In short. A critical-power design should be reviewed at defined stages by people able to challenge it, and accepted only on evidence. A stage-gate framework sets the questions, documents and tests for each stage, so gaps are found while they are cheap to fix. The same gap costs a drawing change at design, rework at commissioning, or an outage after handover. Acceptance criteria are written as measurable numbers before the tests, not after.
Who this page is for: For owners, project managers, consultants and commissioning teams delivering hospitals, data rooms and other critical-power projects.
Key facts
- Review at each gate: requirements, concept, detailed design, procurement, commissioning, handover.
- The cost of fixing a gap rises sharply at each later stage.
- Write acceptance criteria as measurable values, agreed before testing.
- Log every finding with severity, owner and closure evidence.
- Do not hand over with open critical findings.
- Use an independent reviewer on high-consequence systems; they find what the design team overlooks.
Stage gates
| Gate | Focus | Typical evidence |
|---|---|---|
| Requirements | What must be protected, for how long, against which failures | Load classification, outage tolerance, risk assessment |
| Concept design | Architecture and redundancy | Single-line diagram, redundancy and SPOF review |
| Detailed design | Ratings, protection, controls | Calculations, studies, FMEA, test plan |
| Procurement and factory tests | Equipment fit and quality | Data sheets, factory test results |
| Installation and commissioning | Build quality, functional tests | Inspection and test records |
| Integrated testing and handover | Whole-system performance | Integrated test report, as-builts, training, manuals |
Design review questions
- Which loads are critical, and what is each one’s tolerable outage?
- Which failures does the design survive, and which not?
- Where are the single points of failure and shared dependencies?
- Do capacity, fault levels and protection hold in every configuration?
- Can every component be maintained with the load supplied?
- How does the system start, transfer, recover and black-start?
- Are controls, DC and communications redundant where needed?
- How will each claim be tested?
Measurable acceptance criteria (examples)
| Item | Example criterion |
|---|---|
| Generator start and transfer | Emergency board on generator within the time the design and code require, for example 10 to 15 s |
| Voltage during load steps | Dip within the agreed limit and recovery to within ±1% of setpoint within a few seconds |
| UPS autonomy | At least the design minutes at the measured site load |
| Load sharing | kW and kVAr sharing between sets within the agreed tolerance, for example ±5% |
| Protection | Operating times within the relay’s declared tolerance of the settings |
| Failure injection | Critical loads stay supplied when one set fails to start |
Worked example: the same gap at three stages (illustrative)
Both ATS controllers on a project take control power from one 24 V supply, which makes them a common failure.
| Found at | Fix | Relative cost and disruption |
|---|---|---|
| Detailed design review | Drawing change: two supplies with monitoring | Hours of design time |
| Commissioning | Panel rework, rewiring, retest; programme slips | Days, plus rework cost |
| A real outage after handover | Both ATS fail to transfer; critical loads drop | The outage itself, plus emergency repair |
The gate review exists to find this kind of item at the first stage. See single-point-of-failure elimination.
Do not write acceptance criteria after the test, and do not skip gates under schedule pressure. A test without a criterion agreed in advance proves only that something happened, not that it met the requirement.
Items that are often missed
- Fuel autonomy and delivery agreements.
- Cooling for electrical rooms during generator operation.
- Black-start capability.
- Alarm routing and out-of-hours response.
- Capacity headroom under failure conditions.
- Maintenance procedures for every component.
Managing findings
- Log each finding with severity and owner.
- Decide: fix, accept with a recorded reason, or retest.
- Track it to closure with evidence.
- Do not hand over with open critical findings.
Handover package
- As-built single-line, control and wiring drawings.
- Calculations, study reports and protection settings.
- Test and commissioning records, including the integrated test. See integrated systems testing.
- Operating and emergency procedures.
- Maintenance plan, spares list and training records.
See also the FAT and SAT framework.
Findings log
The log from the same 800 kW semiconductor plant, carried across all six gates. It is a different project from the single 24 V control supply traced through three stages in the example above, and it shows the other half of that story: not what one finding costs at each gate, but what a whole project’s findings look like when each is caught at the earliest gate that could have caught it. Six findings, in gate order, with the closure evidence that actually shut each one.
| No. | Gate | Finding | Severity | Owner | Closure evidence |
|---|---|---|---|---|---|
| 1 | Requirements | The load schedule has no non-essential class, so all 800 kW was being carried to the essential board. The generator sizing was being driven by offices and a canteen | High | Client engineering | Revised schedule showing 400 critical, 320 essential and 80 non-essential, signed by the plant engineer. Essential board 720 kW |
| 2 | Concept | A and B equipment shares one switch room. Full separation was not possible within the existing building | Medium — accepted with mitigation | Design lead | Fire barrier between the two halves, separate detection zones, residual risk written into the risk register and signed off by the client |
| 3 | Detailed design | A and B distribution units sized at 125 kVA against a 40% loading rule, but the schedule puts pair 2 at 44%, which is 88% on one path rather than the 80% assumed | High | Design lead | Pair 2 split across an additional pair of units. Recalculated to 38% normal and 77% on one path; new schedule issued |
| 4 | Procurement | The UPS offered has one static bypass per system. The specification required two independent bypass paths | High | Procurement | Supplier substituted the specified unit at no change to the programme. Factory test witnessed and the report filed against this finding |
| 5 | Commissioning | No generator setting group loaded. On one set, a remote fault on the 400 A feeder sits at about 2 kA and is not selective against the incomer | High | Commissioning engineer | Setting group 2 loaded and proved by primary injection at 2 kA. Feeder cleared in about 0.1 s with the incomer intact; results against the selectivity matrix |
| 6 | Handover | The operating instructions do not record the required position of tie Q7, and Q7 was found closed during the A and B audit | Medium | Client operations | Single line marked up, Q7 padlocked open, position entered in the daily log and a high-priority alarm added for Q7 closed |
The last column is the only one that closes a finding, and it is the column most logs leave as “done”. None of these six would be shut by that word. A revised and signed schedule, a witnessed factory report, an injection result at a stated current, a padlock and a log entry — each one is a thing that exists and can be produced two years later by somebody who was not in the room. A finding whose closure evidence is a verb rather than an artefact is still open, whatever the spreadsheet says.
