In short. A plant shutdown or turnaround removes normal production but not the need for power. Lighting, ventilation, pumps, welding, workshops, site offices and recommissioning loads all continue, and the demand changes from day to day. Plan rental generation around the turnaround programme in phases, place sets and cables away from work fronts, give contractor loads their own feeders, and size for the heaviest phase, which is often recommissioning near the end.
How turnaround power differs from a single outage
A planned outage, covered on planned-outage power, is usually a single isolation of one asset with a fixed load behind it. A turnaround at a refinery, chemical plant, steel unit or pharmaceutical site is a multi-week project in which hundreds of contractors work on many systems at once. The electrical requirement is not one number. It starts small, grows as work fronts open, and often peaks when equipment is being reassembled and tested. The temporary power plan has to follow that programme rather than stand still while the site changes around it.
Plan by phase
| Phase | Typical loads | Power planning focus |
|---|---|---|
| Isolation and make safe | Safety lighting, critical instrumentation, fire pumps, control rooms | Minimum essential supply, proven before isolation |
| Maintenance | Welding sets, grinders, motors, dewatering pumps, workshops, cabins | Many single-phase and fluctuating loads, phase balance, earth leakage |
| Reassembly | Cranes, hydrotest pumps, larger tools, increasing auxiliaries | Rising demand, more feeders, motor starting |
| Recommissioning | Process motors, cooling, controls, test runs | Highest transient demand, voltage stability, controlled energisation |
Building this table from the shutdown schedule turns the turnaround calendar into an electrical load plan. A generator sized for the isolation phase will not carry recommissioning, and one sized for recommissioning will run lightly loaded for weeks unless the plan uses several smaller sets added as phases progress.
Contractor loads and welding
Contractor equipment rarely appears in the plant’s own load schedule, yet it can dominate the turnaround demand. Welding rectifiers and inverter sets draw intermittent, non-linear current; a dozen running together produce large swings and harmonic current in the neutral. Give contractor areas their own protected feeders with 30 mA earth-leakage protection on socket circuits, allocate single-phase loads across phases deliberately, and size the generator for the swings, not only the average. Distribution practice is set out on temporary distribution panels.
Layout on a congested site
A turnaround site is far more crowded than normal operation: scaffolding, lifting zones, laydown areas and hot-work permits change daily. Agree generator positions with the turnaround planners against the whole programme, not just day one, and keep sets clear of crane radii, hydrocarbon areas and confined-space entry points. Route cables overhead or in protected crossings, and label every feeder at both ends so a contractor can identify its supply without opening panels. Cable selection is covered in temporary power cables.
Resilience and maintenance during the turnaround
Ask what happens if one rental set fails halfway through. If the answer is that hydrotesting stops for an hour, a single set may be acceptable. If it is that a fire pump, a control room or a cold store loses supply, the critical functions need either a standby set with a transfer arrangement or splitting across two sets. Sets running round the clock for several weeks will also need oil and filter service during the hire, so plan for a spare or a short planned changeover. Fuel deliveries should be scheduled from the turnaround plan, with the reserve defined.
Handback
Handback is planned from the start of the turnaround, not improvised at the end. As permanent equipment returns, loads transfer back in a controlled order agreed with the plant electrical team. Temporary feeders are removed only when their loads are confirmed on permanent supply, cables are inspected before leaving site, and the fuel and hour-meter records are closed out.
A sizing illustration
A chemical unit near Hyderabad plans a 21-day turnaround (illustrative). Isolation needs about 80 kW for control rooms, lighting and a cooling-water pump. Maintenance adds around 15 welding sets, dewatering pumps and cabins, reaching an estimated 260 kW with large swings. Recommissioning brings back a 110 kW feed pump and a 75 kW blower while maintenance loads tail off, giving about 320 kW with a heavy starting event.
Rather than one 500 kVA set for three weeks, a 125 kVA set for the essential supply from day one, plus a 320 kVA set added at the start of maintenance, covers every phase with each set reasonably loaded, and the essential supply is never shared with welding.
Turnaround load by phase (illustrative)
A three-week turnaround at a process plant shows how the power requirement rises and falls. The figures are examples of how the phases are built from the programme.
| Phase | Main loads | Running demand |
|---|---|---|
| Days 1 to 3, shutdown and isolation | Lighting, ventilation, offices, essential pumps | About 120 kW |
| Days 4 to 14, peak work | Welding, workshops, blowers, lighting, offices, pumps | About 380 kW |
| Days 15 to 18, closing up | Reduced welding, testing, lighting, offices | About 220 kW |
| Days 19 to 21, recommissioning | Large motors restarted, utilities, lighting | About 300 kW plus motor starts |
A single large set sized for the 380 kW peak would run below a third of its rating in the first days. Three sets of about 250 kVA, brought in as work fronts open and placed near them, carry the peak at about 63% together, keep each area independent and allow one set to be serviced while the others carry the load during the quieter phases.
