In short. A warehouse can have the lights on and still be stopped, because dispatch depends on the warehouse management system, the network, scanners, dock equipment and security as much as on illumination. Backup power should carry the digital and safety loads first, the handling equipment needed for the operating model next, and treat forklift charging as deferrable. Size from the shift profile, not the connected load, and plan cable routes around vehicle movement.
What actually stops when a warehouse loses power
Logistics sites in the corridors around Hyderabad, Medchal, Shamshabad and along the Vijayawada highway are built around flow: goods in, put away, pick, pack, dispatch. An outage interrupts the flow in ways that are not obvious from the electrical drawing. The warehouse management system server or its link to the cloud drops, so no pick lists are issued. Wireless access points go dark, so handheld scanners cannot confirm anything.
Dock levellers and shutter doors stop mid-travel, so vehicles cannot be loaded. Conveyors and sorters stop with parcels on them. Barcode and label printers reset. CCTV and access control fail at the moment when the site is most exposed. A modern fulfilment centre with automated storage or a sorter is more fragile still, because its control system must be re-homed before anything moves.
The engineering consequence is that the backup scope must be built from the operating model rather than from a list of electrical equipment. Ask what must keep running to receive, pick and dispatch during an outage of the expected duration, and what can wait.
Classify the loads by what they do for dispatch
| Function | Typical equipment | Consequence of loss | Priority on generator |
|---|---|---|---|
| Life safety | Fire pumps, sprinkler controls, emergency lighting, smoke vents, PA | Statutory and safety exposure | First, by design |
| Digital control | WMS servers, network switches, access points, scanners, printers | No transactions, no dispatch | UPS, then generator |
| Security | CCTV, access control, gate barriers, perimeter lighting | Theft and audit exposure | Early |
| Dock operations | Levellers, shutter doors, dock lights | Vehicles cannot load or unload | Early, sequenced |
| Material flow | Conveyors, sorters, vertical lifts, cranes | Throughput loss | Depends on operating model |
| Task lighting | High-bay LED in active aisles | Picking stops | Active zones only |
| MHE charging | Forklift and reach-truck chargers | Deferrable for hours | Shed, restore later |
| Temperature-controlled zones | Chillers, cold rooms | Product loss | See cold-storage guidance |
| Offices and canteen | Air conditioning, pantry | Inconvenience | Last or excluded |
Where the site includes cold rooms or a frozen zone, the refrigeration plant changes the sizing entirely and has its own rules, which are covered on cold-storage power. The general method of ranking loads is on critical-load classification.
Sizing from the shift profile
Warehouse demand moves through the day. Inbound peaks in the morning, picking and packing through the shift, dispatch in the evening, and the forklift fleet charging overnight. The generator should be sized for the loads that will run together during backup operation, which is rarely the site’s metered maximum demand, because charging and offices are shed. Measure or log the demand for a week if a meter is available, then subtract the deferrable and excluded loads and add the starting demand of the largest motor in the retained set, usually a conveyor drive, a sorter or a chiller.
S_gen = (P_retained / PF) + S_start
In this expression S_gen is the indicative generator kVA, P_retained is the running kW of the retained loads, PF is their power factor and S_start is the transient apparent power of the largest motor start once the base load is on the bus.
For a 20,000 square metre dry warehouse with 110 kW of retained lighting, IT, security, docks and conveyors at 0.85 PF, and a 22 kW conveyor drive started direct-on-line, S_gen is about 130 kVA plus roughly 170 kVA of transient, pointing to a 200 to 250 kVA set depending on the acceptable voltage dip (illustrative). If the same site insisted on charging 40 forklifts during the outage, the figure would double, which is why charging is normally deferred. The full method is on generator sizing.
Battery charging as a managed load
Forklift chargers are large, numerous and tolerant of delay. A fleet of lead-acid trucks charges for eight hours overnight; lithium fleets use opportunity charging through the shift. In both cases a load management scheme that blocks chargers on loss of mains and releases them in groups once the generator has capacity avoids a much larger set. If the generator is a paralleled plant, chargers become the lowest priority step in the controller’s shedding table; see load management.
Fire load and generator location
Warehouses carry a high fire load in packaging, pallets, plastics and stored goods, and the fire authority’s requirements for the sprinkler and hydrant pumps often set a minimum generator capability regardless of commercial preference. The generator itself and its fuel storage should be located so that they are not inside the storage hazard, with the CPCB stack height, ventilation and acoustic requirements met, and with vehicle protection where trucks reverse nearby. The room or enclosure needs maintenance access that does not require closing a dock. Installation considerations are set out on installation planning.
Temporary and rental power on a working site
Many logistics sites take a rental set for an HT shutdown, a transformer change or a peak season, and the problems are rarely electrical. The set must be placed where trucks do not reverse into it, cable routes must cross yards and docks without becoming trip or crush hazards, and the connection point must be agreed with whoever controls the main switchboard. Define cable routes and ramps on the actual site plan, agree who operates the changeover and who refuels, and confirm the site’s operating hours so that testing does not coincide with the dispatch peak. Practical points are on rental and temporary power and rental cables and distribution.
