Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Cables, Busbars & Distribution

How to size and route generator cables and busbars: current, derating for Indian ambient, voltage drop with a worked example, terminations and temporary runs.

In short. Power leaves the alternator through cables, busbars, joints, breakers and panels before it reaches a motor or a server, and every element adds impedance and a thermal limit. A correctly sized generator can still fail the load because the feeder drops too much voltage during a motor start, a joint runs hot, or a rental cable is left coiled on its drum. Cable and busbar design is part of the generator system, not an afterthought.

Start with the current, then correct it

The full-load current of a three-phase generator is I = S / (√3 × V), so a 500 kVA set at 415 V delivers about 696 A and a 1000 kVA set about 1391 A. That number is the beginning of cable selection, not the end. Tabulated cable ratings assume a reference ambient, a reference installation method and a single circuit. Real installations in Telangana differ on every count: air temperatures of 45 °C in summer, cables bunched on a tray, runs buried in dry soil with poor thermal resistivity, and harmonic-rich loads that heat the neutral.

Each condition applies a derating factor, and the product of those factors against the tabulated rating gives the current the cable can actually carry. A grouping factor of 0.8 and an ambient factor of 0.87 together leave about 70% of the catalogue rating, which is why a feeder that looks generous on paper runs warm in May. The method is set out in cable sizing for generators.

Voltage drop decides whether the load works

A healthy generator can show 415 V at its terminals while a pump 150 metres away sees 385 V, because current through the cable impedance costs voltage. For a balanced three-phase circuit the drop is calculated as follows.

ΔV = √3 × I × L × (R cos φ + X sin φ)

ΔV is the line-to-line voltage drop in volts, I the current in amperes, L the one-way route length in kilometres, R and X the cable resistance and reactance in ohms per kilometre at operating temperature, and cos φ the load power factor. Worked example (illustrative): a 500 kVA set feeds a panel 80 metres away at 696 A and 0.8 power factor through two parallel aluminium cables with a combined R of 0.10 Ω/km and X of 0.08 Ω/km.

The drop is 1.732 × 696 × 0.08 × (0.10 × 0.8 + 0.08 × 0.6), about 12.3 V, or 3% of 415 V. That is acceptable for a main feeder. Double the distance and the drop reaches 6% before any downstream circuit has been added, and during a direct-on-line motor start the current, and therefore the drop, is six times larger for a second or two. Design limits of around 3% on main feeders and 5% total to the load are common practice, with motor-starting dips checked separately; the voltage drop guide and the screening calculator work through both.

The factors a cable schedule must record

FactorWhat to recordEffect on selection
Conductor and insulationCopper or aluminium, PVC or XLPEAluminium needs a larger section and bimetallic lugs; XLPE allows 90 °C conductors against 70 °C for PVC
Installation methodTray, trench, duct, buried, clippedChanges the base rating and the grouping factor
Ambient and soilDesign air temperature, soil thermal resistivityDerating of 10 to 20% is normal in Indian summers
Route lengthMeasured, including rises and bendsDrives voltage drop and the minimum earth-fault current at the far end
Fault withstandProspective fault current and clearing timeSection must satisfy I²t for the protection in place
Neutral and earthHarmonic content, earthing arrangementFull-size or oversized neutral for drive and UPS loads

Busbars and parallel cables for high current

Above about 1600 A, which is a single 1250 kVA set or two paralleled 630 kVA sets, cables become awkward: four or five single cores per phase, large gland plates, and current sharing between parallel cables that depends on identical length and symmetrical arrangement. Busbar trunking between the generator room and the switchboard solves the sharing problem, reduces the footprint and simplifies terminations, at a higher material cost and with its own requirements for joint torque, expansion and ingress protection.

Inside the switchboard, busbar section is governed by temperature rise under the assembly standard, treated under switchboard thermal and busbar engineering. Where parallel cables are used, they should be the same type, size and length, laid in trefoil groups each containing one cable of each phase, so that the reactance seen by each cable is equal and the current divides evenly.

Joints and terminations fail before conductors do

Most cable failures we have investigated on generator installations began at a termination: a lug crimped with the wrong die, aluminium terminated on copper without a bimetallic lug, a bolt below torque, or a gland that let monsoon moisture in. At 1000 A a joint resistance of a tenth of a milliohm dissipates 100 W into a confined space, and the resistance climbs as the joint oxidises. The defence is procedural: specified lugs and dies, torque values recorded at installation, and a thermographic survey of every termination under load in the first months and then annually.

Temporary and rental distribution

Rental power is where distribution discipline is most often lost. Long flexible runs to a site office or a pump mean voltage drop nobody calculated, cables left partly coiled on drums overheat because the inner turns cannot shed heat, distribution boards sit on wet ground and earthing is improvised. A temporary system deserves the same current, drop and fault checks as a permanent one, the drum must be fully paid out, and the earth path back to the generator neutral must be continuous. Our rental cables and distribution page describes what is supplied with a rental set and how it should be laid.