Finding 1 is the one worth dwelling on, because it is a requirements finding and it is the entry on this sheet that was least expensive to put right. Nobody had written a non-essential class, so 80 kW of offices and canteen was sitting on the essential board, and the generator sizing was being driven by it.
Caught at the requirements gate it is an afternoon with a load schedule. Caught at commissioning it is a pair of sets bought a size larger than the plant needs, and nothing about that can be unwound. The gates are ordered the way they are because the questions they answer get more expensive in exactly that order.
Finding 2 shows the other thing a log has to be able to do, which is to carry a finding that will not be fixed. Full A and B separation was not achievable inside the existing building, so the honest outcome is not a fix and not a deletion: it is a mitigation, a residual risk recorded in words, and a signature from the person who accepted it.
Logs that can only record closures quietly lose these, and they are precisely the items the next engineer needs to know about. The rule that keeps the log trustworthy is narrow and absolute: nothing hands over with an open high finding, and anything accepted rather than fixed hands over with a name against it.
Lastly, note how often one finding is another page’s subject. Finding 3 is a loading calculation, finding 5 is a selectivity study, finding 6 is an audit result and an alarm. A design review does not generate findings of its own kind; it is the mechanism that makes every other discipline produce its evidence before the plant is handed over rather than afterwards.
Checking the design basis against the site
Every design rests on a set of assumptions about the site: the load, the fault level of the supply, the ambient temperature, the space available. A design review that checks the drawings against those assumptions, without checking the assumptions against the site, can approve a design that is correct on paper and wrong in reality. The first questions in any review should test the basis itself.
| Assumption | Check against | What goes wrong if it is wrong |
|---|---|---|
| Critical and total load | A week of measured demand at the boards, plus the documented growth allowance | Equipment oversized and inefficient, or undersized from the first year |
| Utility fault level | Figures obtained from the utility in writing, at the actual connection point | Switchgear under-rated for the real fault current |
| Generator fault current and decrement | The alternator maker’s data for the actual machine | Protection that never trips on generator supply |
| Ambient temperature | Measured temperatures in the actual rooms on a hot afternoon | Derated equipment and battery life far shorter than planned |
| Space and access | A site visit with the layout drawings | Equipment that cannot be installed, serviced or replaced as drawn |
Each assumption should appear in the design basis with its source and date. An assumption marked “estimated” is a finding in itself, to be replaced by a measurement before the design moves to the next gate.
Reviewing the equipment that is actually offered
A design is reviewed against the specification; the equipment is then bought from offers that may differ from it in ways the offer does not highlight. Submittal review closes that gap: each major item’s datasheet, drawings and test plan are checked line by line against the specification before the order is confirmed.
Typical differences found are a UPS whose rating assumes a different output power factor, a changeover rated for a lighter duty category than specified, a generator quoted on its standby rating where prime was required, and switchgear with a lower short-time rating. Each difference is either accepted in writing, with its consequence recorded, or corrected before manufacture. Found at this stage, a difference costs a revised offer; found at commissioning, it costs the project’s programme.
Common mistakes
- Skipping gates under schedule pressure.
- Acceptance criteria written after the test.
- Handover without as-built records.
- No independent review on high-consequence systems.
What to send us
Send your design documents, test plan and acceptance criteria for review. WhatsApp 98852 01608 or use the enquiry form.
Evidence note. The criteria shown are examples; each project sets its own from its requirements and the applicable codes.
Questions engineers ask
What should a design review check before it checks the drawings?
The design basis itself: the critical and total load against a week of measured demand, the utility fault level against written figures from the utility, the generator fault current against the alternator maker data, the ambient temperature against measurements in the actual rooms, and space and access against a site visit. An assumption marked estimated is a finding in itself, to be replaced by a measurement before the design passes the next gate.
What is a submittal review?
A line-by-line check of each major item datasheet, drawings and test plan against the specification, before the order is confirmed. It finds differences such as a UPS rated at a different output power factor, a changeover rated for a lighter duty, a generator quoted on standby rating where prime was needed, or switchgear with a lower short-time rating. Each difference is accepted in writing with its consequence, or corrected before manufacture.
When should a design be reviewed?
At each stage gate, with deeper reviews at concept and detailed design when changes are cheapest. Later reviews at construction and commissioning confirm that what is built matches the reviewed design, and any change made on site is reviewed again by the same reviewers before it is energised.
What are good acceptance criteria?
Measurable, agreed in advance and tied to the requirements. For example, transfer to generator within a stated time, voltage dip on the largest step within a stated limit, and no single failure causing loss of a critical load. Each criterion has a test method, so acceptance rests on recorded results rather than opinion.
Is an independent review necessary?
It is valuable for high-consequence systems because it challenges assumptions the design team may share. The reviewer checks the requirements, studies and single points of failure with fresh eyes, and the findings are answered in writing so each one is closed, changed or formally accepted.
What belongs in handover?
As-built records, studies, test results, procedures, maintenance plans and training. Single-line diagrams, protection settings, panel schedules, operating and emergency procedures, spares lists and warranty details are all included, and the operations team confirms they can run the system before the designers and installers step away.
This guide gives general principles. Apply your organisation’s design and quality procedures.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.