A dispatch-first load register (illustrative)
A regional distribution centre classifies its loads by what each does for dispatch. The register shows how a site of about 900 kW connected load needs far less on the generator.
| Class | Loads | Supply | Demand |
|---|---|---|---|
| Digital | WMS servers, network, scanners, label printers | UPS, generator behind it | 25 kW |
| Safety and security | Fire systems, emergency lighting, CCTV, access control | Generator, with batteries where required | 30 kW |
| Dock operations | Dock levellers, shutters, dock lighting | Generator | 45 kW |
| Picking area | Lighting in active aisles, conveyors and sorters | Generator, restarted in sequence | 120 kW |
| Cooling for staff areas and server room | Server room AC, selected ventilation | Generator | 35 kW |
| Deferrable | Forklift chargers, general HVAC, yard lighting at day | Shed, resumed on the DISCOM supply | Not on generator |
The protected demand is 255 kW, about 320 kVA at 0.8 power factor. A 400 kVA set carries it at about 80% with conveyors restarted in sequence, instead of a set sized for the full connected load.
Forklift chargers and battery equipment
Forklift and pallet-truck chargers are heavy, rectifier-type loads. During a short outage, most fleets have enough charge to keep working, so chargers are usually deferred until the DISCOM supply returns. Where a site runs three shifts with little spare battery capacity, a share of the chargers can be placed on the generator, staggered so they do not start together and allowed for in the alternator selection because of their harmonic current.
Seasonal peaks and growing sites
Warehouses grow. Festival peaks bring extra shifts, temporary conveyors and more lighting, and new tenants add cold rooms or automation. The generator plan records the present protected load and the margin left, and the margin is checked whenever a new load is proposed. Where growth is expected, a set position, cable route and changeover rated for a larger future set save a complete re-installation later.
Service and testing
On sets we maintain, oil and filters are changed every 250 to 500 running hours or six months, whichever comes first, and coolant is replaced every year. Because a warehouse standby set rarely sees real load, a periodic test on the protected loads, or on a load bank, proves it can carry the dispatch operation when it matters.
When a cold room joins the warehouse
Many warehouses add a cold room or chilled zone for pharmaceuticals or food. Refrigeration then becomes the most time-sensitive load on the site, because stock can be lost within hours. The cold room is added to the protected register with its own restart step, its controller and temperature logger are put on UPS, and the generator margin is checked for the refrigeration start before the room is commissioned.
A quick check each quarter of the protected load against the register keeps the plan honest, because warehouse loads change faster than most buildings.
Common mistakes
- Backing up lighting and leaving the network cabinet on the mains. The building is lit and nobody can pick, pack or dispatch.
- Including the forklift charging room in the generator scope. The set is sized for a load that could have waited eight hours.
- Starting conveyors, sorters and dock equipment together after transfer. The combined inrush trips the generator and the control system must be re-homed.
- Placing the rental set and cables in the truck apron. A reversing vehicle damages a cable or the set in the first week.
- Assuming the fire pump is on the generator because it is in the building. Fire pump supply arrangements are statutory and must be designed, not assumed.
What to send us
Send a site plan showing docks, yard and the main switchboard, a load list grouped by function with motor ratings for conveyors, sorters and any refrigeration, the IT and network loads, the number and type of charging points, and your metered demand data if available. Tell us whether the requirement is a permanent standby set, a rental for a shutdown or season, or both. Send your warehouse power requirement.
Questions engineers ask
Which warehouse loads should be on the generator first?
The digital loads that make dispatch possible, such as WMS servers, network, scanners and label printers on UPS, then safety and security systems, dock equipment, picking-area lighting and conveyors restarted in sequence. Forklift chargers and general HVAC are usually deferred until the DISCOM supply returns.
How should a warehouse plan its generator for growth?
Record the present protected load and the margin left, and check that margin before every new load such as a cold room or automation line. Where growth is expected, a set position, cable route and changeover rated for a larger future set avoid a complete re-installation later.
What size generator does a warehouse need?
It depends on the retained loads, not the floor area. A dry warehouse that retains safety, IT, security, docks and some conveyors often needs 150 to 300 kVA (illustrative), while adding refrigeration or full charging can multiply that. Measure, decide what is shed, then size.
Should forklift chargers be on the generator?
Usually not. During a short outage most fleets have enough charge to keep working, so chargers are deferred until the DISCOM supply returns. On three-shift sites with little spare battery capacity, a share of chargers can be placed on the set, staggered and allowed for in the alternator selection.
Do WMS servers and network equipment need a UPS as well as a generator?
Yes. The generator needs seconds to start and transfer, and servers, switches and scanners drop out in that gap, losing transactions and forcing restarts. A UPS carries them through the transfer and the generator then carries them and recharges the UPS for the rest of the outage.
How should a rental generator be placed on a busy logistics site?
Away from truck routes, dock aprons and turning areas, on firm ground with barriers, with exhaust directed away from docks and offices and cables protected where vehicles cross. Fuel deliveries need their own safe access, and the position should not block emergency routes or fire hydrants.
Can a warehouse generator also serve a future cold room?
It can, if the margin was planned. The cold room adds a refrigeration load with its own starting step, and stock can be lost within hours, so it is added to the protected register, its controller goes on UPS and the generator capacity is checked for the start before commissioning.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.