Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Emergency Temporary Power

What to do when you need emergency generator power fast: identify the failed asset, loads to restore, a safe connection point and the details to share.

In short. Emergency temporary power restores essential loads after a failed transformer, cable, switchboard or permanent generator. Speed matters, but the first useful step is identifying what has failed, which loads must come back first and where a rental set can be connected safely without back-feeding the fault or the DISCOM network. An enquiry with the voltage, critical loads, largest motor and site access lets the right set be mobilised the first time.

Identify what has failed

The failed element decides how temporary power can be connected. A DISCOM feeder outage leaves the site’s own transformer and switchboards healthy, so a rental set can feed the LT board through an existing changeover. A failed distribution transformer leaves the LT board usable but its incomer dead. A switchboard fire or flashover removes the normal connection point entirely, and the rental set must feed sub-boards or critical feeders directly. A failed permanent generator only removes the standby source, which is a different level of urgency again.

FailureImmediate questionLikely temporary arrangement
DISCOM supply lost for a long periodIs the existing DG absent, failed or undersized?Rental set into the DG incomer or changeover
Transformer failureIs the LT board healthy and isolated from the HT side?Rental set to the LT main incomer
Main LT board damagedWhich outgoing feeders are intact?Temporary panel feeding critical circuits directly
Cable faultCan the faulted section be isolated?Local set at the affected building or load
Standby generator breakdownHow long is the repair?Rental set as replacement standby, possibly bridging power

Never energise an unresolved fault

A rental generator is not a way to test whether a damaged board will hold. Before connection, the site’s responsible electrical person should confirm that the faulted equipment is isolated and locked off, that the DISCOM incomer is open so the set cannot back-feed the grid, and that the circuits being restored have been checked for insulation resistance where damage is possible. Protection set for utility fault levels may not clear a fault on generator supply quickly, so a cautious restoration is safer than a fast one. Changeover principles are set out under rental ATS.

Restore in priority order

Emergency restoration rarely needs the whole connected load. Agree the priority list with the facility: life safety and fire systems, then critical process or IT, then cooling and essential services, then everything else if capacity permits. Restoring in steps also manages the first load step. Motors restarting together, UPS batteries beginning to recharge and chillers coming back at once can demand far more than the running load, and a set sized only for running kW may trip. The load-shedding logic in load shedding applies directly.

Mobilisation and site practicalities

Availability depends on the size needed, where the set is and the route to site. A small or medium set on a trailer can move quickly within Hyderabad; a large set needs a suitable vehicle, a crane or hydraulic lift, and a clear, level position near the connection. Confirm access width, overhead obstructions, ground conditions after rain, and the cable length from the set position to the connection point before the vehicle leaves. Bring cables, a temporary panel and fuel for the first day with the set, rather than finding out on arrival that they are missing. Sizing guidance is on generator rental.

When emergency becomes bridging

A transformer replacement or switchboard rebuild often takes weeks, not days. Once the emergency set has run for more than a few days, review the arrangement as a longer-term installation: proper cable protection, refuelling contracts, service intervals, earthing checks and a defined end condition. That transition is covered on bridging power.

Sizing for the restoration step

The estimate does not need to be perfect, but it should be honest. A hospital wing near Secunderabad might need 60 kW of lighting and essential sockets, a 30 kW medical gas and vacuum plant, and a 45 kW chiller (illustrative). Running load is 135 kW, about 170 kVA at 0.8 power factor. The chiller start can briefly add more than its running current several times over, so restoring it last, after the other loads are stable, lets a 200 kVA set carry the duty, whereas switching everything on together would call for a larger set. A clear restoration order is often worth more than extra kVA.

Related photographs and videos

Emergency generator preparedness.
Seasonal power resilience.

The first call: details that decide the response

An emergency is resolved fastest when the first call carries enough information to choose and load the right set. The details below let the set, cables and any changeover equipment be selected before anyone travels.

DetailWhy it matters
What has failedDecides where the set can connect safely
Loads that must come back first, with kW or ampsDecides the set size
Largest motor and how it startsDecides whether the set can accept the first load step
Supply voltage and phasesDecides set and cable configuration
Distance from set position to panelDecides cable length and size
Site access for truck and craneDecides the vehicle and lifting arrangement
Name of the site electrical personThe person who isolates and permits the connection

Photographs of the main panel and the proposed set position, sent by WhatsApp to 98852 01608, often answer half these questions at once.

