In short. A rental battery energy storage system solves short-duration power problems differently from a generator: it delivers power instantly, absorbs load steps, covers short outages and lets generators run less or at better load. It must be specified by both power (kW or MW) and energy (kWh or MWh), because a battery with enough energy but too little inverter power, or the reverse, fails the application. Availability is confirmed per project with specialist supply partners.
Where temporary storage helps
- Peak support, where a site’s demand briefly exceeds its grid connection or generator capacity.
- Generator hybridisation, where a battery carries light overnight load so the diesel set can stop.
- Short-duration backup for loads that need power for minutes rather than hours.
- Temporary grid constraints, where a sanctioned load cannot be increased in time for a project.
- Commissioning support, where a stable source is needed to test equipment without running a generator for long periods.
The first question is always which behaviour you are trying to change: generator run hours, low-load running, short peaks, number of starts, transient response, or short-duration continuity. Each points to a different power-to-energy ratio.
Power and energy are separate requirements
Power in kW determines how much the BESS can deliver or absorb at any instant, limited by the power conversion system. Energy in kWh determines how long it can sustain that power. “We need a 1 MWh battery” does not say whether the site needs 100 kW for ten hours or 1 MW for one hour, and the two systems are completely different in inverter size and cost.
Installed energy (kWh) = load (kW) × duration (h) / (usable depth of discharge × round-trip efficiency to the load)
Load is the real power the battery must supply, duration is how long it must supply it, usable depth of discharge is the fraction of nameplate energy the system allows you to use while keeping its reserve, and efficiency accounts for inverter and battery losses.
As an illustration (illustrative), supporting 200 kW for 2 hours with 85% usable depth and 92% efficiency needs about 200 × 2 ÷ (0.85 × 0.92), roughly 511 kWh installed, with a power conversion system of at least 200 kW plus margin for transients. That establishes only the minimum steady requirement; motor starts, auxiliary loads, temperature derating and the state-of-charge reserve kept for emergencies all add to it. The battery energy storage systems page explains chemistry and duration classes.
Typical rental use cases and ratios
| Application | Power need | Energy need | Typical ratio of kWh to kW |
|---|---|---|---|
| Absorbing motor starts on a small generator | High | Low | About 0.5 to 1 |
| Peak shaving above a grid limit | Moderate | Moderate | About 1 to 2 |
| Overnight load so the generator can stop | Low | High | About 4 to 8 |
| Short outage cover for a process | Matches process load | Minutes to an hour | About 0.25 to 1 |
Batteries with generators
Most temporary BESS deployments in India sit alongside a diesel set rather than replacing it. The battery handles light load and step changes, while the generator runs at an efficient load to carry the bulk and recharge the battery. This reduces low-load running, which causes wet stacking and carbon build-up, and reduces fuel per kWh. A hybrid study needs more than peak demand: minimum, average and peak load, transient events, an hourly profile, and which loads are critical. The hybrid temporary power page covers the control strategy, and the generator plus BESS screening guide gives a method for checking whether the combination pays off.
Charging is a load too
When the generator recharges the battery, the charging current adds to the site load. A charge rate set too high can push the generator into overload exactly when the site load is also rising. The controller must limit charging to the generator’s spare capacity.
Safety does not reduce because the system is temporary
Lithium-based containerised systems need the manufacturer’s separation distances from buildings and other equipment, working thermal management for Hyderabad summer temperatures above 40 degrees Celsius, DC and AC protection, fire detection and a suppression approach appropriate to the chemistry, and an emergency plan that local responders understand. Placement must keep the container out of waterlogging during the monsoon. Cooling auxiliaries draw power continuously, which counts against the energy available to the load.
Project inputs
A temporary BESS is configured from the load profile and duration, the expected cycling per day, the connection voltage, the state-of-charge reserve to be held for emergencies, the environment and the charging source, whether grid, generator or solar. Without those inputs, any quoted container size is a guess.
Related photographs and videos
Sizing power and energy together (illustrative)
A night-time site load of 40 kW is carried by a 250 kVA diesel set that runs at about 20% load from 10 pm to 6 am. Adding a temporary battery lets the set stop overnight. The battery is sized in two separate steps.
| Step | Working | Result |
|---|---|---|
| Inverter power | Night load 40 kW plus margin for load steps | About 60 kW |
| Energy delivered | 40 kW × 8 hours | 320 kWh |
| Usable fraction | Keep a reserve and stay within the depth of discharge, say 80% usable | 320 ÷ 0.8 = 400 kWh installed |
| Recharge | From the diesel set during the day at a good load | About 400 kWh needs several hours at a meaningful charge rate |
The diesel set no longer runs eight hours a night at 20% load, which is the condition that glazes engines and wastes fuel. Whether the arrangement pays for itself depends on the hire costs of the battery against the fuel and engine wear saved, which is assessed for each project.
Making batteries and generators work together
- Who forms the grid: either the battery inverter or the generator sets voltage and frequency at any moment, and the control scheme must say which, with clean transitions between them.
