In short. A telecom site runs on a minus 48 V DC plant fed by rectifiers and a battery bank, so the generator never sees the radio load directly. It sees the rectifier input, the battery recharge current and the shelter cooling, often at a remote tower with no attendant. Sizing the set for recharge plus cooling restart, planning fuel and access, and making alarms actionable matter more than the kVA figure on the canopy.
The AC to DC chain decides what the generator sees
Radio units, baseband equipment, transmission and most site electronics draw DC from a power plant at nominal minus 48 V. Rectifier modules convert the 230 V or 415 V AC input to DC, float the battery bank and carry the load. When mains fails, the battery carries the load alone until the generator starts and the rectifiers resume.
At that moment the rectifiers draw not only the site load but also whatever recharge current the plant controller allows, and the shelter air conditioners or free-cooling fans restart together with them. The generator duty is therefore rectifier load plus recharge plus cooling, with the recharge block lasting hours after a deep discharge.
Modern switched-mode rectifiers present a near unity power factor and low harmonic distortion, which suits small generators. Older plants, or sites where rectifier modules have been mixed over the years, can present lower power factor and higher input current distortion, and the alternator must be checked against that. The nameplate on the DC plant and the controller settings are the data needed; see UPS and non-linear loads for the alternator side of this.
Battery autonomy and recharge demand
Autonomy and recharge are two sides of the same calculation. A larger battery rides through more short outages without a generator start, but it also draws more recharge power when the generator finally runs.
Autonomy (h) = (C × V × DoD) / P_load; P_recharge ≈ (C × r × V_charge) / η_rect
C is battery capacity in ampere-hours, V the nominal bus voltage, DoD the usable depth of discharge, P_load the DC site load in watts, r the recharge current limit as a fraction of C, V_charge the charging voltage and η_rect the rectifier efficiency. A worked example (illustrative): a site with a 2400 W load and a 600 Ah bank at 48 V, with 80% usable capacity, has about (600 × 48 × 0.8) / 2400, or roughly 9.6 hours of autonomy.
With recharge limited to 0.1C, the rectifiers draw about (600 × 0.1 × 54) / 0.95, close to 3.4 kW for recharge on top of the 2.4 kW load. Add a 1.5-tonne air conditioner at around 2 kW running with a motor start, and the generator must carry around 8 kW running with a motor start on top. A 10 to 15 kVA set is the practical range, not the 5 kVA that the site load alone would suggest. Lithium banks accept higher recharge rates and may drive the generator size further unless the controller limits them.
Site types and what each needs
| Site type | Typical AC demand on generator | Usual architecture | Main risks |
|---|---|---|---|
| Rural ground-based tower with poor grid | 5 to 15 kW including recharge and cooling | Battery plus 10 to 20 kVA DG, increasingly solar hybrid | Fuel logistics, theft, access in monsoon, high DG hours |
| Urban rooftop site | 5 to 10 kW | Battery with shared or portable DG, structural and noise limits | Rooftop placement without structural review, acoustic complaints |
| Fibre hut or small exchange | 10 to 40 kW | Battery, AMF-controlled DG, cooling on generator | Cooling failure degrading electronics and batteries |
| Core or aggregation node | 50 to several hundred kW | N+1 DG, UPS for AC loads, dual DC plants | Transfer logic, load steps, untested redundancy |
In Telangana and Andhra Pradesh the rural tower is where most generator hours accumulate, because DISCOM outages of several hours a day in some feeders push the set into prime-like duty. Sets specified for standby ratings and run for 2000 hours a year wear out early, so the rating should follow the measured hours. See prime power generators.
Heat, dust and the unattended shelter
Batteries lose life quickly above 25 to 30 °C, and VRLA banks in a shelter whose cooling has failed in a Telangana summer can lose a large share of their design life in one season. The shelter cooling is therefore not a comfort load; it is what preserves the autonomy the whole scheme depends on. The generator must carry it, and the alarm scheme must report cooling failure as urgently as mains failure.
For the generator itself, dust loading of radiators and air filters, high ambient derating and long periods between visits shape the specification. An acoustic canopy with adequate ventilation, an oversized fuel tank with a lockable filler and a level sensor, extended-interval filtration and a controller with remote communication are the practical minimum for an unattended site. See ambient temperature derating.
Monitoring that leads to action
A displayed status is only useful if someone knows what it means and can respond. For telecom fleets the generator controller should report run, fail-to-start, low fuel, high temperature and low battery voltage into the operator’s network operations centre, with each alarm mapped to a response: a technician visit, a fuel delivery or a remote reset. Fuel level trends identify theft and leaks; running hours trigger service.
Hybrid schemes with solar and larger lithium banks cut generator hours by charging in daylight and running the set only to top up at night, but they need an energy management controller to decide when the set runs. The options are set out in solar-diesel hybrid power and remote monitoring. A tower-fleet service contract should pair the monitoring data with a planned visit schedule and a fuel audit.
