In short. Loads differ in how long a break they can tolerate. No-break loads cannot ride through a break longer than about 10–20 milliseconds, so they need a UPS. Short-break loads accept a break of seconds while a generator starts. Long-break loads can wait minutes or hours, but they still need a planned restart. The class depends on what the load does when power returns, not only on how important it is.
Who this page is for: For plant engineers, facility managers and consultants deciding which loads need UPS, which need a generator, and how loads restart after a break.
Key facts
- No-break: tolerates no more than about 10–20 milliseconds; needs UPS.
- Short-break: tolerates about 10–15 seconds; generator-backed.
- Long-break: minutes or more; restored in sequence or manually.
- Some loads survive the break but restart slowly, such as chillers with restart timers.
- Motor contactors usually drop out and need an automatic restart scheme.
- Test each load’s real behaviour with a planned power interruption.
The three classes
| Class | Break tolerated | Supply | Typical loads |
|---|---|---|---|
| No-break | Milliseconds | UPS, generator behind it | PLCs, servers, network, safety controls |
| Short-break | Seconds | Generator via changeover | Pumps, fans, lighting, lifts |
| Long-break | Minutes to hours | Restored later | Process heating, workshops, comfort cooling |
Worked example: a process plant (illustrative)
| Load | What a 12-second break does | Class and action |
|---|---|---|
| PLC and control network, 10 kW | Loses process state; hours to recover | No-break: 20 kVA UPS |
| Cooling water pumps, 90 kW | Contactors drop out; equipment overheats if not restarted | Short-break: generator with automatic restart in steps |
| Chiller, 60 kW | Restarts, then waits several minutes on its restart timer | Short-break; allow for the delay in room temperature |
| Process heaters, 300 kW | Product cools; can be reheated later | Long-break: restored when mains returns |
A 20 kVA UPS covers the only true no-break load. A UPS for all 460 kW would have cost far more and added nothing useful. See critical and essential loads and UPS architecture.
Do not assume a short-break load is safe because the generator starts within seconds. Check that it restarts by itself, in the right order, and without starting every motor at once.
Designing the restart
- Staggered automatic restart of motors after a break.
- Control power on UPS so the restart logic survives the break.
- Restart delays on motors and chillers allowed for.
- Long-break loads held off until the source is stable.
See source hierarchy and transfer coordination.
Break tolerance sheet
The whole load schedule of a 500 kW vaccine cold store and quality-control laboratory — not the process plant in the example above, which has its own three loads and its own figures. Every circuit in the building is listed, because a schedule with gaps in it is how loads end up in the wrong class. The third column is the one that does the classifying, and it is written as an observed consequence rather than as an opinion.
| Load | kW | Effect of a 12-second break | Restarts by itself? | Class |
|---|---|---|---|---|
| Cold-store refrigeration units, 3 × 45 kW, soft started | 135 | All three stop. The store barely warms in 12 seconds; what costs time is the four-minute anti-recycle delay before they may restart | Yes, after the anti-recycle delay | Short break |
| Cold-store evaporator fans and controller | 18 | Controller resets. Set-points hold but the alarm log and the defrost sequence position are lost | No. Needs a reset at the store panel | No break |
| Laboratory instruments: chromatographs, incubators, balances and the sample refrigerator | 64 | Runs abort. A 90-minute chromatography run and the sample in it are both lost, and the sample cannot be remade | No. Every run has to be set up again | No break |
| Laboratory fume extraction | 30 | Hoods lose flow. Open work has to stop until flow is proved again at the hood interlock | Yes, on the interlock | Short break |
| Cleanroom air handling | 72 | The pressure cascade collapses and the room needs about 20 minutes of clean-up before work may restart | Yes | Short break |
| Monitoring and server room | 22 | Temperature monitoring and the audit trail stop. The gap in the record has to be explained before a batch can be released | No | No break |
| Lighting: laboratory and cold store | 26 | The LED fittings return at once; the older discharge fittings over the store restrike after three to six minutes | Yes | Short break |
| Office lighting, small power and the lift | 88 | The lift parks at the nearest floor and office work stops. Nothing is damaged and nothing is lost | Yes | Long break |
| Site lighting and workshop | 45 | The yard goes dark until the set is on load | Yes | Long break |
| Total | 500 | No break 104 kW · short break 263 kW · long break 133 kW | — | — |
Those three totals are the whole design, and they fall out of the sheet rather than being chosen. The 104 kW of no-break load sets the UPS: at 0.9 power factor that is 115.6 kVA, which on three 60 kVA modules in N+1 leaves each module at 64% and leaves 96% on the remaining two if one is taken out.
The 367 kW of no-break plus short-break load sets the generator: at 0.8 power factor that is 459 kVA, so a 500 kVA set runs at 92%. The 133 kW of long-break load is simply left off the essential board, and that omission is what makes a 500 kVA set sufficient where a set covering the whole building would have had to be a size larger.
Two rows repay a second look, because both are routinely put in the wrong class. The evaporator fans and controller are only 18 kW and every instinct says they belong with the refrigeration they serve — but the motors restart themselves and the controller does not, so an 18 kW circuit on the UPS is what keeps a 135 kW plant from needing a person at the panel after every event.
And the laboratory instruments are the opposite case: they are classed no break not because the instruments would be damaged but because the sample would, and a sample that took three weeks to prepare is not recoverable by restarting anything. The question the third column asks is never “does this trip out?” but “what does the break cost, and can it be bought back?”