- Charging limits: the generator must carry the site load plus the charging power, so charging is limited when the site load is high.
- Light-load protection: the controls start the generator at a load level that keeps it well loaded, rather than at every small drop in battery charge.
- Outage behaviour: where the grid is also present, the system must island cleanly and never back-feed the DISCOM network.
Site safety for a temporary battery
A containerised battery holds a large amount of stored energy. Its position needs separation from buildings and fuel storage, ventilation and temperature control, fire detection and the suppression the supplier specifies, clear access for emergency services, and signage. Cables between the battery, the inverter and the site are protected and labelled, and isolation points are marked so that the system can be made safe quickly. Approvals for fire safety and any grid connection are confirmed early, because they can take longer than the equipment.
What to send for a temporary storage enquiry
A logged load profile over several days, the purpose of the battery (peak support, overnight running, outage cover or load-step support), the generators already on site, the grid connection details, the available space and the intended duration. With these, the power and energy can be sized, and the feasibility of supply is confirmed for the specific project.
Where temporary storage earns its place
| Situation | What the battery does | What decides the size |
|---|---|---|
| Generator at light load overnight | Carries the night load so the set can stop | Night kW and hours |
| Large motor starts on a small set | Supplies the start surge so the set does not dip | Inverter kW for a few seconds |
| Peak above the grid connection | Supplies the peak for its duration | Peak kW above the limit and its length |
| Bridging the start of a generator | Holds critical loads until the set is ready | Critical kW for a few minutes |
Each case needs a different balance of inverter power and stored energy, which is why the purpose is settled before any equipment is discussed.
Monitoring a battery on site
A temporary battery is watched through its state of charge, cell temperatures, alarm list and the energy delivered and received each day. These figures, compared with the generator’s running hours and fuel use, show whether the hybrid arrangement is delivering the savings expected and whether its settings need adjusting.
A month of recorded figures usually shows the real pattern of charging and discharging, and the control settings can then be tuned so the generator runs fewer hours at a better load, which is where most of the saving comes from.
What a temporary battery cannot do
A battery does not create energy; every kWh it delivers was first put in by the grid, solar or a generator, with some loss on the way. It cannot carry a large load for a long outage without becoming very large, and its inverter limits the power it can deliver however full it is. Recognising these limits early keeps the battery in the role it does best: short, fast, frequent support alongside a generator that provides the energy.
Common mistakes
- Specifying only kWh. The battery has plenty of energy but its inverter cannot deliver the peak, and the load trips.
- Specifying only kW. The battery handles the step perfectly but empties within minutes of an outage.
- Letting the generator recharge the battery at full rate. Combined charging and site load overloads the set.
- Placing the container in full sun with no allowance for cooling energy. Output is derated and usable energy falls.
What to send us
Send the load profile, ideally hourly data or a logged week, the outcome you want from storage, the required power and duration if known, the connection voltage, the existing generator or grid source, and the site location for the container. Use the application engineering enquiry so the requirement can be screened with our storage partners.
Questions engineers ask
How is a temporary battery sized?
In two separate steps. Inverter power in kW is sized for the load the battery must carry plus margin for steps, and stored energy in kWh is sized from that load multiplied by the hours, divided by the usable fraction. A 40 kW night load for eight hours needs 320 kWh delivered, about 400 kWh installed at 80% usable.
Can a battery stop a generator running at light load overnight?
Yes. A battery can carry a light night load while the generator stops, and the generator recharges it during the day at a good load. That avoids hours of light-load running, which glazes engines and wastes fuel. Whether it pays depends on the hire costs of the battery against the fuel and wear saved.
Can a rental BESS replace a diesel generator entirely?
Only for short durations or where it can be recharged from the grid or solar. For long outages the energy required makes a battery-only system very large and costly, so the usual arrangement is a battery supported by a generator, with the battery carrying light loads and steps and the generator recharging it.
How fast does a BESS respond to a load change?
Grid-forming systems respond within a few cycles, far faster than a diesel engine governor. That is why a battery is effective at absorbing motor starts and load steps that would otherwise dip the frequency and voltage of a generator, and why it pairs well with a smaller or gas-fuelled set.
What is a sensible state-of-charge reserve?
It depends on the purpose. Where the battery also provides outage cover, keep enough energy to carry the critical loads until a generator starts and stabilises, typically several minutes of the critical load. For pure peak shaving the reserve can be smaller, but some reserve always protects battery life.
Does a temporary BESS need approvals?
Grid-connected operation may need DISCOM agreement, and fire safety arrangements may need local approval depending on the size and location. Confirm the requirements early, since approvals can take longer than delivery, and plan separation, ventilation, detection and emergency access as part of the same review.
Generators by rating
- Under 15 kVA generators
- 15–50 kVA generators
- 50–125 kVA generators
- 125–250 kVA generators
- 250–500 kVA generators
- 500–1000 kVA generators
- 1000–2000 kVA generators
- 2000 kVA and above generators
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.