In short. Choose the transfer method from the break the load can tolerate. If a break of about 10 to 15 seconds is acceptable, an automatic transfer switch with a mains-failure panel and a generator is enough. If the load needs a switch within milliseconds between two live, synchronised sources, use a static transfer switch. If no break is acceptable, use a UPS, often with a generator behind it.
Who this page is for: For facility managers and consultants choosing between an ATS, a static switch and a UPS.
Key facts
- ATS with a generator: break of about 10–15 seconds.
- Static switch: milliseconds, but needs two live sources.
- UPS: no break; batteries bridge to the generator.
- A static switch does not create a source; it chooses between two.
- Many sites combine all three.
- Each must be coordinated with the others.
Worked example: three loads on one site (illustrative)
| Load | Break tolerated | Sources | Method |
|---|---|---|---|
| Water pumps and lighting | 10 seconds or more | Mains and generator | ATS with mains-failure panel |
| Single-cord network switches | Under a quarter cycle (a few milliseconds) | Two UPS outputs | Static transfer switch |
| Control system and servers | None | Mains and generator | Online UPS, generator behind it |
See static transfer switches, transfer coordination and UPS capacity.
Do not install a static transfer switch where there is only one live source. With mains gone and the generator still starting, it has nothing to switch to.
What each device does
| Device | Job | Limit |
|---|---|---|
| ATS | Moves the load between mains and generator | Load sees a break |
| Static transfer switch | Fast choice between two live sources | Sources must be in phase |
| UPS | Keeps the load running with no break | Battery time limited |
Load sheet
The transfer decisions for the same pharmaceutical formulation block. The worked example above picks three methods for three loads on a site with two UPS outputs available; this site has only mains and a generator, which rules one of the three devices out before the sheet begins and makes the remaining question sharper than it looks.
| Load | Break tolerated | Sources available | Method |
|---|---|---|---|
| Environmental monitoring and batch records | None | Mains and generator, one of each | Online UPS, generator behind it |
| AHU drive control supplies and the clean room control system | None | Mains and generator | The same UPS. Added after the first transfer test |
| L-01 clean room lighting and small power | 10 s | Mains and generator | Changeover with a mains-failure panel |
| AHU-01 to AHU-06 power circuits | 30 s | Mains and generator | Changeover. The drives ride the transfer out only while their DC bus holds |
| AC-01 compressed-air plant | 4 min | Mains and generator | Changeover, restarted by the sequencer at step 2 on its soft starter |
| CH-01 chiller, P-01 and P-02 | 15 min | Mains and generator | Changeover, restarted at step 3 |
| PR-01, PW-01 and W-01 | 30 min or more | Mains and generator | Changeover. Not restarted on generator; shed at transfer |
The third column is the same on every row, and that is the finding rather than an oversight. This site has one mains supply and one generator plant, so there are never two live sources to choose between, and a static transfer switch has nowhere to go: at the moment it would be wanted, the mains is gone and the generator has not started. The device is excellent and it is not applicable here, which is a better answer than fitting one and discovering it during the first real outage.
Row two is the row that was not on the first version of this sheet. The AHU power circuits tolerate thirty seconds, so they sit on the changeover like everything else, and that looked settled until the first witnessed transfer: the fans came back in eleven seconds and three of the six drives did not. Their control electronics had dropped out with the supply and were sitting in a fault state waiting for a manual reset. The power tolerated the break and the control did not, and nothing in the first column had distinguished them.
Separating a drive’s control supply from its power supply costs a few hundred watts behind the existing UPS and it changes the restoration from a manual intervention to nothing at all. It is also the kind of item that is almost free at design stage and awkward afterwards, because the control terminals have to be re-fed on six machines in a running clean room. The lesson generalises past drives: anything with a processor in it needs its own row on this sheet, read separately from the motor or heater it is attached to.
The second column is doing work that the register behind it did first. Four minutes against the motor is not a comfort figure, it is the measured time the air receiver holds the dampers open, and it is the reason the motor is restarted at step 2 rather than with the rest of the utilities. Fifteen minutes against the chiller is the room temperature drift. Thirty seconds against the air handling is the pressure cascade. Every one of them came from the process, and the sheet is only as good as that column.
One decision this sheet deliberately leaves where it is. The clean room lighting at ten seconds sits on the changeover rather than on the UPS, which means an operator with a batch open does stand in the dark for about eleven seconds. Putting 70 kW of lighting behind the UPS would need a far larger unit and a far larger battery room, and the plant’s own judgement is that eleven seconds of emergency lighting is tolerable where eleven seconds without monitoring is not. That is written here so that the next person to ask is told why, rather than being told it was never considered.
