separate from it before the generators or inverters can feed back into the network, where line staff may be working, and before the grid returns out of phase with the island. Loss-of-mains protection detects the failure from changes in frequency, rate of change of frequency, vector shift or voltage, and trips the grid breaker. Its settings are agreed with the distribution company, which usually specifies the functions and limits for any site that can run in parallel with the network or island from it. A sensitive setting that trips on normal grid disturbances causes nuisance islanding; a slow one risks backfeed.

Earthing on the island side

Many sites take their neutral earth from the star point of the distribution transformer. If the island separates on the high-voltage side of that transformer, the earth stays with the site; if it separates on the low-voltage side, the transformer and its neutral earth are left behind with the grid. The island then has no earthed neutral, earth-fault protection cannot work and the voltage to earth can float. The fix is a defined neutral earth on the island side, for example at the generator neutral, switched so that the site always has exactly one neutral-earth point in each operating mode.

Fault levels and protection in the island

A generator gives much less fault current than the grid, and solar and battery inverters give only about one to one and a half times their rating. Protection set for grid fault levels may therefore not trip, or trip too slowly, when the site runs as an island. The protection study covers the island configuration with the weakest likely source arrangement, and settings are chosen, or a second settings group is switched in, so that faults in the island are still cleared in time.

Where a battery helps

A battery with a grid-forming inverter can hold voltage and frequency while generators start, absorb surplus solar for a few minutes instead of curtailing it, and cover the sudden loss of solar output when a cloud passes. It reduces the spinning reserve the generators must carry and can allow fewer sets to run. It is not always necessary: a site with generators that can accept the expected steps and a controller that curtails solar quickly can island without one.

Testing the island

TestWhat it proves
Loss-of-mains trip by secondary injectionProtection settings and trip wiring
Planned separation on loadGenerators take the load and solar is curtailed
Loss of solar output while islandedReserve covers the step
Earth-fault test in island modeNeutral earth and protection work without the grid
Resynchronisation and return to gridBreaker closes in synchronism; normal settings restored

The tests are witnessed, recorded and repeated after any change to sources, controls or protection.

Approvals

Islanding and parallel operation with the grid usually need the approval of the distribution company, and sometimes of the electrical inspectorate, before the system is used. The application normally includes the single-line diagram, the protection settings, the interlocks that prevent backfeed and the test plan. Approval is sought before equipment is ordered, because the required protection functions can change the design.

Load priorities for island operation

PriorityTypical loads on a campusIsland treatment
1Safety systems, fire pumps, emergency lighting, IT and controlsAlways supplied
2Water pumping, kitchens, laboratories with sensitive workSupplied once generators are on line
3General lighting and small powerRestored as capacity allows
4Comfort cooling, workshops, vehicle chargingShed first; restored last

The priorities decide how much generator capacity the island really needs, and they let the controller shed load in a known order when a set trips or the solar output falls suddenly.

Common transition problems

  • Large motors reconnected all at once after separation, causing a step the generators cannot accept.
  • Solar inverters reconnecting automatically after their own anti-islanding delay, at full output, before the controller has set a limit.
  • Generator controllers left in a mode that expects the grid, so they do not share load correctly when islanded.
  • UPS units transferring to battery on every small frequency excursion in the island, because their input tolerance was set for grid supply.
  • The grid breaker closing out of synchronism on return, because the sync-check function was bypassed during commissioning and never restored.

Data needed for a readiness assessment

A useful assessment starts from the single-line diagram, the ratings and controllers of every source, the solar inverter models and their control interfaces, the location of the neutral earth, the existing protection settings, a load profile with the midday minimum and evening peak, and the list of loads in priority order. With these, the gaps found by the decision tool above can be turned into a scoped list of works and studies.

The evening case

The midday case tests the solar limit; the evening case tests capacity. After sunset the solar output is zero and the campus load rises to its evening peak, say 600 kW. Both 400 kW sets must then run, sharing about 300 kW each, with the largest expected load step checked against the reserve of the two sets together.

The controller must start the second set before the solar output falls away, using the solar trend and the time of day, rather than waiting for the first set to overload. Each operating case, midday, evening and night, is written into the control philosophy with the sets that run and the loads that are supplied.

The night case, with the lowest load, checks the opposite limit: one set must not run below its minimum load for long periods, so the controller may shed nothing and instead accept a short light-load period, or use a battery to carry the smallest loads with the set stopped.

Common mistakes

  • Solar left uncontrolled.
  • Earthing lost in island mode.
  • No loss-of-mains protection.
  • Transitions never tested.

What to send us

Send your sources, loads and single-line diagram. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Values are illustrative.

Questions engineers ask

How much solar can run with generators in an island?

Only as much as the load minus the minimum output of the running generators. In the example, a 350 kW load with one 400 kW set held at 120 kW allows 230 kW of solar. The running set must also be able to pick up that solar output at once if a cloud removes it.

Why can an island lose its neutral earth?

Many sites take their neutral earth from the distribution transformer. If the island separates on the low-voltage side of that transformer, the earth stays with the grid and the island has no earthed neutral, so earth-fault protection cannot work. A switched neutral earth on the island side solves it.

Can any generator site become an island?

Not automatically. It needs a controller that manages sources, load and the grid breaker, loss-of-mains protection agreed with the distribution company, solar inverters that can be curtailed, a neutral earth that stays in place when separated and protection that works at island fault levels. The decision tool above shows which of these are missing.

What is the biggest technical risk?

Stability and protection at low fault levels, together with step response. An island has no grid to absorb sudden changes, so a cloud over the solar plant or a large motor start must be covered by the running sets or a battery, and faults must still be cleared by protection set for much lower fault currents than on the grid.

Do I need storage?

Often, but not always. A battery with a grid-forming inverter can hold the island while generators start, absorb surplus solar and cover fast changes, which reduces the spinning reserve. A site whose generators can accept the expected steps and whose controller curtails solar quickly can island without one.

Who must approve?

Typically the distribution company, and sometimes the electrical inspectorate or regulator. The application usually includes the single-line diagram, the protection settings, the interlocks that prevent backfeed and the test plan. Check the local rules and seek approval before equipment is ordered, because required protection functions can change the design.

This guide gives general principles. Feasibility needs studies and approvals.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.

CallWhatsAppEnquire