In short. A critical-power UPS is normally online double-conversion. The load runs from the inverter all the time, with a static bypass for faults and overloads and a maintenance bypass for servicing. Size it from today’s critical load in kW, plus growth, kept below a sensible maximum loading. Then check its batteries, its bypass source and the generator that feeds it, because a UPS only bridges the gap until the generator takes over.
Who this page is for: For owners, IT and facility managers and consultants choosing and sizing UPS systems for critical loads.
Key facts
- Online double-conversion gives no break and isolates the load from mains disturbances.
- Size in kW first; many modern UPS have an output power factor of 1.0; check the rating plate.
- Add growth and keep loading below about 80%.
- The static bypass connects the load directly to its bypass source when needed.
- A maintenance bypass lets the UPS be serviced without a shutdown.
- The generator feeding a UPS must handle its input current and battery recharge.
Worked example: sizing a UPS for 36 kW (illustrative)
| Step | Working | Result |
|---|---|---|
| Critical load today | Measured | 36 kW |
| Add 20% growth, keep loading at 80% | 36 × 1.2 ÷ 0.8 | 54 kW |
| UPS rating (output power factor 1.0) | Next standard size above 54 kW | 60 kVA / 60 kW |
| Generator behind it | UPS input about 65 kVA (60 kW plus losses) plus about 5 kVA recharge = about 70 kVA; × 1.5 to 1.8 for rectifier load | about 100–125 kVA set for the UPS share |
The calculator above follows the same method. Batteries are sized separately for the autonomy needed. See battery autonomy and modular UPS.
Do not run a UPS near 100% from the start, or feed it from a generator sized only for its kW. Leave room for growth, and check the generator against UPS input current, harmonics and recharge.
UPS types
| Type | Break on mains failure | Use |
|---|---|---|
| Online double-conversion | None | Critical loads |
| Line-interactive | Very short | Small offices, network cabinets |
| Offline (standby) | Short | Desktop equipment |
See online UPS systems and bypass arrangements.
UPS sizing sheet
| Item | Value |
|---|---|
| Critical load today, kW | |
| Growth allowance | |
| Required kW at maximum loading | |
| Autonomy needed | |
| Bypass source |
The main ways to arrange UPS units
A critical load can be served by one UPS or by several, and how several are arranged decides what they protect against. The arrangements differ less in the equipment they use than in what the units share, and every shared item is a point where the arrangement can fail as a whole.
| Arrangement | How it works | Survives a UPS failure? | What the units share |
|---|---|---|---|
| Single UPS | One unit with static and maintenance bypass | Only by going to bypass, unprotected | Everything |
| Parallel redundant, N+1 | Several units on a common output bus, one more than the load needs | Yes, the others carry the load | Output bus, output breaker, parallel control link, often the bypass |
| Isolated redundant | Each unit feeds its own load; a reserve unit feeds the bypass inputs of the others | Yes, the failed unit’s load goes to bypass on the reserve | The reserve unit, which must be healthy when called |
| 2N | Two complete UPS systems, each able to carry the whole load, feeding dual-corded loads | Yes, and a whole system can fail | Only the load itself, if properly separated upstream |
Parallel N+1 is the most common step up from a single unit, because it adds redundancy with one extra unit. Its weakness is the common bus: a fault on the shared output bus or in the shared output breaker takes out every unit at once, and the parallel control link that keeps the units sharing must itself be redundant or fail safely. A 2N system shares nothing but the load, which is why it is the arrangement of choice where a whole UPS system must be maintainable or able to fail without exposure.
A rough guide to the choice follows the load and its tolerance. A small critical load that can accept running on bypass during the rare UPS failure is well served by a single unit with a maintenance bypass. A load that must stay protected through a unit failure, but can accept planned maintenance windows, suits parallel N+1.
A load that must stay protected through maintenance as well as failure needs 2N, or 2(N+1) where a failure during maintenance must also be covered. Each step up removes more of what the units share, and the decision should be made against the availability target and the outage history, not against what a neighbouring site happens to have.
Where a parallel system can fail as a whole
A parallel N+1 system is redundant only in the parts that are duplicated. Three items are shared in many designs and deserve particular scrutiny. The first is a common battery: some parallel systems connect every unit to one battery string to save cost and space, which makes that string, its breaker and its cabling a single point of failure for the whole system; each unit should have its own battery.
The second is the parallel communication link between units, which coordinates load sharing and synchronisation: if it fails, the units must continue sharing safely by themselves rather than trip, and the link should be duplicated or arranged as a ring so that one broken cable does not split the system. The third is the system bypass: where a single bypass switch serves all units, a fault in it affects the whole system.
Ask the maker how the system behaves on the loss of each shared item, and test the answers at commissioning: disconnect a parallel communication cable with the system on load, and confirm that the units keep sharing and raise an alarm rather than transferring to bypass or shutting down.
From the UPS output to the load
The UPS output is not where the protection ends. Between the UPS and the equipment there is usually an output switchboard, power distribution units, sometimes transformers, and final circuits, and each of these can drop a load that the UPS itself is protecting perfectly. Three design points keep the distribution as resilient as the UPS. The output switchboard and its breakers should be arranged so that a fault on one outgoing circuit clears without disturbing the others, which on an inverter source needs the small final-circuit breakers covered on the UPS pages.