Transfer times compared
| Arrangement | Typical break seen by the load | What it depends on |
|---|---|---|
| ATS with a mains-failure panel and a generator that must start | About 10 to 15 seconds | Mains-failure delay, engine start, voltage build-up and the transfer itself |
| ATS between two sources that are both already live | A fraction of a second for open transition | Switch mechanism and any deliberate delay for motor loads |
| Static transfer switch between two live, synchronised sources | A few milliseconds, around a quarter of a cycle | Detection time and the phase relationship of the sources |
| Online UPS | None | Battery time and the UPS staying within its ratings |
The figures are typical, not guarantees. The installed equipment is timed at commissioning, and that measured figure is what the load list is checked against.
Dual-cord and single-cord equipment
Much IT equipment has two power supplies, each able to carry the whole load. Fed from two separate UPS outputs, A and B, such equipment rides through the loss of either side without any transfer device at all. Single-cord equipment has only one supply, so it needs a static transfer switch at the distribution level, or a small rack transfer switch, fed from the same A and B outputs. Counting single-cord loads early tells you whether a static switch is needed and how large it must be.
| Equipment | Fed from | Transfer device |
|---|---|---|
| Dual-cord servers and storage | UPS A and UPS B, one cord each | None needed |
| Single-cord network switches | UPS A and UPS B through a static or rack transfer switch | Static or rack transfer switch |
| Cooling for the room | Generator-backed board through the ATS | ATS; the room tolerates the short break if the restart is staged |
How the three devices work together in an outage
- Mains fails. The UPS carries the critical load on battery at once; the ATS waits for its mains-failure delay so a brief dip does not start the set.
- The generator starts and builds voltage, and the ATS transfers the generator-backed board.
- The UPS sees its input return from the generator and walks back onto it gradually, so the generator does not see the full UPS load and battery recharge as one step.
- Cooling and other loads restart in stages set by timers, keeping each step within the generator’s acceptance.
- When mains returns and has been stable for the set delay, the ATS retransfers and the generator cools down before stopping.
Each step is a setting in a different panel, often from different suppliers. The coordination is written down as one sequence and proved in a witnessed test, because each device can work perfectly on its own and the sequence still fail.
The neutral question
Where the generator neutral is earthed at the set and the mains neutral at the transformer, the ATS must switch the neutral as well as the phases, so a four-pole switch is used. Otherwise the two sources share a neutral path, earth-fault current divides unpredictably and earth-fault protection can mis-operate. The same question applies to a static transfer switch and to the bypass paths around a UPS, and it is settled on the single-line diagram before the equipment is ordered.
The witnessed test switches off the incoming mains at the main breaker, with the site informed, and records the time from failure to generator supply, the moment the UPS returns to its input, the order and spacing of restarts, and the retransfer when mains is restored. The record shows each setting doing what it was meant to, and it becomes the reference for every later test after equipment is added or replaced.
Keeping that test record beside the single-line diagram means the next change to the site starts from facts rather than from memory.
A copy of the sequence, the measured times and the settings of each panel is also given to the site team, so the people on shift know what a normal outage looks and sounds like and can recognise at once when something has gone wrong.
Common mistakes
- Static switch with one source.
- UPS where a short break is fine.
- Devices set without coordination.
- Single-cord loads forgotten.
What to send us
Send your loads and how long each can be without power. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. The example is illustrative.
Questions engineers ask
Do dual-cord servers need a static transfer switch?
No. Equipment with two power supplies, each fed from a separate UPS output, rides through the loss of either side without any transfer device. Single-cord equipment needs a static or rack transfer switch fed from both outputs, so counting single-cord loads early tells you whether one is needed.
What happens in the first minute of an outage with UPS, ATS and generator?
The UPS carries the critical load on battery at once, the ATS waits for its mains-failure delay, the generator starts and the ATS transfers, then the UPS walks back onto the generator gradually while other loads restart in timed stages. Each step is a setting, proved together in a witnessed test.
Do I need both ATS and STS?
Only if you have loads that need a millisecond transfer and two live sources for it to choose between. An ATS moves the main board between mains and generator; a static switch chooses between two live, synchronised sources such as two UPS outputs. Many sites need only the ATS and a UPS.
Can a UPS replace an ATS?
No. A UPS bridges the gap with its battery, but something still has to connect the generator to the board when it starts. The ATS does that and the UPS covers the seconds in between, so the two work together rather than replacing each other.
When is a four-pole ATS needed?
When the generator neutral is earthed at the set and the mains neutral at the transformer. Switching the neutral with the phases keeps one neutral-to-earth bond per source, so earth-fault current returns by a predictable path and earth-fault protection operates correctly on both supplies, mains and generator.
What transfer time can an ATS achieve?
With a generator that must start, about 10 to 15 seconds from mains failure to restored supply. Between two sources that are both already live, an open-transition transfer takes a fraction of a second. The installed switch is timed at commissioning and that figure is used.
This guide gives general principles. Selection needs a design review.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.