Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Events & Temporary-Infrastructure Power

Generator power for events and temporary infrastructure: load scheduling by programme, redundancy for stage and broadcast, noise, earthing and public safety.

In short. Event power is temporary but it is not improvised. The load changes between build, rehearsal, show and strike, the equipment is electronic and sensitive to voltage and frequency, the public walks past the cables, and a failure happens in front of everyone. The engineering answer is a programme-based load schedule, silent generators with redundancy for the loads that cannot fail, clean distribution with residual current protection and earthing, and a named person responsible for the installation throughout.

Loads that change with the programme

An exhibition, wedding, concert or corporate event has four distinct electrical phases, and the load in each is different. During the build, the demand is tools, work lighting and the first air-conditioning units in the marquee. During rehearsal and sound check, the stage, lighting rig and LED screens come alive for the first time, often all at once. During the show, the load is at its peak but is largely known.

During strike, it falls back to work lighting and tools, often at night. A load schedule built around this programme separates peak simultaneous demand from equipment that never runs together, and avoids sizing the whole event for a figure that only occurs for two hours; the generator sizing guide explains diversity. The event power rental page covers the equipment side.

Load groupCharacterWhat it needs from the generatorTolerable interruption
Stage audio and lighting consoles, LED walls, broadcastElectronic, nonlinear, low inertiaStable voltage and frequency, low harmonic distortion, no breakNone during the show
Moving lights, dimmers, amplifiersNonlinear, high crest factor, swings with the showAlternator with margin, oversized neutralSeconds, but visible
Air conditioning and chillers for marqueesLarge motors startingStarting capacity, often a separate setMinutes
Catering, vendors, temporary officesMixed resistive and small motorOrdinary supply with residual current protectionMinutes
Emergency lighting, PA for announcements, CCTVSmall, life-safetyIndependent supply or UPSNone

Why electronic loads dislike generators

Stage and broadcast equipment is powered through switch-mode supplies and dimmers that draw current in short pulses rather than a smooth sine wave. On the grid this passes unnoticed, because the source impedance is tiny. On a generator, the same current distorts the alternator’s output voltage, and the equipment that caused the distortion is the equipment most upset by it: LED walls flicker, audio picks up hum, and video switchers reboot.

The remedy is an alternator with a low sub-transient reactance and a rating margin for the nonlinear load, in practice a generator loaded to no more than 60 to 70% by electronic equipment, a full-size or oversized neutral conductor to carry the third-harmonic current, and the air-conditioning units kept on a separate set so their starts do not reach the stage supply. The UPS and nonlinear load guide explains the alternator side, and a small online UPS on the consoles and broadcast chain covers the brief interruptions that even a good generator installation cannot rule out.

Redundancy for the loads that cannot fail

For a concert, televised event or a wedding where the ceremony is timed to the minute, the stage supply should not depend on one engine. The usual arrangement is two generators of equal rating feeding the stage distribution through a changeover panel, with the second set running at no load during the show so that the changeover takes seconds rather than the minute a cold start would need.

For larger productions the two sets run synchronised in parallel so that a failure of either leaves the other carrying the load with no interruption at all, which is the only arrangement that is truly seamless. The generator-to-generator transfer page describes both schemes. Whichever is chosen, the changeover should be tested at the sound check, not discovered during the headline act.

Noise, exhaust and placement

Generators at events must be heard by nobody and reached by no one who should not. CPCB noise norms require diesel generators up to 1000 kVA to be supplied in acoustic enclosures limited to 75 dB(A) at one metre, and event sites usually need better than that near the audience, which means placing the sets as far from the stage and seating as the cable run allows and orienting the exhaust and radiator discharge away from the public and from marquee air intakes.

Exhaust contains carbon monoxide; a generator placed against a marquee wall with the exhaust discharging under the canvas edge is a known cause of illness at events. Fence the generator compound, keep the fuel store within it, and keep a fire extinguisher and spill kit at hand. The acoustic engineering guide covers attenuation at the source and along the path.

Distribution, earthing and public safety

Event distribution is a temporary low-voltage installation and must be treated as one under the CEA safety regulations. RCD protection, source earthing and bonding are specified by a competent electrical designer for the documented temporary distribution arrangement, under the applicable regulations. That normally means 30 mA residual current devices on final circuits accessible to the public, vendors and crew, one defined earthing and neutral-bonding point for the generator that suits the changeover and distribution arrangement, with its earth resistance and the earth-fault loop measured, and bonding of exposed metal structures within reach, such as stage scaffolding, trussing and barriers near cables, as the design requires.