Sizing for restoration (illustrative)

A hospital wing loses its transformer. The priority loads are 60 kW of lighting and medical equipment, 45 kW of air handling and a 15 kW fire pump that starts direct on line only in a fire. Running priority load is 105 kW, which is about 131 kVA at 0.8 power factor. Allowing for the air handling fans restarting together, a 160 kVA set carries the priority loads with margin, and the fire pump is checked separately as a start on an otherwise loaded set. Restoring the 105 kW in three steps rather than at once keeps each step within what the set accepts comfortably.

Handover and records during an emergency hire

Once the set is running, a short handover note records the connection point, the loads restored, the running hours at start, the fuel level, the alarm list and the names of the people responsible on site. An hourly or shift log of voltage, frequency, load, fuel and any alarms keeps the hire under control and gives evidence for later decisions, such as whether the temporary arrangement should become a longer bridging hire while the permanent repair is completed.

Being ready before an emergency

Sites that depend on power can cut emergency response time by preparing in advance: a recorded connection point for a temporary set, a labelled set of cable glands or a temporary connection box, a list of priority loads with their ratings, and the contact details of the electrical person who can authorise isolation. With that preparation, the call becomes a simple confirmation of what is already written down.

Three emergency decisions that save the most time

Our sets on longer hires are serviced on the same standard as permanent sets: oil and filters every 250 to 500 running hours or six months, whichever comes first, so an emergency that turns into a long hire stays reliable to the end.

Protection on generator supply

A rental set delivers far less fault current than a DISCOM transformer. Breakers set to clear a fault on utility supply may react slowly, or not at all, on generator supply, so a fault that would normally trip a feeder in milliseconds could persist and damage cables. Before restoration, the protection on the circuits being energised is checked against the fault level the set can deliver, and where the margin is doubtful the set’s own breaker is set to protect the temporary arrangement. This check takes minutes and is one of the reasons a cautious restoration is safer than a fast one.

Where the margin cannot be confirmed quickly, restoring fewer circuits at first and watching the set’s current and voltage as each group is added keeps the site safe while the full check is completed, and the protection review becomes part of the handover note.

Common mistakes

What to send us

Call or WhatsApp with the site location, what has failed, the supply voltage and phases, the critical loads with an estimate of their kW, the largest motor, and photographs of the connection point and the access route. An estimate is useful if it is labelled as one. Then follow up through the generator rental enquiry so the details are recorded for the hire.

Questions engineers ask

What should I tell the supplier in the first emergency call?

What has failed, the loads that must come back first with their kW or amps, the largest motor and how it starts, the supply voltage, the distance from the set position to the panel, site access for a truck and crane, and the name of the site electrical person. Photographs of the main panel help greatly.

When does an emergency hire become a bridging hire?

When the permanent repair will take more than a few days, such as a transformer rewind or a switchboard rebuild. At that point fuel deliveries, servicing at the normal interval, operator cover and protection checks are planned for the full period rather than day by day, so the temporary supply stays reliable to the end.

How quickly can an emergency generator be on site?

It depends on the size, where a suitable set is, the distance and the access to your site, so we confirm it when you call rather than promise a time. Small and medium sets are simpler to move than large sets, which need lifting equipment and route planning. Complete details at the first call shorten the arrangement most.

What size generator should I ask for in an emergency?

Ask for one that carries the loads you must restore, not the whole site. Add the running kW of those loads, allow for the largest motor start, and divide by 0.8 to get kVA. If unsure, describe the loads and let the supplier size the set.

Can a rental generator connect to my existing ATS?

Often yes, if the ATS is healthy, rated for the set and its generator-side terminals are accessible. The phase rotation and control wiring must be checked, the existing permanent generator isolated if it is faulty, and a transfer test made before the site relies on the arrangement.

Who is responsible for safe connection?

The authorised electrical person of the site is responsible for isolating the faulted equipment and permitting the connection. The rental team is responsible for the set, its cables and the work it performs. Agreeing these boundaries in writing before energisation is part of a safe emergency response.

Generators by rating

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.

CallWhatsAppEnquire