In short. A data centre generator is sized and proven against the whole chain it supports, not the IT load alone. It must carry the UPS input including battery recharge, and the cooling plant with its motor and pump restarts. Its alternator must tolerate the UPS’s harmonic current, and the transfer must complete well before the UPS batteries run down. Capacity is arranged as N+1 or 2N, and readiness is proven by integrated tests throughout the site’s life.
Who this page is for: For data centre owners, facility managers and consultants sizing, upgrading or testing standby generation for server rooms, colocation halls and edge sites.
Key facts
- As a first estimate, the generator running load is about 1.6 to 1.8 times the IT load in an air-cooled facility, before redundancy.
- Battery recharge adds a step of about 10 to 25% of IT load as soon as the UPS sees generator supply.
- The alternator is chosen for the UPS’s harmonic current, often one frame larger than the engine needs.
- Chillers must restart in sequence, not together.
- N+1 is real only if fuel, controls and distribution behind the sets are also N+1.
- A resistive load-bank test does not prove UPS compatibility; an integrated test does.
The load is the whole facility, not the racks
| Load component | Typical share of IT load (illustrative) | Generator-relevant behaviour |
|---|---|---|
| UPS input at steady state | 105 to 110% | Non-linear current; distortion depends on rectifier type |
| Battery recharge after an outage | 10 to 25% extra for 30 to 120 minutes | Step increase as soon as the UPS sees generator supply |
| Mechanical cooling | 30 to 50%, higher at peak ambient | Motor starts, often several at once unless sequenced |
| Building and auxiliaries | 5 to 10% | Mostly linear; includes radiator fans and fuel pumps |
Worked example: a 500 kW IT hall (illustrative)
| Step | Working | Result |
|---|---|---|
| UPS input | 500 kW ÷ 0.95 efficiency | about 525 kW |
| Battery recharge | 15% of IT load | 75 kW |
| Cooling | 40% of IT load, Hyderabad summer | 200 kW |
| Building and auxiliaries | 8% of IT load | 40 kW |
| Running load during recharge | 525 + 75 + 200 + 40 | about 840 kW (1.68 × IT) |
| One 1000 kVA set at 0.8 power factor | 800 kW | Overloaded once the chillers are back: 840 kW on an 800 kW rating |
| Two 1000 kVA sets | Both share 840 kW at about 53% each | Fine while both run, but losing either leaves 800 kW for 840 kW |
| True N+1 | Three 1000 kVA sets (any two give 1600 kW), or two sets of at least 1250 kVA (1000 kW) each | Full load carried with any one set lost |
Two sets look like redundancy, but with one lost the survivor faces 840 kW on an 800 kW rating once cooling is running, before allowing for chiller starting current. Only the last row is N+1. Writing that check down is what turns “N+1” from a label into a fact. Build your own figures with the generator sizing guide.
Do not size the set from the IT load or the UPS output rating. Recharge, cooling and auxiliaries push the running load 60 to 80% higher, and the set is overloaded on its first real outage.
The UPS and the generator must be proven together
The UPS rectifier draws harmonic current, and that current across the alternator’s reactance distorts the bus voltage. Older six-pulse rectifiers can draw current with distortion above 30%; modern active front ends are below 5%. The alternator is chosen for the actual UPS, usually with a sub-transient reactance of 10 to 12%. The UPS input window for voltage and frequency, and its behaviour when the window is exceeded, must be checked against the set’s governor and AVR response. See UPS and non-linear loads.
Timeline of an outage
| Time (typical) | What happens |
|---|---|
| 0 s | Utility fails; UPS carries IT load on battery; cooling and lighting stop |
| 2 to 5 s | Mains failure confirmed; set cranks |
| 10 to 15 s | Set at voltage and frequency; transfer switch moves |
| 15 to 20 s | UPS sees generator supply and starts recharging |
| 20 s to a few minutes | Chillers and pumps restart in sequence |
With no cooling, a dense hall can rise several degrees a minute, so server thermal shutdown can come before the chillers are back. UPS autonomy, typically 5 to 15 minutes, should cover a failed first start and a second attempt, not just the normal 15 seconds. See restart sequencing.
Capacity architecture
| Arrangement | Meaning | Tolerates |
|---|---|---|
| N | Just enough sets for the load | No failure |
| N+1 | One spare set beyond the load | Loss or maintenance of one set |
| 2N | Two complete independent systems | Loss or maintenance of an entire system |
Shared dependencies. Two sets on one day tank with one transfer pump share a fuel failure. Two sets on one control PLC share a logic failure. Two sets through one switchboard share a bus fault. See N, N+1, 2N and distributed redundancy.
Fuel for the stated autonomy
Autonomy is stated in hours at full load, commonly 12, 24 or 48. At about 0.26 to 0.28 litres per kWh for a loaded set, a 1 MW facility running 24 hours burns about 6200 to 6700 litres, before adding unusable tank bottoms and a margin for a late delivery. Day tanks are filled from bulk storage by duplicated transfer pumps on the generator supply, and long-held diesel needs polishing and periodic testing. See fuel-tank sizing.
Testing that proves readiness
- Weekly: no-load start; proves cranking and little else.
- Monthly or quarterly: loaded run, with a load bank where IT load cannot be disturbed; prevents wet stacking.
- Annually and at commissioning: integrated test pulling the utility breaker, logging UPS state and hall temperature through start, transfer, recharge, cooling restart, retransfer and cool-down, with a failed start injected at least once.
