In short. The right generator follows from your load, duty, site and rules. Work through the steps below, then send the details to us. We will size the set properly rather than selecting from the connected load alone.
Step 1: define the load
- List equipment with kW or kVA and power factor.
- Note the largest motor and its starting method. See motor starting.
- Identify UPS, drives and other nonlinear loads. See UPS and nonlinear loads.
Step 2: define the duty
| Duty | Meaning |
|---|---|
| Standby | Runs during utility failure; few hours per year |
| Prime | Main source with variable load |
| Continuous | Constant load, long hours |
| Rental / temporary | Short-term need. See rental power |
Step 3: size
Size for running load, starting surge, site conditions and growth. See generator sizing, ambient derating and altitude derating.
Step 4: rules and fuel
Check emission rules for your location and fuel options. See emissions overview and cleaner fuels.
Step 5: system
Decide on ATS or AMF, parallel operation, redundancy and enclosure. See N+1 and synchronisation.
Step 6: commissioning and support
Plan commissioning, load bank testing and AMC.
What to send us
Load list, duty, location, fuel, space, noise limits and timeline. Send your application details or call 98852 01608.
A worked example, start to finish (illustrative)
A commercial building in Secunderabad needs backup for lifts, fire pumps, lighting, IT and part of the air conditioning.
| Step | Decision | Result |
|---|---|---|
| 1. Load | Essential load list after demand factors | 380 kW running, 0.85 power factor, so 447 kVA |
| 2. Duty | Standby, outages of a few hours, occasional long outages | Standby rating applies |
| 3. Size | Largest motor 55 kW star-delta, summer ambient 45 °C, growth 15% | Approximately 447 × 1.15 ÷ 0.95 ≈ 540 kVA required, so a 625 kVA class set is shortlisted and the motor start is checked |
| 4. Rules and fuel | Check current emission and noise rules for the set and site | Confirm applicable norms before ordering |
| 5. System | ATS, single set, space for a second | Provision for future paralleling |
| 6. Commissioning | Load bank test, service contract | Documented acceptance |
Choosing between standby, prime and continuous
- Standby: runs only during outages. Highest rating for the same machine, limited annual hours.
- Prime: runs as the main source with variable load. Lower rating and an overload allowance.
- Continuous: runs at constant load for unlimited hours, lowest rating.
Using a standby-rated set for long running hours shortens its life. Match the class to the duty and confirm definitions with the maker.
Single set, parallel sets or hire
| Option | Best when |
|---|---|
| Single set | Modest load, an outage of hours tolerable, budget limited |
| Parallel sets (N+1) | Critical load, growth expected, maintenance without outage needed |
| Rental | Temporary need, event, shutdown or bridging a repair. See rental power |
Fuel and emissions
Diesel remains the common choice for backup. Cleaner-fuel options, including dual fuel and emission-control retrofits, depend on duty and regulation. Confirm current official notifications for your site. See cleaner-fuel generator systems and emissions and power transition.
Site, noise and ventilation
Generator rooms and canopies need combustion air, cooling airflow and an exhaust path. Poor ventilation derates a set more than altitude does. Acoustic enclosures and silencers meet noise limits at the boundary. Hyderabad’s dust and monsoon humidity affect filters and electrical enclosures.
Which rating band fits which site
| Rating band | Typical sites | What usually decides the size | Guide |
|---|---|---|---|
| Under 15 kVA | Homes, small shops, clinics, telecom shelters | Single-phase motors and air conditioners starting | Under 15 kVA |
| 15 to 50 kVA | Offices, bank branches, small workshops, apartment common services | Lift and pump starting, single-phase balance | 15 to 50 kVA |
| 50 to 125 kVA | Commercial floors, function halls, small factories, cold rooms | The largest motor start | 50 to 125 kVA |
| 125 to 250 kVA | Mid-size factories, hotels, hospital blocks, construction sites | Block loads after transfer and motor groups | 125 to 250 kVA |
| 250 to 500 kVA | Commercial towers, process plants, larger hospitals | Redundancy and the restart sequence | 250 to 500 kVA |
| 500 to 1000 kVA | Industrial plants, data rooms, campuses | Paralleling, fault level and switchgear | 500 to 1000 kVA |
| 1000 kVA and above | Large plants, utilities, multi-set power stations | System design, often several sets in parallel | 1000 to 2000 kVA |
The band is a starting point, not the answer. Two sites with the same running load can need sets a full band apart because of one large motor, a UPS or a demand for redundancy.
The information that settles the choice
| Information | Why it matters |
|---|---|
| Loads that must run on generator, with kW and power factor | Sets the running kW and kVA |
| Largest motor, its kW and starting method | Often decides the size more than the running load |
| UPS, drives and other electronic loads | Harmonics and recharge load on the alternator |
| Expected hours: occasional outages, daily cuts or continuous | Selects the standby, prime or continuous rating |
| Site location, room or open yard, and neighbours | Derating, enclosure, noise and ventilation |
| Existing switchboard and incomer | Changeover type, AMF panel and cable route |
| Growth expected in the next few years | Margin now, or space for a second set later |
A photograph of the main switchboard and the nameplates of the largest motors often answer half these questions in one message.
New, used or rented
| Route | Suits | Watch for |
|---|---|---|
| New set | Long service life ahead, current emission stage required, maker warranty wanted | Lead time for larger ratings |
| Used or refurbished set | Standby duty, budget limits, quick delivery, a proven frame | Condition proven by a load test, emission stage accepted at the site |
| Rental set | Temporary need, events, shutdowns, bridging a repair or a delivery wait | Fuel arrangements, operator and the scope of cables and panels |
Reddy Generators sells used sets as is, with an inspection report, and refurbished sets with a six-month warranty, of all major makes from 15 to 2000 kVA, every one load-bank tested before sale; we also rent sets and buy used sets or take them in part exchange. See used and refurbished generators and rental power.
