In short. Choose a critical power architecture by working from requirements, not equipment. The requirements are: how long a break the load can take, how much downtime per year the business can accept, whether maintenance must happen without a shutdown, and how the load will grow. Those answers point to a UPS type, a generator arrangement and a distribution scheme. Then check the choice against the budget.
Who this page is for: For owners, consultants and facility managers starting a new critical power design or reviewing an existing one.
Key facts
- Start with the allowed break: none, seconds or longer.
- Then the downtime the business can accept per year.
- Then whether servicing must happen without shutdown.
- Then load size, growth and site constraints.
- Only then choose UPS, generator and distribution arrangements.
- Before finalising, check for shared weak points that could take out both paths, such as one fuel tank, one room or one controller.
Requirement to architecture
| Requirement | Typical architecture |
|---|---|
| Short break acceptable; small site | Generator with automatic changeover |
| No break for a few loads | Online UPS for those loads, generator for the rest |
| Servicing without shutdown | N+1 UPS and generators with maintenance bypass |
| Survive any single failure | 2N or distributed redundant, separated A and B paths |
| Long outages likely | More fuel storage, multiple sets, possibly battery storage |
Worked example: three sites (illustrative)
| Site | Key requirement | Architecture chosen |
|---|---|---|
| Office, 80 kW | Servers no-break; rest short-break | 10 kVA UPS for servers; 125 kVA generator with changeover |
| Process plant, 600 kW | Controls no-break; process must restart safely | UPS for controls; two generators with load shedding and staged restart |
| Hospital block, 400 kW critical | Survive any single failure; service without shutdown | Distributed redundant UPS, N+1 generators, A and B distribution |
See load classification, bus arrangements and fault tolerance.
Do not choose the architecture first and fit the requirements to it afterwards. The cost of redundancy is justified only by a requirement that needs it.
Requirement sheet
| Question | Answer |
|---|---|
| Break the critical load can take | |
| Downtime acceptable per year | |
| Servicing without shutdown needed? | |
| Load today and in five years | |
| Longest outage to plan for |
Not every load needs the top tier
The most common and most costly mistake in choosing a critical power architecture is to treat the whole site as one load and buy the arrangement the most demanding part of it needs. Almost every site divides into loads that cannot tolerate any break, loads that can tolerate the seconds a generator takes to start, and loads that can wait. Sizing each layer of the architecture for its own class, rather than for the total, usually changes the result entirely.
| Load class | Example on a 400 kW site | What it needs | Sized for |
|---|---|---|---|
| No break | Servers, control systems, critical instruments: 60 kW | UPS, with generator behind it | 60 kW plus margin, not 400 kW |
| Short break, seconds | Essential lighting, pumps, cooling for the UPS room: 140 kW | Generator through an automatic changeover | 200 kW with the no-break class, plus its starting steps |
| Long break or none | Comfort cooling, non-essential process, workshops: 200 kW | Mains only, or generator if capacity allows | Shed in an outage, or restored last |
In this example a single architecture for the whole 400 kW would mean a UPS of that size and a generator to match. Split by class, the UPS serves 60 kW, the generator serves 200 kW with headroom for motor starts, and 200 kW is shed. The protection given to the loads that need it is the same; the equipment, the losses, the battery and the maintenance are a fraction. The split has to be done honestly, load by load, with the people who run each area, because a load placed in too low a class is discovered only during an outage.
Designing for the load the site will have, not the load it has
A critical power system lasts fifteen years or more, and the load it serves rarely stands still. A critical load of 120 kW growing at 10% a year reaches about 193 kW in five years; at 8%, about 176 kW. The architecture has to accommodate that growth without a rebuild, which does not mean buying the five-year capacity on day one.
What has to be sized for the final load is everything that is hard to change later: the switchboard ratings and busbars, the cable routes and their capacity, the space for additional UPS modules or units and their batteries, the generator room or plinth, the fuel storage and the cooling. What can be added as the load grows are the modules themselves, the battery strings, and in some designs a second generator.
A modular UPS in a frame sized for the final load, cabled and protected for it, with modules added as the load arrives, is the clearest example. Write the growth assumption into the design basis, so that the people who extend the system years later know what it was designed to take.
Buying the final capacity on day one has costs of its own beyond the outlay. A UPS loaded at a fifth of its rating runs at poor efficiency and wastes energy for years; a generator lightly loaded for most of its running hours suffers from it; a battery sized for the final load and installed on day one may reach the end of its life before the load it was bought for ever arrives.
Matching the installed capacity to the actual load, within an infrastructure sized for the final load, avoids all three. The test is simple: at commissioning, each item should be loaded within a sensible range of its rating, and the plan should say when and how each next step of capacity will be added.
