In short. Each electrical problem or project calls for particular studies, done in the right order. Most start with a load study and a short-circuit study, because coordination, arc-flash and many other studies depend on their results. Pick the situation in the decision tool above, then gather the data the study needs before asking for it.
Who this page is for: For facility managers, owners and consultants deciding which engineering study to commission.
Key facts
- Load study first, then short-circuit, then coordination.
- Motor-starting studies need generator transient data.
- Harmonic studies need measurements as well as models.
- Paralleling needs synchronising and protection studies.
- An up-to-date single-line diagram is the base of all of them.
- A study should end with clear actions.
Situation to study
| Situation | Studies |
|---|---|
| New building or plant | Load, generator sizing, short-circuit; then coordination |
| Adding generators, transformers or large loads | Load, short-circuit, coordination check |
| Unexplained tripping | Coordination and event review |
| Voltage dips on motor start | Motor starting |
| Overheating or harmonics | Harmonic measurement and study |
| Paralleling sets or with the grid | Synchronising, short-circuit, protection |
| Upgrading switchgear | Short-circuit and coordination |
Worked example: a factory expansion (illustrative)
| Order | Study | Answer it gave |
|---|---|---|
| 1 | Load study | Demand rises from 650 to 900 kW |
| 2 | Generator sizing | Existing 1000 kVA set (800 kW) too small; add a second set in parallel |
| 3 | Short-circuit | Main board rating still adequate with both sets |
| 4 | Coordination | Two feeder settings changed for generator supply |
Doing the coordination study first would have meant redoing it once the second set was added. See short-circuit studies and protection study screening.
Do not commission a coordination study before the short-circuit study. Settings without known fault levels are guesses.
Study planning sheet
The actual programme run on the same pharmaceutical formulation block, in the order it was run. The worked example above orders four studies for a factory expansion; this sheet is nine studies on a site that started not with a project but with a complaint, and the order was set by what each study needed rather than by what anybody wanted to know first.
| Study | Data needed | Data ready? | Order |
|---|---|---|---|
| Symptom record | A fortnight of logged events with time stamps and what was running | No. Started from nothing on 11 February | 1 |
| Load study at the main incomer | A week of logging through a production week | Yes, meter already fitted | 2 |
| Load list and maximum demand | Nameplates, efficiencies, power factors, duty and criticality | Partly. Two loads are still estimates and are marked as such | 3 |
| Motor starting screen | Motor data, starter types, what runs during each start, and the candidate set sizes | Yes, after the starters were read off the machines rather than the drawing | 4 |
| Generator sizing and plant options | The demand figure, the dip limit, and the starting screen’s verdict on each candidate | Yes | 5 |
| Priority register | The load list, plus a dependency trace signed by operations and quality | Yes, and it found a fourth critical load | 6 |
| Load shedding and restoration scheme | The register, and which loads are separately switchable | Yes | 7 |
| Black-start dependency walk | A physical walk with somebody who opens the panels | No. The instrument air dependency was found during the walk itself | 8 |
| Harmonic measurement at sub-board 2 | A week of recording with the seven drives running | No. Not yet commissioned | Still open |
Not one of these studies was chosen from a list. Each one is the previous one’s output turned into a question. The symptom record produced three faults; one of them sent the programme to the motor-starting screen. The screen could not say which plant to buy, but it could say which candidates failed, and that constraint is what the sizing study at order 5 was actually solving against. The register at order 6 then changed the shedding scheme at order 7 and sent the walk at order 8 looking for a dependency nobody had asked about.
Order 4 before order 5 looks wrong and is the most useful line on the sheet. The dip a motor causes depends on the generator, so how can the starting screen precede the sizing? Because it is not run once on the chosen plant; it is run across every candidate, and its output is a list of plants that fail rather than a dip figure. Run the other way round — buy the set, then check the starts — and the site discovers after delivery that its motor needs a soft starter or a larger machine, which is the sequence that produces an oversized plant running at 40%.
The third column is where a programme is kept honest, and four of its nine entries are not a plain yes. Row one says no because the record did not exist: the programme began by creating its own first input, which is what a site has to do when it starts from a complaint rather than from a project.
Row three is marked partly ready because two loads on the list are estimates rather than measurements; that is not a reason to stop, it is a reason to write it down, and it means any later finding that turns on those two loads has to be re-examined before it is acted on. Row eight says no for a different reason again: the walk was not waiting for data, it was generating it, and what it generated changed a register that had already been signed. Row nine has simply not been done.
Row nine is the one still open, and it is deliberately left on the sheet rather than filed somewhere else. The first evidence for it — a neutral conductor at 61 degrees with seven drives running and no process load — is in the symptom record from 19 February, which makes it the oldest unanswered question in the whole programme. A planning sheet that quietly drops the studies nobody commissioned is a sheet that flatters the project. This one shows the gap, with the date it opened.
One ordering rule is worth stating because it is the one most often broken. Nothing that produces a setting may run before the study that produces the fault level it will be set against, and nothing that produces a fault level may run before the plant is chosen. That is why sizing sits at 5 and everything that touches protection sits after it. Settings calculated against a plant that then changes are not conservative or approximate; they are simply settings for a different site.