Welding loads in practice
Welding sets draw power in bursts, and their input rating can be several times their average draw. Inverter welders draw far less input than older transformer welders for the same output and are kinder to a generator. On a turnaround, welding sets are grouped on their own boards, fed from a set or feeder that does not also supply instrument power or control systems, and their diversity is checked by logging the board current over the first days. That measured figure replaces the estimate and decides whether a set can be released or another is needed.
Service and fuel through the turnaround
Sets running round the clock reach 250 running hours in a little over ten days. On our standard of oil and filters every 250 to 500 running hours or six months, whichever comes first, a three-week turnaround usually needs at least one service on each continuously running set. The service is planned for a quieter phase, with another set carrying the area. Fuel deliveries are scheduled from the logged consumption of each set, with a reserve held on site because a turnaround cannot pause for a late tanker.
Recommissioning large motors on rental power
Recommissioning is often the most demanding phase. A large motor started direct on line can draw six times its full-load current, and the voltage dip affects every other load on the same set. Each large motor is listed with its rating and starting method before the turnaround, its starting kVA is checked against the set that will feed it, and motors are started one at a time with the others running. Where a motor cannot be started within an acceptable dip, a larger set, a soft starter or a drive is arranged in advance rather than discovered on the last day.
Placing sets on a congested plant
Turnaround sites are crowded with scaffolding, cranes, laydown areas and vehicles. Sets are placed where they will not block access routes or crane swing paths, away from hazardous areas defined for the plant, on firm level ground with drainage, and with exhaust directed away from work fronts and air intakes. Cables follow agreed routes, are protected where vehicles cross, and are labelled at both ends with the set and board they connect. A simple layout drawing showing every set, board and cable route, updated as work fronts move, lets everyone on site find the supply for their area quickly and stops contractors from tapping unplanned connections.
Handing back after the turnaround
When the permanent plant is back on its own supply, rental sets are run down on no load, isolated and confirmed dead before cables are removed. Temporary boards are taken out in reverse order of installation, and a short handback record lists the running hours, fuel delivered and used, any faults during the turnaround and the readings logged on each set. That record becomes the starting point for planning power at the next turnaround, with real figures in place of estimates.
Common mistakes
- Sizing from the plant’s normal maximum demand. The rental plant is far larger than the turnaround needs and runs inefficiently for weeks.
- Sizing only for the first phase. Recommissioning loads overload the set at the end of the shutdown, when time pressure is greatest.
- Leaving contractor loads inside a single general allowance. Welding and pump loads overload one phase and trip the supply for everyone.
- Placing generators where day-one access is easy. A later lifting zone or work front forces a relocation mid-turnaround.
What to send us
Send the turnaround schedule with dates for each phase, the list of permanent loads that must stay powered, an estimate of contractor equipment such as welding sets and pumps, and a plot plan showing possible generator positions and work fronts. Send a generator rental enquiry and we will propose a phased generator and distribution plan. Requirement structuring is also supported by the power requirement configurator.
Questions engineers ask
How is welding load estimated for a turnaround?
List each welding set by type and rated input, estimate how many run at once with the contractors, and group them on their own boards. Inverter welders draw much less input than transformer types for the same output. Logging the board current over the first days replaces the estimate with a measured figure.
What should be checked before recommissioning large motors on rental power?
Each large motor rating and starting method, its starting kVA compared with the set that will feed it, and the voltage dip the other running loads can accept. Motors are started one at a time with the others running, and where a start is too heavy a larger set, a soft starter or a drive is arranged in advance.
Should I hire one large generator or several smaller ones for a turnaround?
Several smaller sets usually suit a turnaround better, because the load grows and falls in phases and separate areas can be fed locally. One large set is simpler to manage but runs lightly loaded for much of the time and is a single point of failure.
How do I estimate welding load?
List the welding sets by type and rated input, and estimate how many run at once. Inverter welders draw much less input than older transformer types for the same output. A diversity assumption agreed with the contractors, checked by logging on the first days, gives a defensible number.
Do rental generators need servicing during a long turnaround?
Yes, if they run continuously for longer than the service interval. Our standard is oil and filters every 250 to 500 running hours or six months, whichever comes first. Sets running round the clock reach 250 hours in a little over ten days, so the service is planned for a quieter phase with another set carrying the area.
Can rental generators support recommissioning of large motors?
They can, if the set is sized for the motor’s starting kVA and the voltage dip is acceptable to the other loads. Starting method, such as star-delta, soft starter or drive, changes the required generator size considerably and should be confirmed for each large motor.
Generators by rating
- Under 15 kVA generators
- 15–50 kVA generators
- 50–125 kVA generators
- 125–250 kVA generators
- 250–500 kVA generators
- 500–1000 kVA generators
- 1000–2000 kVA generators
- 2000 kVA and above generators
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.