Data Centre Rental Power

How rental generators support data centres during maintenance or expansion, covering UPS interaction, cooling loads, redundancy and acceptance testing.

In short. Data centre rental power provides temporary generation when a permanent generator, switchgear section or utility path is out of service for maintenance, replacement or expansion. Define which path is unavailable and which loads remain, size for IT load plus cooling and UPS battery recharge, check the generator’s behaviour with the UPS rectifiers, keep the redundancy level the facility depends on, and accept the arrangement by test before relying on it.

When a data centre needs rental power

Typical cases are major overhaul or replacement of a permanent generator, maintenance of an LT switchboard or generator synchronising panel, commissioning of a new hall before its permanent sets arrive, and extended utility work on a feeder. In each case the facility’s redundancy is reduced while the work is done, and the temporary source restores it. The starting question is what has been taken away and what level of resilience the operator must keep during the work.

The load is more than the IT load

A generator feeding a data centre carries UPS input power, which is IT load divided by UPS efficiency, plus battery recharge current after a discharge, plus cooling: chillers or DX units, pumps, CRAH fans, and the controls, lighting and fire systems. Cooling can equal a large fraction of the IT load. After a mains failure the UPS batteries have discharged, and recharge can add 10 to 20% to the UPS input for a period (illustrative; confirm from the UPS data).

Generator kVA ≥ (IT kW ÷ UPS efficiency + recharge kW + mechanical kW + other kW) ÷ PF

Here IT kW is the critical load, UPS efficiency is typically 0.94 to 0.97, recharge kW is the battery charging allowance, mechanical kW covers cooling, other kW covers building services, and PF is the generator rated power factor of 0.8. For 400 kW of IT load at 0.95 efficiency, 60 kW recharge, 200 kW cooling and 30 kW other, the result is (421 + 60 + 200 + 30) ÷ 0.8 ≈ 890 kVA (illustrative). With N+1 that becomes two sets each able to carry the full load, or three smaller sets in parallel.

UPS and generator interaction

Large UPS systems present rectifier loads to the generator. Older six-pulse rectifiers draw high harmonic current; modern IGBT rectifiers are cleaner but have input filters that can make the load leading at light load, which some AVRs handle poorly. UPS systems also check generator frequency before they leave battery or bypass, and a set whose frequency hunts may keep the UPS on battery. Obtain the installed UPS documentation and check walk-in time, frequency tolerance and recharge settings against the rental set’s governor and AVR. More in UPS and non-linear loads and ATS, STS and UPS transfer coordination.

Keep the redundancy the facility depends on

Permanent designWork being doneTemporary provision to keep resilience
N+1 generatorsOne generator outRental set connected to restore N+1, ideally synchronised to the bus
2N power pathsOne path’s switchboard outRental set feeding the affected path so both paths remain backed
Single generatorGenerator replacementRental set into the ATS, with a second set if the risk justifies it

Connection may be to a dedicated rental termination cabinet, a spare breaker on the generator bus or the ATS generator side. Synchronising a rental set to an existing bus needs compatible controls; see synchronising panels.

Test before relying on it

A load-bank test proves the rental set’s output and cooling; it does not prove the transfer, the UPS acceptance or the step load. A practical acceptance sequence is a load-bank run to the planned load, then a supervised transfer test under the facility’s change-control procedure, with voltage, frequency and UPS status recorded. Bank sizing is covered in load-bank sizing. Return to the permanent arrangement needs the same control, with the permanent equipment tested before the rental set is removed.

Site and operational details

Rental sets for a data centre are usually positioned in a yard or car park, so the cable route to the connection cabinet, its protection from vehicles and the security of the area must be planned. Fuel autonomy should at least match the facility’s own standard for the duration of the work, with a refuelling arrangement that does not depend on access through secured areas at night.

Remote monitoring of the rental set into the facility’s building management or alarm system lets operators see its status alongside the permanent plant. Hyderabad summers push ambient temperatures above 40 degrees Celsius, so check the set’s derated output at the expected ambient, especially when enclosures sit close together and recirculate hot air. Finally, the method statement should name who may start, stop or transfer the rental set, because uncontrolled switching by well-meaning staff is one of the commonest causes of incidents during maintenance windows.

A worked sizing record (illustrative)

The formula above becomes clearer in a table. The figures below continue the 400 kW IT example and show how each part of the load builds up to the generator rating.

Load elementBasiskW
UPS input400 kW IT ÷ 0.95 efficiency421
Battery rechargeAllowance from UPS data60
CoolingChillers or DX, pumps, CRAH fans200
Other building servicesLighting, controls, fire systems30
TotalSum of the above711
Generator kVA711 ÷ 0.8889, rounded to about 890

With N+1 redundancy the facility needs either two sets each above 890 kVA, so that one can carry the load alone, or three sets that share the load and leave one in reserve. The choice depends on the existing switchgear and whether a synchronising panel is available for the rental sets.

