ATS, STS and UPS Transfer Coordination

How automatic transfer switches, static transfer switches and UPS systems work together: transfer timing, sequence, retransfer, synchronism and the settings that avoid double interruptions.

In short. A UPS, a static switch and an automatic changeover act on very different time scales: the UPS with no break, the static switch in milliseconds, the changeover in seconds, and the return to mains in minutes. Each must be set with the others in mind. If the settings disagree, a UPS can stay on battery while the generator runs, or a transfer can drop the load. Coordinate the settings on paper, then prove them with a full mains-failure test.

Who this page is for: For commissioning engineers, facility managers and consultants setting up UPS, static switch and changeover systems to work together.

Key facts

  • UPS to battery: no break. Static switch: milliseconds. Changeover: seconds.
  • The changeover’s failure-confirmation delay should ignore short dips.
  • The UPS should ramp its input onto the generator gradually.
  • UPS bypass synchronising limits must suit generator frequency swings.
  • Return to mains should wait for a stable supply.
  • Test the full sequence on load, including the return to mains.

Worked example: a mains failure sequence (illustrative)

TimeEvent
0 sMains fails; UPS carries the load from battery with no break
3 sChangeover confirms the failure and starts the generator
about 11 sGenerator at voltage and frequency; changeover connects it
11–30 sUPS ramps its input onto the generator gradually instead of in one step
Mains returnsChangeover waits about 5 minutes of stable mains, then transfers back
After returnGenerator runs unloaded to cool down, then stops

A common problem

SymptomCauseFix
On generator, the UPS kept showing “bypass not available”The UPS synchronising window was ±0.5 Hz; the generator swung between 49.2 and 50.8 Hz on load stepsWindow widened to about ±1 Hz with a slow slew rate; generator governor checked

The load stayed up, but any overload or inverter fault would have dropped it, because the bypass was blocked. See static transfer switches and changeover studies.

Do not set UPS, static switch and changeover timings separately. A setting that suits one device on mains can block another on generator.

Transition types

TypeBehaviour
Open transitionShort break; UPS covers it
Delayed transitionPause lets motors slow down before reconnection
Closed transitionBrief paralleling; needs synchronising and utility permission

Coordination sheet

SettingValueChecked on generator?
Mains failure confirmation delay  
UPS input ramp time  
UPS synchronising window  
Return-to-mains delay  

Every timer in the sequence, on one sheet

A mains failure and the return to mains pass through timers in at least four devices: the changeover controller, the generator controller, the UPS and the static transfer switch. Each timer is usually set by a different person at a different time, and the sequence works only if they fit together. Writing them all on one sheet, in the order they act, with the rule each must obey, is the most effective coordination check there is.

TimerDeviceTypical settingRule it must obey
Mains failure confirmationChangeover controller2 to 5 sLonger than the utility’s first reclose dead time, where that is known; shorter than the UPS can comfortably ride through
Warm-up before transferGenerator controllerA few seconds, or none for emergency dutyShort enough to keep total time on battery well inside UPS autonomy
Walk-in delay and walk-in timeUPSDelay of a few seconds, ramp of 5 to 15 sStaggered between UPS units; long enough for the set to recover from the transfer
Retransfer delaySTSA few seconds after the preferred source is healthyShorter than the UPS bypass would take to give up, so that the load returns cleanly
Mains return confirmationChangeover controllerSeveral minutesLong enough to prove the mains stable, and to let the UPS battery recharge partly
Cool-downGenerator controller3 to 5 minutes off loadRuns after retransfer; never shortened to save fuel

The settings shown are typical starting points; the rules are what matter. Read down the table and check each rule against the actual settings of each device. Most coordination failures found this way are not exotic: a UPS walk-in that starts before the generator has recovered from the transfer, two UPS units ramping together, or a mains-return delay so short that the site returns to a supply that fails again within a minute.

Two STS sources behind the same changeover

A static transfer switch protects the load only if its two sources fail independently. A common design error places both STS sources downstream of the same automatic changeover — for example, two UPS units both fed from one generator-backed board. When the mains fails, both UPS units go to battery together and the STS has nothing different to transfer to; when the changeover operates, both sources see the same break. The STS then adds a component without adding resilience against the events it is supposed to cover.

Trace each STS source back to the point where the two paths first share a component, and write it down. If the shared point is the changeover, the generator or the main switchboard, the STS covers failures downstream of that point — a UPS fault, a breaker opening — but not failures at or above it. That may be acceptable if the shared point is itself redundant; it should be a deliberate decision, not a discovery.

Faster devices downstream, slower upstream

A well-coordinated system responds to a disturbance from the load outwards: the device nearest the load acts first and fastest, and the devices upstream act only if the disturbance persists. The UPS rides through a dip on its battery within milliseconds without any other device moving. The STS transfers within a quarter to half a cycle if one source fails outright. The changeover acts only after seconds, once the failure is confirmed. If an upstream device acts faster than a downstream one — a changeover that transfers on a dip the UPS was already covering — the result is unnecessary switching, each switching event a small risk of its own.