Distribution shapes protection too

A long feeder does not only drop voltage under load; it limits the fault current that reaches the far end. The earth-fault loop impedance may be high enough that the breaker protecting the feeder never sees its instantaneous pickup, and clears, if at all, on its slow thermal curve. This is why cable selection and protection coordination are done together, and why a feeder from a generator, whose fault contribution decays within cycles, is checked for minimum fault current and not only maximum.

Related photographs and videos

Industrial power distribution.
Cable engineering.
More related media (2)
Electricity distribution network.
Electrical distribution applications.

Worked example: voltage drop on a 250 kVA feeder (illustrative)

A 250 kVA set at 415 V gives about 348 A. A 60-metre route to the main board uses a 240 square millimetre copper cable with a resistance of about 0.09 ohms per kilometre at working temperature and a reactance of about 0.08 ohms per kilometre. At 0.8 power factor the three-phase voltage drop is 1.732 times 348 amperes times 0.06 kilometres times the sum of 0.09 times 0.8 and 0.08 times 0.6, which is about 4.3 volts, roughly 1%. That leaves ample margin within typical limits, and the motor starting dip is checked separately with the higher starting current.

Derating factors applied in practice

ConditionEffect
High ambient temperatureLower current rating
Several cables grouped togetherLower rating for each cable
Buried in dry or poor soilLower rating due to poor heat loss
Cables in conduit or closed trenchLower rating than in free air

The factors multiply, so a cable that looks generous on its free-air rating can be undersized once all of them apply.

Testing before energising

Fire barriers and segregation

Where cables pass through walls and floors, fire barriers restore the fire rating of the wall. Power and control cables are kept apart, and generator feeders serving life safety loads follow routes that a fire elsewhere cannot easily reach.

Temporary and rental cabling

Cables for rental sets lie on the ground or cross roadways, where vehicles, water and heat can damage them. Armoured or heavy-duty flexible cables, cable protectors at crossings, correctly rated connectors and earth leakage protection on outgoing circuits keep temporary distribution safe. Each run is inspected daily while the hire lasts.

Common mistakes

What to send us

Send the route length from generator to switchboard, the generator rating, the installation method and any existing cable schedule, the largest motor on the feeder with its starting method, and photographs of the cable route, the termination box at the generator and the switchboard incomer. For rental, tell us the distances to each point of use. Use the application engineering enquiry page.

Questions engineers ask

How is voltage drop calculated on a generator feeder?

Multiply 1.732 by current, route length and the sum of resistance times power factor and reactance times sine. In the illustrative 250 kVA case, 348 A over 60 metres of 240 square millimetre copper gives about 4.3 volts, roughly 1%, before checking motor starting, which usually sets the tighter limit on cable size.

Which derating factors reduce a cable current rating?

High ambient temperature, grouping with other cables, burial in dry or poor soil and installation in conduit or closed trenches. The factors multiply together, so a cable that looks generous on its free-air rating can be undersized once all of them are applied, which is why each factor is written into the cable schedule.

What tests are done on generator cables before energising?

Insulation resistance between phases and to earth, continuity and phase identification at both ends, torque checks of lugs and busbar joints to maker values, and a thermal scan after the first period on load to find any connection running hot. Results are recorded as the baseline for later checks.

How should temporary cables for rental generators be protected?

Use armoured or heavy-duty flexible cables, protectors where they cross roadways, correctly rated connectors and earth leakage protection on outgoing circuits, and inspect each run daily during the hire, because ground-laid cables face vehicles, water and heat. Damaged sections are replaced at once rather than taped, and routes are kept clear of standing water.

What voltage drop is acceptable on a generator feeder?

Common design practice holds the main feeder to about 3% and the total from generator to the furthest load to about 5% at full load. Motor-starting dips are judged separately against what the connected equipment tolerates, usually 10 to 15% at the motor terminals. The governing design standard for the project sets the formal limit.

Is aluminium cable acceptable for generator feeders?

Yes, and it is widely used in India for cost reasons. It needs roughly one size larger than copper for the same current, bimetallic lugs at every copper interface, and more careful crimping and torque control. For short, high-current runs inside a generator room copper is often still preferred because of the space it saves.

When should I use busbar trunking instead of cables?

Generally above 1600 A, where cables would need four or more cores per phase, where the route is straight and short, or where the generator room sits directly beside the switchboard. Below that, cables are cheaper and easier to modify. Trunking also helps where future generators will be added, because tap-off points can be built in.

Why does the neutral need to be full size on generator circuits?

Because the loads most often placed on generator supply, UPS systems, drives, LED lighting and IT equipment, draw third-harmonic currents that add in the neutral rather than cancel. The neutral current can approach or exceed the phase current. A full-size neutral is the minimum; where such loads dominate, a neutral of larger section than the phases is specified.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.

CallWhatsAppEnquire