How long common equipment survives a break
Putting each load in its class starts with knowing how long it can survive without supply, and how it behaves when the supply returns. Equipment varies widely, and the figures below are typical behaviours to check against the maker’s data for the actual items on site.
| Equipment | Typical ride-through | When the supply returns | Usual class |
|---|---|---|---|
| Computers and servers | Around 10 to 20 ms, from the power supply’s stored energy | Restarts from the beginning; work in progress lost | No break |
| Programmable controllers | Around 10 to 20 ms on most power supplies | Restarts; the process may be left in an unknown state | No break |
| Variable-speed drives | A few cycles, set by the DC bus and the undervoltage trip | Trips, or restarts if automatic restart is set | Short break if restart is configured |
| Contactor-controlled motors | About a cycle or two before the contactor drops out | Stays off until restarted, unless the control circuit restarts it | Short break with a planned restart |
| LED lighting | Milliseconds | On again almost at once | Short break |
| High-intensity discharge lighting | Milliseconds | Stays dark for several minutes while the lamp cools and restrikes | Short break only if minutes of darkness are acceptable |
The last row is the one that surprises people. Large halls, warehouses and outdoor areas lit by discharge lamps remain dark for minutes after a supply break of any length, even a fraction of a second, because the lamps must cool before they can restart. A generator that restores supply in twelve seconds does not restore the lighting for several minutes, and emergency or LED lighting must cover the gap.
Moving a load into a better class without a UPS
A load that drops on a short break is not necessarily a load that needs a UPS. Often the part that cannot tolerate the break is small, and protecting that part alone moves the whole load into a better class at a fraction of the size.
| Problem | Targeted remedy | Result |
|---|---|---|
| Contactors drop out on a brief dip and motors stop | Feed the control circuit from a small UPS, or fit contactors with a hold-in or delayed drop-out | Motors ride through dips and restart in sequence after longer breaks |
| Drives trip on a dip | Enable kinetic buffering and automatic restart in the drive settings | The drive rides through short dips and catches the spinning motor after longer ones |
| Controllers lose their state | A small UPS for the controller and its input and output power | The process is held in a known state through the break |
| Lighting goes dark for minutes | A share of LED or emergency luminaires on a battery or no-break supply | Safe lighting through the break and the restrike period |
Each remedy is small, and together they often turn a plant that stops for half an hour after every outage into one that resumes within a minute of the generator taking load. Check each against the process: some loads are better left to stop safely and be restarted deliberately, and the point of the class is to make that a choice rather than an accident.
Marking the class at the board
The class of each circuit is a design decision that has to survive years of changes, and it survives best where it is visible. Mark each outgoing circuit on the distribution board schedule, and on a label at the board, with its class and the supply it relies on: “no break — UPS”, “short break — generator”, “long break — mains only”. When a new load is connected, its class is chosen and written at the same time, and a no-break load connected to a short-break circuit is visible to anyone who reads the schedule. Without the marking, classes drift: critical equipment ends up on circuits that drop for twelve seconds on every outage, and the first anyone knows of it is the outage.
Review the class marking whenever the break-tolerance sheet on this page is reviewed, and after any outage in which a load behaved differently from its class. Each such event is evidence that either the load, its class or its supply has changed.
Common mistakes
- Classes guessed, not tested.
- No automatic restart after a break.
- Restart logic itself not on UPS.
- All motors restarting together on the generator.
What to send us
Send your load list and what each load does after a power cut. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. The example is illustrative.
Questions engineers ask
Why do warehouse lights stay off for minutes after a very short power cut?
Because high-intensity discharge lamps must cool before they can restrike, which takes several minutes, so they stay dark after a break of any length, even a fraction of a second. A generator that restores supply in twelve seconds does not restore that lighting for minutes. Provide part of the lighting as LED or emergency luminaires on a battery or no-break supply so that areas stay safely lit through the break and the restrike period.
How long can a server ride through a break in supply?
Typically around 10 to 20 milliseconds, from the energy stored in its power supply, after which it restarts from the beginning and loses work in progress. Programmable controllers are similar. That is why servers and controllers belong in the no-break class on a UPS: a generator restoring supply in seconds is far too slow for them. Check the maker data for the actual equipment, especially for older or basic supplies.
What interruption can a standby generator system hide?
None. It has a gap while the engine starts and the transfer happens, usually seconds. Only UPS or battery systems bridge that gap. Loads that cannot accept that break are placed on UPS, and the remaining loads are designed to restart cleanly when generator supply arrives, with staggered restarts so the set is not hit by every load at once.
Do all loads need a defined class?
For design purposes yes. Unclassified loads default to the most expensive assumption or are overlooked. A register of every load with its class, its tolerable break and its supply path makes the design traceable, and it is the document that operations use to check that changes keep each load on the right supply.
What is contactor drop-out?
A starter that opens when voltage dips or is lost, even briefly, so the load stays off until restarted. After a generator transfer, motors with such starters remain off until someone restarts them, which can stop a process. Automatic restart schemes, with staggered timing, are added where the process requires it.
Can a load change class?
Yes, if the process changes or the load is given hold-up. Update the register when it does. A load that gains a small UPS or ride-through capability moves to a shorter-break class, while a new process step can make a once tolerant load critical, so changes are reviewed before they are made, not after an outage.
This guide gives general principles. Confirm ride-through values with equipment data.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.