Planning fuel before buying
Fuel is the largest running cost of most sets, so it belongs in the choice. At about 75% load, a 125 kVA set uses roughly 21 to 23 litres an hour, a 250 kVA set about 42 to 46 and a 500 kVA set about 77 to 83, ranges drawn from the published data of several makers.
A site with four hours of outage a day on a 250 kVA set at that load burns about 42 to 46 × 4 × 30, roughly 5040 to 5520 litres a month. That figure sizes the tank, the delivery arrangement and the budget, and it shows why an oversized set, running lightly loaded, wastes fuel as well as capital. See DG fuel consumption chart.
Space and weight to allow for
| Canopied set, typical | Length | Width | Height | Weight |
|---|---|---|---|---|
| 125 kVA | About 3.0 to 3.3 m | About 1.1 m | About 1.5 to 1.8 m | About 1.7 to 2.0 t |
| 250 kVA | About 3.3 to 3.8 m | About 1.1 to 1.2 m | About 1.8 to 1.9 m | About 2.4 to 3.0 t |
| 500 kVA | About 4.3 to 4.5 m | About 1.45 to 1.6 m | About 2.2 to 2.3 m | About 4.3 to 4.8 t |
Ranges are drawn from data sheets of several makers and differ by engine and enclosure, so the actual set’s drawing governs. Allow about a metre of clear space around the canopy for doors and maintenance, a level foundation able to take the weight, a route for the crane or forklift, and space for the exhaust to discharge away from windows and air intakes. See outdoor installation.
From enquiry to a running set
- Load list, duty and site details shared, with photographs.
- Sizing checked for running load, largest motor start and site derating.
- Set, changeover or AMF panel, cables and earthing proposed as one scope.
- Foundation, cable route and exhaust prepared on site.
- Set delivered, installed, connected and earthed.
- Commissioning with a load test and a transfer test on the real changeover.
- Service plan agreed, so the set is ready on the day it is needed.
Noise, exhaust and approvals
Diesel sets in India are subject to noise and emission rules that affect the choice of set and its position. Sets up to the larger commercial ratings are supplied in acoustic enclosures built to a noise limit of 75 dB(A) at 1 m from the enclosure surface, and the exhaust must discharge through a stack whose height above the building is commonly set by a rule of about 0.2 × √kVA metres: about 2.2 m for a 125 kVA set, 3.2 m for 250 kVA and 4.5 m for 500 kVA, added to the height of the building.
The emission stage of the set must be one the local authority accepts. Rules change, so the current notification and the local pollution control board’s requirements are confirmed before ordering. See acoustic enclosures and exhaust systems.
What keeps the set ready afterwards
A standby set fails most often when it is called after months of standing. A service plan that includes regular runs on load, battery and charger checks, fuel quality checks and filter changes on schedule keeps it ready. Reddy Generators services the sets it supplies, and other makes, across Telangana, Andhra Pradesh and the districts within about 300 km of Hyderabad, with project-based service further afield.
Each of these steps is quick when the information in the table above is ready, and each one avoids a mistake that is expensive to correct after the set is installed.
Common mistakes
- Sizing on connected load instead of demand.
- Ignoring the largest motor start.
- Choosing the engine and forgetting the alternator reactance.
- Leaving out fuel storage and delivery planning.
- No load bank testing at handover.
The master engineering question
If the utility fails now, will this set start, carry my real load and keep running for as long as I need it?
Questions buyers ask
How much diesel does a generator use in a month?
Multiply the hourly use at the expected load by the running hours. At about 75% load a 125 kVA set uses roughly 21 to 23 litres an hour, a 250 kVA set about 42 to 46 and a 500 kVA set about 77 to 83, depending on the make. A 250 kVA set running four hours a day for a month at that load uses roughly 5040 to 5520 litres, which sizes the tank and the budget.
How high must a generator exhaust stack be?
A common rule sets the stack height above the building at about 0.2 times the square root of the kVA rating, in metres: about 2.2 m for 125 kVA, 3.2 m for 250 kVA and 4.5 m for 500 kVA, added to the building height. Confirm the current rule and the local pollution control board requirements before installation.
Can I choose by kVA alone?
No. Two sites with the same kVA of load can need sets a full rating band apart. The largest motor and how it starts, UPS and drive loads, the running hours, site temperature and altitude, and any need for redundancy all change the answer. A short load list with the largest motor settles it.
New or used?
It depends on duty, budget, delivery time and the emission stage the site needs. For standby duty a tested used set is often sound value; for long daily running a refurbished set with a warranty, or a new set, is safer. Whatever the route, insist on a load test of the exact set.
Do I need an ATS?
For automatic changeover when the grid fails, yes, either as an automatic transfer switch or as an AMF panel that starts the set and switches the load. A manual changeover is cheaper but needs someone on site to start the set and switch over during every outage.
Can you size from my bill?
Bills help, because the billed maximum demand shows the peak drawn from the grid. They do not show which loads must run on generator, the largest motor start or the UPS load, so a short load list of the loads to be backed up gives a far better answer than the bill alone.
Guidance only. Final selection needs site data.
Generators by rating
- Under 15 kVA generators
- 15–50 kVA generators
- 50–125 kVA generators
- 125–250 kVA generators
- 250–500 kVA generators
- 500–1000 kVA generators
- 1000–2000 kVA generators
- 2000 kVA and above generators
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.