In short. Not every load needs the same protection against power loss. Critical loads cannot accept any break, so they need a UPS or battery. Essential loads can wait the 10 to 15 seconds a generator needs to start and take over. Mission-critical describes the business functions that must keep running, and it usually covers a chain of loads, not one machine. Classifying loads first stops a site from paying for UPS on everything, or from leaving a vital function on mains only.
Who this page is for: For owners, facility managers and consultants deciding which loads go on UPS, which go on generator and which can be shed.
Key facts
- Classify by what happens if the load stops, not by its size.
- Critical: no break allowed; needs UPS or battery ride-through.
- Essential: a short break is acceptable; generator-backed.
- Non-essential: can be shed or restored later.
- Include hidden dependencies: cooling, controls, network, fuel pumps.
- The classes set UPS size, generator size and load-shedding priorities.
The three classes
| Class | Break allowed | Typical source chain | Examples |
|---|---|---|---|
| Critical | None (milliseconds) | Mains → UPS or battery → generator | Servers, PLCs, life-support, fire and alarm control |
| Essential | Seconds | Mains → generator | Cooling for critical rooms, lifts, key pumps, lighting |
| Non-essential | Minutes to hours | Mains; restored later or shed | Workshops, comfort cooling, car charging |
Worked example: a hospital block (illustrative)
| Class | Load | Supply decision |
|---|---|---|
| Critical | 60 kW | UPS with generator behind it |
| Essential | 180 kW | Generator within seconds |
| Non-essential | 260 kW | Shed on generator, restored when mains returns |
| Generator duty | 60 kW + 180 kW + 10 kW UPS recharge = 250 kW | 400 kVA set (320 kW): 78% loaded, leaving headroom for UPS rectifier load and motor starting |
Putting all 500 kW on generator would have needed a set nearly twice the size. A UPS for everything would have cost far more and still needed the generator. See critical-load classification studies and no-break and short-break loads.
Do not classify a load as critical while leaving what it depends on, such as room cooling or a network switch, on mains only. The function fails when its weakest dependency fails.
Check the dependencies
- Cooling for UPS, server and battery rooms.
- Control power, PLCs and network switches.
- Generator auxiliaries: fuel transfer pumps, starting batteries, ventilation.
- Fire and alarm systems.
See source hierarchy and UPS architecture.
Load classification sheet
A hospital block with a data room, larger than the block in the example above and classified here load by load rather than by class totals. The third column is the one that does the work; the fifth follows from it.
| Load | kW | What happens if it stops? | Break allowed | Class |
|---|---|---|---|---|
| Operating theatres, lighting and equipment | 42 | A procedure is interrupted part way through | None | Critical |
| Data room IT load | 180 | Records and imaging unavailable across the whole hospital | None | Critical |
| Data room cooling | 65 | IT load shuts itself down on temperature within about four minutes | None, in practice | Critical — not essential, see below |
| Fire pump and alarm system | 30 | Life safety system unavailable | Short | Essential, highest priority |
| Ward lighting and sockets | 95 | Care continues on local lighting for a short period | Short | Essential |
| Lifts, one of four kept live | 22 | Patients stranded between floors | Short | Essential |
| Sterilising and kitchen | 88 | Cycles repeated later | Long | Non-essential |
| Administration air conditioning | 60 | Discomfort only | Long | Non-essential, first to shed |
| Totals | 582 | Critical 287, essential 147, non-essential 148 | — | — |
Row three is the reclassification that this exercise exists to find, and almost every site we survey has it the other way round. Data room cooling looks like an essential load: it is a set of fans and pumps, nobody dies if it stops, and a short break is obviously survivable.
But the load it protects is critical and shuts itself down on temperature within about four minutes. Put the cooling on a generator-backed essential supply and a long generator start, a failed first start or a shedding decision takes the IT load down just as surely as cutting its own power would — only with a four-minute delay that makes the connection hard to see afterwards.
So the cooling is classified critical, which moves 65 kW onto the UPS and takes the critical total from 222 kW to 287 kW. That is a materially larger UPS, and it is the correct one. The same reasoning applies to control power, network switches and fuel transfer pumps: a load is as critical as the most critical thing that depends on it.
The three totals at the foot are what the rest of the design is built from. 287 kW sizes the UPS. 434 kW of critical plus essential is what the generators must carry. And 148 kW of non-essential is all that can be shed — which, with two 400 kW sets, turns out not to be enough when one of them is unavailable.
Asking the right questions of each load owner
Load classification is decided by the people who depend on each load, not by the electrical designer alone, and the quality of the result depends on the questions asked. The same few questions, put to every load owner in the same way, give answers that can be compared across the site.
| Question | What the answer decides |
|---|---|
| What happens if this load stops for a fraction of a second? | Whether it needs a no-break supply |
| What happens if it stops for fifteen seconds and then restarts? | Whether a generator alone is enough |
| What happens if it stays off for an hour? For a day? | Whether it can be shed during a long outage |
| Does it restart by itself, or does someone have to restart it? | Whether its restart needs a procedure or automation |
| What else must be running for it to work? | Its dependencies, which inherit its class |
| Who decides if it may be shed? | The owner who must approve the classification |
Answers should be written in the owner’s own words before they are turned into a class. “We lose the batch in the reactor, about six hours’ work” carries more information, and is easier to challenge later, than a bare “critical”. Owners often overstate the importance of their loads at first; the follow-up question “what would you do if it stopped?” usually brings the answer back to a realistic level.