Acceptance test before the work window

  1. Run the rental set on a load bank to its rated load and record voltage, frequency and temperatures.
  2. Transfer the actual facility load in the agreed steps and confirm the UPS accepts the generator supply without returning to battery.
  3. Simulate a UPS recharge condition where the facility procedure allows, and confirm the set holds frequency.
  4. Check that alarms from the rental set reach the facility monitoring or a manned point.
  5. Record fuel level, refuelling arrangements and the running log format.

Only when every step is signed off is the permanent equipment released for work. A load-bank test beforehand removes most of the uncertainty from the day.

Fuel autonomy for the work window

Data centres usually require a stated number of hours of fuel on site. For the example above, carrying about 711 kW at roughly 0.27 litres per kWh, the rental sets together use close to 190 litres an hour, so twelve hours of autonomy needs about 2300 litres on site. External tanks, refuelling access and fuel quality checks are planned with the facility, and the fuel is sampled on delivery.

Working within change control

Data centre operators run strict change-control processes. A rental arrangement fits into them when it comes with a method statement, the single-line diagram of the temporary arrangement, the acceptance test plan, the switching programme and the roll-back plan if anything goes wrong. Providing these documents early lets the operator review the arrangement on its own terms and approve the work window with confidence.

Typical data centre rental arrangements

SituationUsual arrangementKey check
One permanent set overhauledRental set into that set’s incomer or synchronising sectionController compatibility or separate transfer
LT switchboard maintenanceRental sets feeding UPS inputs and cooling boards directlyConnection points independent of the board under work
New hall before permanent sets arriveRental sets as the hall’s standby sourceRedundancy equal to the hall design
Extended utility feeder workRental set supporting the permanent plantFuel autonomy and refuelling plan

Harmonics and power factor with UPS loads

UPS rectifiers draw current in pulses rather than smooth waves, and the generator’s alternator must supply those pulses through its own internal reactance. A set feeding a large share of rectifier load can show voltage distortion that a utility transformer would hide. Modern active-front-end UPS units reduce the problem, but their input filters can make the load leading at light load, which some voltage regulators handle poorly.

When rental sets are chosen for a data centre, the share of rectifier load, the UPS rectifier type and the alternator reactance are reviewed together, and an alternator one frame size larger is sometimes the simplest cure. The acceptance test confirms the result with a power quality reading at the UPS input.

Recording the voltage distortion and power factor during the acceptance test also gives the facility a baseline for future rental arrangements, so the next work window starts with known figures rather than assumptions.

Where the reading shows distortion close to the UPS input limits, the remedy is chosen before the work window rather than discovered during it, whether that is a larger alternator, a different set or a staged transfer of the rectifier load.

Common mistakes

What to send us

Send the single-line diagram with the equipment being taken out of service, the IT load and UPS make and rating, the cooling and building services loads, the facility’s redundancy requirement and the planned work window. Send a generator rental enquiry and we will propose the sets, connection and test plan.

Questions engineers ask

How is a rental generator accepted for a data centre?

By test before the work window: a load-bank run to rated load, transfer of the actual load in agreed steps with the UPS accepting generator supply, alarms confirmed to the facility monitoring, and fuel and refuelling arrangements recorded. Only when every step is signed off is the permanent equipment released for work.

How much fuel autonomy should rental sets have at a data centre?

The number of hours the operator requires, calculated from the actual load. For about 711 kW at roughly 0.27 litres per kWh the sets use close to 190 litres an hour, so twelve hours needs about 2300 litres on site, with external tanks, refuelling access and fuel sampling planned with the facility.

How big should a rental generator be for a data centre?

Large enough for UPS input, battery recharge, cooling and building services at the 0.8 rated power factor of the generator, with redundancy matching the facility design. IT load alone understates the requirement. In the worked example, 400 kW of IT load needs about 890 kVA once all elements are added.

Can a rental set be synchronised with the permanent generators?

It can if its controller is compatible with the existing synchronising and load-sharing system, or if a dedicated synchronising panel is provided. Otherwise it serves a separate section through its own transfer arrangement. Either way, the arrangement is proved by test before the work window begins.

Will my UPS accept generator power?

Most modern UPS systems do, provided the frequency and voltage of the generator stay within the UPS input tolerance and the set is sized for the rectifier and recharge load. Check the UPS walk-in time, frequency window and recharge settings, and test with the actual rental set before the work window.

Does rental power affect data centre certification?

Rental equipment does not itself certify a facility. Whether the temporary arrangement maintains the design redundancy of the facility is for the operator and its engineers to confirm under their change-control process, supported by the method statement, the single-line diagram of the temporary arrangement, the switching programme and the acceptance test records.

Generators by rating

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.