In short. A mobile or trailer generator changes its electrical and physical environment with every deployment, so mobility is an engineering parameter, not a chassis option. Each new site brings a different load, cable length, earthing arrangement, connection point, ground condition and ambient. The set may be unchanged between projects, but voltage drop, fault current, protection, earthing and placement must be checked again every time it moves, or the convenience of mobility becomes a safety problem.
What mobile means in practice
Three configurations are usually grouped under the heading. A trailer-mounted set is built on a road-towable chassis with axles, brakes and lighting, in the range of roughly 15 to 500 kVA, and moves behind a vehicle. A skid or containerised set can be lifted and transported on a truck but is not towed, and covers larger ratings. A truck-mounted set is fixed to a vehicle for rapid response.
The word mobile should not suggest that any generator can be put on wheels and moved: transport suitability depends on the specific unit’s mass, dimensions, lifting points and the applicable road rules. Mobile sets serve construction, infrastructure, maintenance outages, remote work, commissioning, events and emergency response, and most are rented rather than owned; a set that will stay in one place for years is better specified as a stationary set. The mobile generator rental page covers that route.
| Check before every deployment | What changes between sites | Consequence if skipped |
|---|---|---|
| Electrical connection | Voltage, phase sequence, connection point, upstream protection | Reverse rotation of motors, wrong breaker coordination |
| Load | Running kW, largest motor start, nonlinear content | Voltage dip, tripping, overheated alternator |
| Cable run | Length, size, route, mechanical exposure | Voltage drop, cable damage, earth faults |
| Earthing | Soil, available electrode, bonding to the installation | Protection does not operate, touch voltage hazard |
| Position | Ground bearing, level, exhaust clearance, airflow | Overheating, fumes into buildings, trailer movement |
| Fuel | Hours of running, refuelling access | Set runs dry at the worst moment |
Every site is a new earthing question
A fixed generator is earthed once and tested. A mobile set is connected to a different earth at every site, and the quality of that earth decides whether the protection works and whether a damaged cable becomes a shock hazard. The set’s neutral should be earthed at the generator by a driven electrode with a measured resistance, or bonded to the installation’s existing earth when the set feeds a building’s switchboard, and the frame bonded to the same point.
Which arrangement is right depends on whether the set feeds a stand-alone temporary installation or an existing one, and on whether the existing supply neutral is still connected. A remembered earth resistance figure from the last site is no use at the next one. Residual current protection on all final circuits is the practical safeguard where the earth path is uncertain. The earthing guide explains the arrangements for each case.
Long cables, voltage drop and fault current
Mobile sets are often placed where they can be reached by the towing vehicle, which may be 100 or 200 metres from the load. Over that distance a flexible cable sized for current alone may drop voltage well beyond the 3 to 5% that motors and electronics tolerate, and the generator’s own limited fault current, typically around three times rated current sustained for a few seconds, may not be enough to trip a downstream breaker through the cable impedance.
Voltage drop (V) = √3 × I × L × (R cos φ + X sin φ)
I is the load current in amperes, L the one-way cable length in kilometres, R and X the cable resistance and reactance per kilometre, and cos φ the load power factor. For 150 A at 0.85 power factor over 150 metres of 50 mm² copper, with R near 0.39 and X near 0.08 ohms per kilometre, the drop is about 15 V, or 3.6% at 415 V (illustrative), which is close to the limit before any motor starting is considered. The voltage drop guide and the temporary cable page cover sizing and routing.
Towing, placement and the physical site
Transport introduces requirements that have nothing to do with electricity: gross trailer mass and the towing vehicle’s rating, brakes and lighting, registration where the road rules require it, and lifting points and slinging for skid sets. On site, the trailer must stand on firm, level ground, chocked and with the jockey wheel and stabilisers down, clear of excavations and traffic, with the radiator discharge and exhaust pointing away from buildings, tents and people and with free airflow around the canopy.
Security matters because mobile sets are stolen and tampered with; a fenced compound with the fuel inside it is the norm on longer deployments. Repeated redeployment also wears the set differently from fixed duty: door seals, cable glands, battery terminals and fuel connections loosen with road vibration and need a check at each arrival.
Load, protection and fuel on the move
The load at a new site must be assessed as if the set were being selected fresh. Motors, drives, welders and UPS behave differently from the resistive loads the rating implies, and a set that served an office cabin well may be wrong for a pumping station. Protection settings that suited the previous site’s cable and load should be reviewed for the new one, and the connection to an existing installation must prevent any possibility of back-feeding the grid, which means an interlocked changeover rather than a plug into a socket.
Fuel is planned per deployment: the integral tank of a trailer set typically gives 8 to 12 hours at 75% load, so longer jobs need an auxiliary tank or a refuelling arrangement. The generator sizing guide applies in full to each new deployment, and the generator systems overview explains the selection chain it follows.
