Generator Synchronising Readiness Checklist

A checklist and decision guide for readiness to synchronise generators: the four conditions, phase sequence, protection, controls and tests to complete before closing a breaker onto a live bus.

In short. Closing a generator breaker onto a live bus out of step can damage the engine, alternator and switchgear. Before synchronising, the incoming unit must match voltage, frequency, phase angle and phase sequence, and the controls, protection and breaker must be ready. This guide gives the readiness questions in order.

The four synchronising conditions

ConditionTypical check-sync tolerance (illustrative)
Voltage matchWithin a few per cent
Frequency matchSlip within a fraction of a hertz
Phase angleWithin about 10 degrees at closing
Phase sequenceSame rotation; verified at commissioning

Tolerances come from the manufacturer and the control settings. Do not close outside them.

Readiness checklist

Mechanical and electrical

Controls

Protection

Bus and load

Decision flow

  1. Is the bus dead? If yes, use dead-bus closing logic for the first source, with interlocks.
  2. If the bus is live, are all four conditions met? If yes, close.
  3. If not, adjust speed and voltage, or wait for the synchroniser. Never force a close outside the window.
  4. After closing, ramp load on in a controlled way and check sharing.

Commissioning tests

See synchronising and paralleling switchgear.

Worked illustration

After a generator overhaul, the alternator leads are reconnected. The unit looks healthy, but phase rotation was changed. At the first synchronising attempt, the check-sync relay prevents closing because the rotation is wrong. This is exactly the failure the readiness check should catch, before an out-of-phase closing breaks a coupling. The fix is to swap two leads and repeat the check.

Readiness checklist before closing

ItemPass condition
Phase sequenceSame on both sides, verified by meter
VoltageWithin about 5 percent of the bus
FrequencyWithin about 0.1 to 0.2 Hz, slow slip
Phase angleWithin the sync-check window at close
Governor and AVRControls responding, no hunting
BreakerClosing time known, healthy, correct control voltage
ProtectionReverse power, over/under voltage and frequency, short circuit enabled
Load sharingMethod configured and tested
Dead-bus interlockOnly one source may close on a dead bus

Decision tree

  1. Bus dead: allow one set to close after interlock check.
  2. Bus live: run automatic synchroniser, supervised by a sync-check relay.
  3. Any check fails: do not force; find and fix the cause.

Closing angle illustration

With 0.1 Hz slip and a breaker closing time of 80 ms, the close command issues about 2.9 degrees before zero phase angle. If the closing time is wrongly entered as 200 ms, the contacts touch about 7 degrees off.

Commissioning tests

Verify each sync-check window by injecting out-of-limit conditions and confirming the breaker will not close.

See synchronisation and dead-bus and sync-check logic.

Common mistakes

What to send us

Send your synchronising scheme and controller details. Send your application details. See also DG synchronising panels.

Questions engineers ask

What happens if a generator closes out of phase?

It can cause severe mechanical shock and high currents, damaging couplings, windings and breakers.

Is automatic synchronising safer than manual?

Automatic synchronisers with check-sync supervision are generally more consistent. Manual synchronising should always have a check relay.

How do I verify phase rotation?

With a phase-rotation meter on each source, or by sync-check measurement before energising.

Can I synchronise to a dead bus?

You do not synchronise; you close onto it under dead-bus logic with interlocks.