Cables crossing public walkways go under cable ramps or overhead; cables near catering and wet areas need appropriate ingress protection. Before the public arrives, one person should walk the whole installation with the single-line diagram, test each residual current device and record the earth resistance and earth-fault loop readings before the installation is used. The temporary distribution page lists the panel and cable arrangements that make this practical.

Fuel, runtime and responsibility

An event generator may run 18 hours a day for a week. A 125 kVA set at 60% load uses roughly 18 to 20 litres an hour, so a three-day event with two sets needs well over 2000 litres on site or a refuelling plan that does not involve a tanker crossing a crowded venue (illustrative).

Agree in writing who may request additional load, who operates the sets, what the response is to an alarm, and when the installation is handed back; the rental and temporary power page describes the usual scope. The event manager should know the supported demand and the condition, such as a new vendor or a bigger LED wall, that requires the installation to be reviewed before it is connected.

Estimating event load by period (illustrative)

A corporate conference with an evening dinner shows how load changes through the programme. Each period is planned with its own supply arrangement.

PeriodMain loadsDemand
BuildWork lights, tools, rigging motorsAbout 20 kW
Conference sessionsSound, projection, LED wall, stage lighting, air-coolingAbout 90 kW
Dinner and entertainmentSound, effects lighting, catering, air-coolingAbout 120 kW
BreakdownWork lights, toolsAbout 15 kW

The peak of 120 kW is about 150 kVA at 0.8 power factor, split between a show supply of about 50 kW and a general supply of about 70 kW. Two sets sized for those feeds, with a backup for the show, give separation and resilience that one large set cannot.

Why LED walls and dimmers need care

LED walls, moving lights and dimmers draw current in short pulses rather than smooth waves. On a generator, that distorts the voltage more than on a mains supply, which can cause flicker, hum and controller resets. Keeping these loads on their own set or feeder, choosing a set with headroom over the electronic load, and keeping catering and cooling on a separate supply removes most of the problem.

Who is responsible for what

TaskUsually done by
Load list from each vendorEvent organiser
Set sizing, placement and distribution planPower supplier with the organiser
Earthing, residual-current protection and testingPower supplier
Fuel during the event and refuelling safetyAs agreed in writing
Running the sets and switching to backupNamed operator for the live period

Writing these responsibilities down before the build avoids the most common event failure: everybody assuming somebody else was watching the fuel.

Backup that actually works on the night

A backup set that has never been switched to is a hope, not a plan. For the show supply, the backup is connected through a changeover the operator can work quickly, both sets are fuelled, and the transfer is rehearsed once during the sound check. The operator knows which loads move first, how long the transfer takes, and who to tell in the show team. A short note taped to the changeover with these steps turns a stressful moment into a routine action.

Checks before doors open

Common mistakes

What to send us

Send the event programme with dates and daily hours, the equipment list for stage, lighting, screens, air conditioning and catering with their kW, and a site plan showing the stage, seating, marquees and where generators and cables can go. Tell us which loads must not fail, the noise constraints of the venue and whether broadcast is involved. Send your event power requirement.

Questions engineers ask

How is event power estimated by period?

Each part of the programme is listed with its loads: build, sessions, dinner and entertainment, and breakdown. The highest period sets the size, split into separate show and general supplies. For a conference peaking at 120 kW, about 150 kVA, two sets sized for the show and general feeds with a backup for the show give better resilience than one large set.

Who is responsible for fuel and switching at an event?

That is agreed in writing before the build. The organiser supplies vendor load lists, the power supplier plans the sets, distribution, earthing and protection, fuel and refuelling safety are assigned to a named party, and a named operator runs the sets and switches to backup during the live period.

How many kVA does a wedding or corporate event need?

Add the power each vendor needs for the busiest period, allow for diversity and the starting of cooling equipment, and divide kW by 0.8 for kVA. Then split the total into separate supplies for sound and lighting and for catering and cooling, adding a backup for the show supply if an interruption would stop the event.

Do events need two generators?

If a power loss would stop the show or create a safety issue for a crowd, yes. The second set needs a defined changeover, its own fuel and a named operator, and the transfer should be rehearsed once during the sound check so everyone knows what it looks and sounds like.

What noise level should an event generator meet?

The limit at the boundary or the nearest neighbour set by local rules and the venue. Acoustic canopies help, but distance, barriers and pointing outlets away from people make the biggest difference. A sound meter reading at the boundary during rehearsal confirms the placement before the live period.

Why do LED walls flicker on generator power?

LED walls and dimmers draw distorted current that a generator’s alternator turns into distorted voltage, and the same equipment is sensitive to that distortion. An alternator loaded to no more than 60 to 70% by electronic loads, a full-size neutral and separation from motor starts usually cures it.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.

CallWhatsAppEnquire