Related photographs and videos
Worked example: cable length and voltage drop (illustrative)
A 62.5 kVA trailer set at 415 V delivers about 87 A at full load. Through a 35 mm² copper cable at operating temperature, with a power factor of 0.85, the drop grows with every metre of cable.
| Cable length | Voltage drop | Share of 415 V |
|---|---|---|
| 50 m | About 4.3 V | About 1.0% |
| 100 m | About 8.7 V | About 2.1% |
| 200 m | About 17.4 V | About 4.2% |
Running drop is only the first check. On a long cable the earth fault loop impedance rises, and the set’s breaker may no longer see enough current to trip quickly on a fault at the far end, so a residual current device or a larger cable is needed. Motor starting adds a much larger dip than the running figure. See cable sizing and voltage drop studies.
Fuel planning for a mobile set
A modern 62.5 kVA set uses roughly 11.5 to 12.3 litres an hour at three-quarters load, so a 100-litre tank lasts about eight hours. On a site that runs around the clock, refuelling has to be planned with access for the bowser, spill containment and someone responsible for each fill. Running a set dry lets air into the fuel system and needs bleeding before it will restart, often at the worst moment.
Before every move
- Shut down, isolate and disconnect all cables and earth connections.
- Secure doors, the fuel cap and any loose items; check for leaks.
- Inspect tyres, brakes, lights and the coupling.
- Check the route for height, width and ground conditions at the new site.
- On arrival, level the set, chock the wheels, earth it, then connect and test before loading.
Safe connection points
A mobile set must never be connected to a building by back-feeding through a socket or by joining cables to a live board. The connection is made through a changeover switch or a dedicated generator inlet that isolates the grid supply first, so the set cannot energise the utility network and the utility cannot feed back into the set. On temporary sites, distribution boards with residual current protection on every outgoing circuit protect people working near long cable runs. See rental distribution panels.
A short written checklist kept with the set, and signed at each move, makes these steps routine for every crew that handles it.
Common mistakes
- Connecting the set without earthing it because the job is only for a day. A damaged lead becomes a shock hazard and residual current devices behave unpredictably.
- Reusing a cable drum sized for a previous short run on a 200-metre run. Voltage drop trips motor contactors and the generator is blamed.
- Plugging a mobile set into an installation without an interlocked changeover. The set back-feeds the DISCOM line and endangers linesmen.
- Parking the trailer against a wall or under a canopy for shade. Hot air recirculates into the radiator and the set shuts down on temperature.
- Assuming the integral tank covers the shift. The set stops at night and the pump or lighting it served goes with it.
What to send us
Send the load list for the deployment with the largest motor and its starting method, the distance from where the set can stand to the connection point, and whether the set will feed a stand-alone temporary installation or an existing switchboard. Add the daily running hours, the duration of the job, the site access for a towing vehicle or crane, and photographs of the connection point and the ground where the set will stand. Send your mobile generator requirement.
Questions engineers ask
How much voltage drop does a long cable from a trailer generator cause?
For a 62.5 kVA set delivering about 87 A through 35 mm² copper at 0.85 power factor, roughly 1.0% at 50 m, 2.1% at 100 m and 4.2% at 200 m. Long runs also raise the earth fault loop impedance, so a residual current device or a larger cable may be needed for safe disconnection.
How long does a mobile generator run on one tank?
A modern 62.5 kVA set uses roughly 11.5 to 12.3 litres an hour at three quarters load, so a 100-litre tank lasts about eight hours. Sites running around the clock need planned refuelling with access, spill containment and a named person responsible, because running dry lets air into the fuel system.
Does a trailer generator need to be earthed at every site?
Yes. The neutral and frame must be earthed at each deployment, either by a driven electrode with a measured resistance or by bonding to the installation’s existing earth, depending on how the set is connected. Earthing from the previous site does not travel with the trailer.
How far can a generator be placed from the load?
As far as the cable can carry the current within about 3 to 5% voltage drop and still allow the protection to trip on a fault at the far end. For a 125 kVA set this is typically 100 to 200 metres with properly sized copper cable, and longer runs need larger cable or a closer position.
Can I plug a mobile generator into my building supply?
Only through a changeover switch or a dedicated generator inlet that isolates the grid first. Back feeding through a socket or joining cables to a live board can energise the utility network, endangering line workers, and can damage the set when the grid returns. Have the connection installed and checked by a competent electrician.
What size trailer generator can be towed by a pickup?
It depends on the towing vehicle’s rated capacity and the trailer’s gross mass. Sets up to roughly 60 to 100 kVA on a single or tandem axle trailer are commonly towed by light commercial vehicles; above that a truck or a flatbed transport is usually needed. Confirm the specific unit’s mass against the vehicle rating.
Generators by rating
- Under 15 kVA generators
- 15–50 kVA generators
- 50–125 kVA generators
- 125–250 kVA generators
- 250–500 kVA generators
- 500–1000 kVA generators
- 1000–2000 kVA generators
- 2000 kVA and above generators
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.