Distribution units with transformers create a new neutral and need their own earthing arrangement. And dual-corded equipment must take its two cords from two genuinely different distribution paths, traced back to different UPS outputs in a 2N design, not from two sockets on the same distribution unit.
A practical check is to walk from each critical item back to the UPS, writing down every breaker, distribution unit and cable it depends on. Two cords that converge on one breaker anywhere on the way are one cord.
Room, access and weight
A UPS system has to be serviceable for fifteen years or more, and its room should be planned for that from the start. Most units need front access for service and some need side or rear access too; the maker’s clearances are minimum figures, not targets. Battery cabinets or racks are heavy, and a room on an upper floor needs its floor loading confirmed by a structural engineer before the batteries arrive.
The heat from the UPS and its batteries must be removed reliably, by cooling that continues on generator. And there must be a route wide and strong enough to bring in a replacement unit or battery cabinet without removing a wall, because the day the UPS is replaced, years later, is the day an undersized door becomes a significant project.
Replacing a UPS without a shutdown
UPS units have a service life, typically in the region of ten to fifteen years depending on design and conditions, and the critical load usually cannot be shut down while the unit is replaced. Planning the replacement in the original design makes it straightforward. A 2N system replaces one side at a time while the other carries the load.
A parallel N+1 system can often replace one unit at a time if the new units can run in parallel with the old ones, which depends on the maker. A single UPS needs a different approach: the load is transferred to the maintenance bypass, protected during the changeover by a temporary UPS connected through a dedicated connection point, while the old unit is removed and the new one installed and tested.
Provision for that temporary connection — a switched and labelled connection point on the output side, rated for the full load — costs little when the system is first built and avoids a period of running the critical load on raw mains during the replacement. It also serves for any major repair that takes the unit out of service for more than a few hours.
What to receive at handover
A UPS system is only as maintainable as the information handed over with it. The list below is short, and every item on it is something an engineer will need on a bad night years later.
| Document | Why it matters later |
|---|---|
| Factory test report for each unit | The baseline for output regulation, efficiency and transfer behaviour |
| Site acceptance results, including load step and battery discharge | The baseline for autonomy and for every later test |
| Settings file and firmware versions for each unit | Restores the system after a controller replacement |
| As-built single-line and earthing drawings | Shows what each breaker feeds and where the neutral is bonded |
| Written procedures for transfer to and from maintenance bypass | The step most often done wrongly, with the most serious result |
| Battery records: type, batch, installation date, block voltages at handover | Tracks ageing and supports staggered replacement |
| Training record for the site staff who will operate it | Confirms that someone on site knows the procedures |
Keep a copy beside the UPS and another off site. The settings file in particular should be saved again after every service visit, because it is the item most likely to have changed and the hardest to reconstruct from memory.
Common mistakes
- Sizing from kVA nameplates.
- No maintenance bypass.
- Generator too small for the UPS.
- Bypass source not studied.
What to send us
Send your critical load measurements and backup time needed. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Values are illustrative.
Questions engineers ask
What is the difference between parallel redundant and 2N UPS?
A parallel redundant N+1 system has several units on a common output bus, one more than the load needs, so the others carry the load if one fails, but they share the output bus, breaker, control link and often the bypass. A 2N system has two complete UPS systems, each able to carry the whole load, feeding dual-corded equipment, and shares nothing but the load. 2N can lose or maintain a whole system without exposure; N+1 cannot.
How is a UPS replaced without shutting down the load?
A 2N system replaces one side while the other carries the load, and many parallel systems replace one unit at a time. A single UPS needs the load moved to the maintenance bypass, protected during the work by a temporary UPS connected through a dedicated, switched connection point on the output side. Providing that connection point when the system is first built avoids running the critical load on raw mains for days during a replacement or a major repair.
What is the best UPS topology for critical loads?
Online double conversion is the usual choice because it isolates the load from supply disturbances and gives a defined transfer. The inverter supplies the load continuously, so a supply failure causes no break at the load, and the static bypass handles internal faults. The battery runtime is sized to cover generator start and transfer with a margin.
Is a single UPS acceptable?
It can be where the load tolerates the risk, but the UPS is then a single point of failure. Critical sites often use parallel redundant arrangements. An N+1 parallel system keeps the load on inverter if one module fails, and a maintenance bypass lets the whole system be serviced without a shutdown.
How is UPS rating chosen?
From the load in kVA and kW, power factor, growth and redundancy needs. See the UPS capacity guide. Check both the kVA and the kW rating against the load, allow for planned growth, and add the redundant module so the load stays within rating with one unit out of service.
Do UPS units cause problems for generators?
They can, through input current distortion and step loading. A study or manufacturer check avoids surprises. The generator must accept the UPS input current, its battery recharge load and the step when the UPS transfers onto generator. Ramped or walk-in rectifier start and a low-distortion input help the set accept the load.
This guide gives general principles. UPS selection should be confirmed with the manufacturer’s data.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.