Consequence grows with time, and the class should say how
Most loads are not simply critical or not. Their consequence grows with the length of the interruption, often in steps, and the shape of that growth decides the supply arrangement. A cold store tolerates an hour without power if its doors stay shut; after several hours its contents are at risk. A server room’s computers cannot tolerate any break, but its air conditioning can stop for a few minutes before temperatures become a problem. A process may tolerate a short stop but not one long enough for material to set in the pipes.
| Load | Under a second | Up to a minute | Up to an hour | Several hours |
|---|---|---|---|---|
| Servers and controllers | Serious | Serious | Serious | Serious |
| Cooling for a server room | None | Minor | Serious | Serious |
| Cold store refrigeration | None | None | Minor | Serious |
| Office lighting and power | Minor | Minor | Moderate | Moderate |
Filling a table like this for every significant load turns the classification from a single label into a profile, and the profile answers the questions the label cannot: which loads must be on the UPS, which can wait for the generator, and which can be shed for how long during an extended outage when fuel must be stretched.
Keeping the classification current
A classification done once and filed is out of date within a year. Equipment is added, processes change, a room is repurposed, and new loads are connected to whatever circuit has a spare way. A classification register, listing each significant load with its class, its profile, its owner and its supply, needs a simple rule to stay current: no new critical or essential load is connected until it has been entered in the register and its supply checked against its class.
The facilities team applies the rule at the point of connection, and the register is reviewed in full once a year with the load owners. A load found on the wrong supply during the review is corrected in a planned way, rather than being discovered during an outage.
Common mistakes
- Everything labelled critical.
- Dependencies left on mains.
- Classes set by department wishes, not consequences.
- Classes never reviewed as loads change.
What to send us
Send your load list and tell us what must keep running during a power cut. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. The example is illustrative.
The six loads that are routinely put in the wrong class
Classification goes wrong in one direction almost every time: a support load is judged on what it is rather than on what depends on it. The sheet above caught one; these are the six we find most often, and the test for each is the same question — what is the most critical thing that stops working if this stops working?
- Cooling for an IT or equipment room. Looks like fans and pumps. Actually carries the critical load it serves, because that load shuts itself down on temperature within minutes. The sheet above moved 65 kW because of this.
- Control power and building management. A few hundred watts of controllers, relays and transfer switch logic. If it fails, the changeover does not happen and nothing else in the design matters. Small, invisible and genuinely critical.
- Network switches and structured cabling. Servers on a UPS and the switches between them on an essential supply means the servers stay up and unreachable, which from a user’s point of view is indistinguishable from an outage.
- Fuel transfer pumps. The generator carries the building; the pump keeps the generator fed. A pump on a non-essential feeder gives you a few hours of autonomy and then an outage, and the test record elsewhere in this section shows exactly that arithmetic.
- Lifts, during an evacuation. Normally essential at most. During a fire or a medical evacuation one car becomes a life-safety load, which is a different class under a different condition — and it has to be decided in advance.
- Security, access control and door releases. Fail the wrong way and people are locked in or out of exactly the areas they need during an incident.
There is one error in the other direction worth naming, because it is expensive rather than dangerous: putting an entire building on the UPS because classifying it looked like too much work. That buys a UPS three or four times the size it needs, a battery to match, and motor loads cycling on an inverter that was never meant to carry them. The classification exercise usually pays for itself on the first UPS quotation.
Questions engineers ask
What questions should be asked to classify a load?
What happens if it stops for a fraction of a second; what happens if it stops for fifteen seconds and restarts; what happens if it is off for an hour or a day; whether it restarts by itself; what else must be running for it to work; and who decides whether it may be shed. Record the answers in the owner’s own words before turning them into a class, and ask what they would actually do if the load stopped.
Why does the length of an outage change how a load is classed?
Because most loads become more serious the longer they are off, often in steps. Servers cannot tolerate any break; cooling for a server room can stop for a minute or two; a cold store can usually manage an hour with its doors shut but not several hours. A profile of consequence against time for each load shows which belong on the UPS, which can wait for the generator, and which can be shed in a long outage.
Is “essential” the same as “critical”?
Not always. The words are used differently between standards and organisations. Define the tiers for your site by consequence and tolerable gap rather than relying on the label. Write each tier down with its definition, the tolerable break and an example load, so that designers, operators and maintenance staff all use the words in the same way.
Who should approve the classification?
The operations or process owner, with safety and engineering input. It is a business and safety decision as much as a technical one. Engineering advises what each class costs and what it protects against, safety confirms life-safety loads, and the owner signs the final list so that it carries authority when budgets are set.
Do essential loads need UPS?
Only if they cannot tolerate the generator start and transfer gap. Many essential loads accept a short break and do not need UPS. Pumps, lifts, general lighting and air-conditioning usually restart on generator supply, while controls, servers and instruments that lose data or settings on a break are the loads that need UPS support.
How often should classification be reviewed?
Whenever loads or operations change, and as part of regular design reviews. New equipment, a changed process or a change of use can move a load into a higher or lower class. A yearly review of the load register, with the operations owner, keeps the classification and the supply arrangement in step with the site.
This guide gives general principles. Applicable codes and regulations for your facility type must be checked separately.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.