The whole programme took eleven weeks, of which three were the symptom record and one was the load study — four weeks of waiting and watching before a single calculation. That ratio is normal and it is the part clients find hardest to accept. The alternative, which this site had already tried, was buying a stabiliser for a problem that turned out to be two voltage regulators set differently.
What each study answers
| Study | Question it answers | Typical trigger |
|---|---|---|
| Load flow | Are voltages and loadings acceptable in every operating state? | New loads, new sources, voltage complaints |
| Short circuit | Can every breaker and busbar withstand and interrupt the fault current? | Added generators or transformers, paralleling |
| Protection coordination | Does the device nearest a fault trip first, on mains and on generator? | Nuisance or wrong tripping, new sources |
| Arc flash | What energy would an arc release where people work? | Safety programme, live work, changes to protection |
| Motor starting | Will the voltage dip during a start upset other loads or stall the motor? | Large motors on generator, new pumps or fans on site |
| Harmonics | Is distortion within limits, and is there a resonance risk? | Drives, UPS, capacitor failures, overheating neutrals |
| Earthing | Are touch and step voltages and fault paths safe? | New substation or generator, high earth readings |
| Transient stability | Will paralleled sets stay in step after a fault or load loss? | Multi-set plants, grid paralleling |
Most sites need only two or three of these at any one time. The trigger in the right-hand column is usually what brings the question to light, and it is the best guide to which study comes first.
Collecting the data without wasting a visit
Studies fail most often because the data is incomplete or out of date. A single planned survey can collect almost everything: transformer nameplates and impedances, generator data sheets with reactances, cable sizes, lengths and routes, breaker types and protection settings, motor ratings and starting methods, and logged load at the main incomers. Photographs of each nameplate and relay setting screen avoid transcription errors. Where a value cannot be found, the assumption used is written into the report together with its effect on the result, so the reader knows which conclusions depend on it.
Why generator supply needs its own case
A site that has been studied on mains supply alone can still fail on generator. A generator supplies far less fault current than the grid, and that current falls within a few seconds, so breakers that trip quickly on mains may be slow on generator. Voltage dips during motor starts are deeper because the source is weaker, and harmonic currents create more voltage distortion. Every study that matters for the site is therefore run for both sources, and for any arrangement where sets run in parallel with each other or with the grid.
What a useful study report contains
- A clear statement of the question asked and the operating cases studied.
- The network model, with every data source and assumption listed.
- Results in tables and diagrams that a site engineer can read without the software.
- Recommended settings or changes, ranked by importance and cost.
- A list of what to verify on site before the recommendations are applied.
Settings recommended by a study are applied, tested and recorded, and the study is updated whenever sources, transformers or major loads change.
Common mistakes
- Studies in the wrong order.
- Out-of-date single-line diagram.
- No generator data.
- Reports without actions.
What to send us
Send your situation and single-line diagram. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. The example is illustrative.
Questions engineers ask
Do I need a study for a small single-generator site?
Often a sizing check, a motor starting check and a review of protection on generator supply are enough. A full set of studies is justified when there are paralleled sets, large transformers, switchgear near its fault rating, many drives or repeated unexplained trips, because those are the cases where errors become costly.
Why did protection work on mains but not on generator?
A generator supplies much less fault current than the grid, and that current falls within seconds, so breakers set for mains fault levels may trip slowly or not at all. The coordination study must include generator supply, and settings are chosen so faults clear quickly on both sources.
How long does a study remain valid?
Until something important changes: a new source, a larger transformer, changed cables, new large motors or drives, or replaced protection devices. Many owners also review studies every few years, because small changes accumulate. Each update is recorded with the date and the changes made to the network model.
What should I send to start a study?
The single-line diagram, transformer and generator nameplates, cable sizes and lengths, breaker types and protection settings, motor ratings with starting methods, and logged demand at the main incomers. Photographs of nameplates and relay screens are ideal. Missing items are listed so that a survey can collect them.
Which study should I do first?
Validate the diagram and data, then load flow and short-circuit as the base for the rest. Coordination, arc-flash, motor starting and harmonic studies all depend on an accurate network model and correct fault levels, so errors at this stage spread quietly into every later study and its recommendations.
Do I need all of these?
No. Choose by the problem. Many sites need only a few. A site with breakers tripping on generator supply needs a coordination review, one with flickering lights during motor starts needs a motor starting study, and one with overheating cables needs a load and harmonic survey, rather than every study at once.
How accurate must the data be?
As accurate as the decision requires. Studies are only as good as their inputs. Cable lengths and sizes, transformer impedance, generator reactances, protection settings and actual loads are verified on site, and any assumption that cannot be checked is stated clearly in the report with its effect on the result.
Can studies be done for an existing site?
Yes, with a survey to verify the as-built system. The survey compares the drawings with what is actually installed, records nameplates, cable details and relay settings, and measures loads, because existing sites very often differ from their drawings after years of small changes and repairs.
This guide gives general principles. Study scope should be defined for your project.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.