The same principle applies to the return. The mains-return confirmation is the slowest timer in the system so that every downstream device has settled on the generator before the next disturbance arrives. A sequence that returns to mains quickly and unsettles every device twice in a few minutes has inverted the order and gained nothing for it.

The voltage and frequency windows must nest too

Each device also decides whether a supply is acceptable by comparing it with a window of voltage and frequency, and the windows must fit together in the same way as the timers. On generator, the frequency moves on every load step; a device whose window is narrower than that movement will treat the generator as failed at the worst moment.

WindowDeviceRelationship it needs
Rectifier input windowUPSWider than the generator’s frequency and voltage movement on its largest load step, so the UPS stays on the set
Bypass synchronisation windowUPSWide enough to keep the bypass available on generator, narrow enough not to pass a poor supply to the load
Source acceptance windowSTSConsistent with the UPS output limits, so the STS does not reject a source the UPS considers healthy
Generator-healthy windowChangeover controllerNarrow enough to stop transfer onto a set still running up, wide enough to accept it once settled

Record the actual windows beside the generator’s measured behaviour on a load step, taken from a recording during a test. If any window is narrower than the generator’s movement, the device will switch to battery, to bypass or to its other source during normal generator operation, and the sequence will look unreliable for reasons that have nothing to do with the generator’s health.

Testing the combinations, not just the normal case

Most sites test the transfer sequence with everything in its normal state. The failures that matter happen when something is already out of normal: a UPS on bypass, an STS already on its alternate source, one generator out for service. A short matrix of tests covers the combinations that a real outage is likely to meet.

Starting stateEventExpected result
All normalMains failure and returnLoad uninterrupted; UPS on battery for the transfer; clean retransfer
UPS on maintenance bypassMains failureLoad sees the changeover break; confirm this is accepted and the load restarts
STS on alternate sourceFailure of the alternate sourceSTS returns to the preferred source within its transfer time
One generator out of serviceMains failureRemaining sets carry the critical load; non-essential load shed as planned
Generator running, on loadMains returns and fails again within a minuteNo retransfer until the mains has proved stable

Not every combination can be tested every year, but each should be tested at commissioning and after any significant change, and the results kept with the coordination sheet. The second row in particular tends to surprise people: a UPS on maintenance bypass offers no protection at all, and an outage during that window drops the critical load. Knowing that, and planning maintenance windows accordingly, is part of coordination too.

Reading what happened from the event logs

After a real outage, the event logs of the changeover controller, generator controller, UPS and STS together tell the story of the sequence, if they can be lined up. Each device records its own events with its own clock, so the first step is to know how far each clock is from the others, which is why the clocks should be synchronised and checked at each service.

Lined up, the logs show the timer ladder in action: when the mains was declared failed, when the set started and was ready, when it took load, when each UPS began its walk-in, and when the mains returned. Comparing those times with the settings on the coordination sheet shows at once which timer acted as intended and which did not, and turns every real outage into a free test of the whole sequence.

Common mistakes

  • Factory settings left unchanged.
  • Testing on mains only.
  • Return to mains never tested.
  • No event logs kept.

What to send us

Send your UPS, static switch and changeover settings. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Times and settings are illustrative.

Questions engineers ask

In what order should the transfer timers be set?

From the load outwards, fastest nearest the load. The UPS rides through dips at once, the static transfer switch acts within a quarter to half a cycle, and the changeover confirms a mains failure over a few seconds, longer than the utility first reclose where known. UPS walk-ins start after the generator has recovered from the transfer and are staggered between units. The mains-return confirmation is the slowest timer, several minutes, followed by the generator cool-down.

What should be tested beyond a normal mains failure?

The states a real outage is likely to meet: a mains failure with a UPS on maintenance bypass, the failure of an STS alternate source while it is in use, a mains failure with one generator out of service, and a mains supply that returns and fails again within a minute. Each should be tested at commissioning and after significant changes. A UPS on maintenance bypass offers no protection, so an outage in that window drops the load.

Why does my UPS stay on battery when the generator runs?

The generator voltage or frequency is likely outside the UPS input window, or frequency is hunting. Check generator regulation and the UPS settings. Record generator voltage and frequency with the UPS load connected, tune the governor if frequency swings, and widen the UPS input frequency window only within what the maker permits.

Is closed transition better?

It avoids an interruption but needs synchronism and permission, and it raises fault levels momentarily. Open or delayed transition is simpler where a short break is acceptable. Where a UPS already covers the critical loads, a short open-transition break on retransfer usually causes no harm.

What is a retransfer delay for?

It waits until utility is stable, to avoid repeated transfers and unnecessary interruptions. Utility supply often fails again shortly after restoration, so the controller waits for a set period of stable voltage and frequency before retransferring, and each transfer that it avoids is one less disturbance for the loads and the UPS.

Do ATS and STS need to be coordinated?

Yes, so one does not transfer while the other is changing state and cause an unintended break. Time delays and interlocks are set so that the upstream ATS completes its transfer before the downstream STS or UPS reacts, and the whole sequence is tested together on load, since each device alone may work perfectly while the combination fails.

This guide gives general principles. Settings should be set and tested on the actual installation.