See load-bank sizing and data centre rental power for maintenance windows.
Data centre generator sizing sheet
| Item | kW |
|---|---|
| IT load now and at build-out | |
| UPS input (IT ÷ UPS efficiency) | |
| Battery recharge (limit set?) | |
| Cooling at peak ambient; largest motor start | |
| Building and auxiliaries | |
| Total running load; sets and arrangement (N+1 / 2N) |
How redundancy choices change the plant (illustrative)
For a facility needing about 1200 kVA of generator capacity, the redundancy level decides how many sets are installed and how they are used.
| Arrangement | Sets installed | Capacity with one set out | What it protects against |
|---|---|---|---|
| N | 2 × 625 kVA | 625 kVA, not enough | Nothing beyond normal operation |
| N+1 | 3 × 625 kVA | 1250 kVA, enough | One set failing or in service |
| N+2 | 4 × 625 kVA | 1875 kVA with one out, 1250 with two out | One set in service while another fails |
| 2N | Two complete plants of 2 × 625 kVA | 1250 kVA on the other side | Failure of a whole plant or its switchgear |
Redundancy must extend beyond the sets: fuel systems, controls, synchronising switchgear and distribution paths can each become the single point of failure that defeats an otherwise redundant plant.
Maintaining without losing redundancy
Every service takes a set out of the plant. With N+1, that leaves the facility at N for the duration, which operators accept only for short, planned windows. Services are therefore scheduled one set at a time, at low-risk periods, with the remaining sets proved ready before work starts. On sets we maintain, oil and filters are changed every 250 to 500 running hours or six months, whichever comes first, and coolant is replaced every year, so data centre sets that run little are serviced on the calendar.
Records that prove readiness
- Monthly start and run records for each set, with any alarms.
- Integrated transfer tests with UPS, recording transfer times and UPS behaviour.
- Load-bank test results at rated load, including step-load response.
- Fuel quality results and tank inspection records.
- Service records and any changes under change control.
Kept together, these records let an operator show at any time that the generator plant will carry the facility, rather than assuming it.
Planning for growth
Data halls grow in phases. The generator plan reserves space, switchgear positions and fuel capacity for future sets, and the sizing sheet is updated as each phase is fitted out, so capacity is added before the IT load reaches the point where redundancy is quietly lost.
Fuel quality for sets that rarely run
Data centre generators may run only for tests for months at a time, so their fuel sits in tanks for long periods. Water from condensation and microbial growth can build up unseen and block filters on the day the sets are needed. Regular sampling, water draining, fuel cleaning or polishing when results call for it, and filter changes on schedule keep the fuel ready. A full-load test on a load bank each year also confirms that the fuel system delivers enough flow at rated output, which a short no-load run never proves.
Each phase is commissioned with an integrated test of the new sets alongside the existing plant, so the facility always knows its true capacity and redundancy level.
Common mistakes
- Sizing from the IT load or the UPS output rating.
- Accepting a resistive load-bank test as proof of UPS compatibility; the UPS drops to battery on the first live transfer.
- Letting all chillers restart together; the set stalls or the voltage dip trips the UPS rectifier.
- Counting generators without counting shared fuel, control and distribution.
What to send us
Send the IT load now and at build-out, the UPS rating, rectifier type and battery autonomy, the cooling schedule with motor ratings and starting methods, the target availability, the fuel autonomy in hours and the single-line diagram. For an existing facility, the last integrated test record and any UPS alarm logs from a transfer tell us most of what we need. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Shares, timings and fuel rates are typical values for illustration; the UPS, cooling and generator makers’ data govern.
Questions engineers ask
What is the difference between N+1 and 2N for data centre generators?
N+1 adds one set beyond what the load needs, so one set can fail or be serviced. 2N provides two complete plants, each able to carry the load, so the failure of a whole plant or its switchgear is covered. Redundancy also has to extend to fuel, controls, synchronising switchgear and distribution paths.
How are data centre generators serviced without losing redundancy?
One set at a time, in planned low-risk windows, with the remaining sets proved ready before work starts. On our standard, oil and filters are changed every 250 to 500 running hours or six months, whichever comes first, and coolant every year, so sets that rarely run are serviced on the calendar.
How big should a data centre generator be relative to the IT load?
As a first estimate, 1.6 to 1.8 times the IT load in kW covers UPS losses, battery recharge, cooling and building services in an air-cooled facility in Indian conditions, before adding redundancy. The actual figure comes from the cooling schedule and UPS data, and from checking the largest motor start against the set’s transient capability.
Why does the UPS go to battery when the generator takes over?
The generator’s voltage or frequency is leaving the UPS input window during the transfer or the recharge step, often because the alternator is too small for the UPS’s harmonic current or the governor overshoots. Fixes include a lower-reactance alternator, a recharge current limit on the UPS, and widening the UPS input window where the manufacturer allows it.
Is N+1 enough for a data centre?
For most enterprise and colocation facilities, yes, provided the fuel, controls and distribution are also N+1 and the spare set is kept online or starts automatically on a trip. Facilities that must tolerate a failure during maintenance move to 2N or a distributed redundant arrangement.
How much fuel should a data centre keep on site?
Enough for the autonomy the operator commits to, calculated from the actual load rather than the installed rating, with a delivery arrangement for longer events. Stored fuel is sampled regularly, drained of water and cleaned when results call for it, because sets that rarely run leave fuel standing for months.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.