Sizing a tower generator from the DC plant (illustrative)
A rooftop site carries 3 kW of radio and transmission load on a minus 48 V DC plant, with a battery bank that has discharged during a long outage and must be recharged. The generator is sized from what the rectifiers draw, plus cooling.
| Item | Working | Result |
|---|---|---|
| DC load | Radio and transmission equipment | 3.0 kW |
| Battery recharge | Charging current limit set on the rectifiers | 2.5 kW |
| Rectifier input | (3.0 + 2.5) ÷ 0.92 efficiency | About 6.0 kW |
| Cooling | Shelter AC or free-cooling fans | 2.5 kW |
| Total | 6.0 + 2.5 | About 8.5 kW |
| Generator | 8.5 kW ÷ 0.8, with margin for AC start and heat derating | 15 kVA rather than 10 kVA |
Sized for the radio load alone, the set would be overloaded at exactly the moment it is needed most: after a long outage, when the batteries are flat and the shelter is hot.
Running the generator only as long as needed
At grid-poor sites, the generator is often scheduled to run until the batteries reach a set charge and then stop, rather than running continuously. This cuts fuel and engine hours, but only if the battery bank is healthy and the controller logic is set correctly. The running hours, fuel used and battery voltage at start and stop are logged remotely, so a site whose generator runs longer each week, a sign of a weakening battery, is noticed before it fails.
Service for unattended sites
On sets we maintain, oil and filters are changed every 250 to 500 running hours or six months, whichever comes first, and coolant is replaced every year. Remote towers that run many hours reach the hour limit quickly, so services are planned from the remotely reported hour meter. At each visit the air filter, radiator, battery, belts and fuel are checked, the fuel is drained of water, and the site is left with a short record of the work done and the readings found.
Fuel security at remote sites
Fuel theft is a real cost at unattended towers. Locked tanks and caps, fuel-level sensors that report to the monitoring system, and a comparison of litres delivered with running hours and load make losses visible. A sudden drop in the level without matching running hours is investigated at once.
Shelter heat and the generator
Telecom shelters on hot rooftops and in open fields can reach temperatures that reduce battery life and push equipment towards its limits. When the grid fails, the shelter cooling restarts on the generator together with battery recharge, often in the hottest part of the day. The set must carry that combined load at the site temperature, which is why a set chosen for the radio load alone so often trips. Ventilation around the generator itself matters too: a set enclosed in a cage without airflow overheats and derates long before its rated output.
Common mistakes
- Sizing the generator for the DC site load alone. The set stalls or trips when recharge and cooling restart arrive together after the first long outage.
- Leaving the rectifier recharge limit at maximum. The generator runs overloaded for the first hours of every run and the alternator overheats in summer.
- Treating shelter cooling as optional on generator. Battery life collapses and the autonomy the design assumed no longer exists.
- Running a standby-rated set as a prime source at a poor-grid site. Oil consumption and wear rise, and the engine needs overhaul years earlier than expected.
- Collecting alarms without assigning responses. The fail-to-start alarm is logged at 2 a.m. and nobody acts until the site goes down.
What to send us
Send the DC plant rating and rectifier module details, the battery bank capacity, chemistry and age, the measured site load, the shelter cooling rating and the grid outage pattern in hours per day. Photographs of the existing generator nameplate, the controller display and the site access route tell us a great deal about what is practical. For fleets, a list of sites with hours run and fuel consumption per month lets us identify which sets are wrongly rated. Send your service and AMC requirement or ask for a site-by-site review.
Questions engineers ask
Why must a telecom generator be sized for battery recharge?
After a long outage the batteries are flat and the shelter is hot, so the generator must carry the DC load, the recharge current and the cooling together. In the example on this page that is about 8.5 kW, which needs a 15 kVA set; a set sized for the 3 kW radio load alone would trip at exactly that moment.
How is fuel theft controlled at unattended towers?
Locked tanks and caps, fuel-level sensors reporting to the monitoring system, and a comparison of litres delivered with running hours and load make losses visible. A sudden fall in fuel level without matching running hours is investigated at once, and deliveries are recorded against each site.
What size generator does a typical mobile tower need?
Most single-operator ground-based sites fall in the 10 to 20 kVA range once battery recharge and air conditioning are included, and multi-tenant sites go higher. The real number comes from the rectifier recharge limit, the cooling load and the motor start, not from the radio load alone.
Why does the generator trip a few seconds after taking load?
Usually because the rectifiers start drawing full battery recharge current together with the shelter cooling, and that combined step exceeds what the set can carry or upsets its voltage and frequency. Limiting the recharge current, soft-starting the cooling, or using a larger set solves it once the actual step is measured.
Is a solar hybrid worth it at a poor-grid site?
Where the generator runs several hours a day, a solar array with a larger battery often cuts diesel use substantially and extends the engine’s life by reducing run hours. The economics depend on outage hours, fuel delivery cost and the site’s load, so they should be screened site by site.
How often should a remote-site generator be serviced?
On our standard, oil and filters every 250 to 500 running hours or six months, whichever comes first, with coolant replaced every year. Remote towers that run many hours reach the hour limit quickly, so services are planned from the remotely reported hour meter, with water drained from the fuel at every visit.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.