Turning the business’s tolerance into a design target
Asking what availability a site needs usually produces a vague answer. Asking how many hours a year without supply the business can accept produces a number, and the number converts directly into a target.
| Acceptable time without supply | Equivalent availability | Architecture usually needed |
|---|---|---|
| A day a year | 99.73% | Single supply, generator, manual or automatic changeover |
| 8.76 hours a year | 99.9% | Automatic changeover, UPS for the critical class, tested maintenance |
| 4 hours a year | 99.95% | Redundant UPS capacity, maintenance bypasses, spares on site |
| 1 hour a year | 99.99% | Redundant paths with nothing shared, concurrent maintenance |
Two further questions sharpen the target. How long can a single outage last before it causes harm — is it the total hours that matter, or any outage over a few minutes? And does the business need to carry out maintenance without any shutdown, or can it accept a planned shutdown each year? A site that can accept one planned shutdown a year can meet a demanding availability target with a far simpler arrangement than one that must stay up through every maintenance task.
One generator, two, or three
The number of generators is one of the decisions most often made by instinct. Suppose each set, on a given demand, starts and takes load successfully 98% of the time. One set large enough for the whole load gives 98%. Two sets, each large enough for the whole load, fail only if both fail: about 99.96%. But two sets that must both run to carry the load, each at half the size, are worse than one: both must succeed, about 96.04%. Three half-size sets, any two of which can carry the load, give about 99.88%.
The arithmetic makes the rule plain: splitting a generator into smaller units adds resilience only if there is at least one more unit than the load needs. Two half-size sets with no spare are the arrangement to avoid, because they double the chances of a failed start without adding any cover. Where two sets are chosen for maintenance or growth reasons, size them so that either can carry the critical classes alone, shedding the rest, and the resilience follows.
The site constraints that decide what is possible
An architecture chosen on paper must still fit the building. Batteries are heavy and concentrated, and a battery room on an upper floor needs its floor loading checked by a structural engineer. Generators need air in and air out, an exhaust route, fuel delivery access and space for maintenance, and their noise affects neighbours.
Fuel storage above certain quantities needs approval and separation from other buildings. Two independent paths need two independent routes through the building for their cables, which is easy to draw and often hard to build. Each of these constraints should be checked before the architecture is fixed, because a design that cannot be built as drawn ends up built with compromises that undo its redundancy.
Questions that test a proposed architecture
Before an architecture is approved, it should be walked through a short set of questions, each answered on the single-line diagram rather than in general terms.
| Question | What a good answer looks like |
|---|---|
| What happens when each item fails, one at a time? | For every breaker, UPS, transformer, cable and controller, the critical load stays supplied or the break is within its class |
| How is each item maintained? | A switching sequence that keeps the critical load supplied, or a planned shutdown the business has accepted |
| What is shared between paths? | Nothing, or a short list of items each with a stated reason and mitigation |
| Where does growth go? | Named spaces, ratings and cable routes for the final load |
| How is it tested once built? | An integrated test plan covering every failure and transfer, with recorded results |
An architecture that cannot answer the first question for every item has a single point of failure that has not yet been found. Answering it on the drawing, item by item, takes an afternoon and is the most valuable afternoon in the design.
Record the answers, the load split, the growth assumption and the availability target together in a short design basis. It is the document that lets anyone who later extends, modifies or audits the system understand what it was meant to do, and it is the first thing missing on most sites where an extension has quietly removed the redundancy the original design provided.
Common mistakes
- Copying another site’s design.
- Redundancy without a requirement.
- Growth not considered.
- Fuel and outage length ignored.
What to send us
Send your answers to the requirement sheet. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. The examples are illustrative.
Questions engineers ask
Should the whole site be on the UPS?
Rarely. Most sites divide into loads that need no break, loads that can wait the seconds a generator takes to start, and loads that can be shed. On a 400 kW site with 60 kW of no-break load, 140 kW of essential load and 200 kW that can wait, the UPS serves 60 kW plus margin and the generator about 200 kW. The critical loads get the same protection with a fraction of the UPS, battery, losses and maintenance.
Are two generators more reliable than one?
Only if either one can carry the load. If each set starts successfully 98% of the time, one full-size set gives 98%, two full-size sets about 99.96%, but two half-size sets that must both run only about 96.04%, worse than one. Three half-size sets, any two of which can carry the load, give about 99.88%. Splitting a generator adds resilience only with at least one more set than the load needs.
Where do I start if I do not know my requirement?
Begin with a load list and ask what happens to each load if power is lost for one second, a minute and an hour. The answers group loads into no-break, short-break and long-break classes, which then set where UPS, generator capacity and redundancy are needed.
Is there one architecture that fits all sites?
No. The right design depends on tolerance, failure targets, duration and constraints. A small office, a hospital and a process plant need very different arrangements, and copying another site design can either overspend or leave critical loads exposed. The requirement is written first, and the architecture is chosen to meet it.
Do I need 2N?
Only if you must survive the loss of a whole system or keep full redundancy during maintenance. 2N doubles the main equipment and its cost, so it is justified where the cost of an outage is high and the failures it protects against are credible. Many sites meet their target with N+1 and good maintainability instead.
How do I check the final design?
By single-point-of-failure review, studies for protection and capacity, and integrated testing. The review checks the design on paper, the studies prove ratings and selectivity in every source state, and the integrated test proves on site that the whole system responds to failures as the design intended.
This guide gives general principles. Final design needs a site-specific engineering review.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.