Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

80 kVA generator rental for an international offshore pipeline contractor at Kakinada

An 80 kVA diesel generator hired from August 2009 for an international offshore pipeline contractor at Kakinada, extended from three to about five months.

In short. In August 2009 an international offshore pipeline contractor, based in Switzerland, hired an 80 kVA diesel generator from Reddy Generators for its project at Kakinada on the Andhra Pradesh coast. The hire was ordered for about three months and, in November 2009, extended by two more, giving roughly five months of continuous supply under the contractor’s own international purchasing terms.

ClientAn international offshore pipeline contractor headquartered in Switzerland (name withheld)
LocationKakinada, Andhra Pradesh
Start1 August 2009
DurationAbout 3 months, extended in November 2009 by 2 months (about 5 months)
Equipment80 kVA diesel generator on rental
TermsDelivered duty paid at Kakinada, to the client’s equipment specification

The requirement

Offshore pipeline projects run an onshore base for logistics, offices, stores and workshops. The contractor needed dependable power there for the duration of the campaign, supplied to its own specification and documentation standards, which are typically stricter than a local hire.

An extended hire

The original order covered about three months. As the project ran on, the client revised the order in November 2009 to add two more months. An extension like this is common on marine projects, where weather and vessel schedules move the end date, and it is one reason long-duration rental needs servicing and breakdown cover agreed from the start.

What an onshore base for an offshore campaign needs

Offshore pipeline work is supported from land. The onshore base holds the project office, stores for pipe coatings and spares, workshops, and often a radio room that keeps contact with vessels. Each of these needs power for the whole campaign, often from early morning to late night, and some of it, such as communications and computers, cannot tolerate repeated interruptions.

Area (illustrative)Typical loadsSensitivity
Project officeComputers, printers, air conditioning, lightingHigh for computers and communications
Radio and communications roomRadios, network equipment, small UPSVery high
StoresLighting, fans, small handling equipmentLow
WorkshopPower tools, small welding, pumpsLow, but causes load swings

Worked example: loading an 80 kVA set (illustrative)

An 80 kVA set gives 64 kW at 0.8 power factor. A base of this kind might draw about 20 kW for the office and communications, 12 kW for cooling, 8 kW for stores and lighting and around 10 kW in the workshop when tools are running, roughly 50 kW at the busiest time. That leaves margin for motor starts and short peaks. Communications equipment sits behind a small UPS so that any transfer or dip does not interrupt contact with the vessels, and workshop loads are kept on their own circuit so their swings do not reach the radio room.

Meeting an international client specification

International contractors usually issue an equipment specification and expect documents that a local hire might not need. Preparing these before delivery avoids delays at the gate.

DocumentPurpose
Equipment data sheetConfirms rating, voltage, enclosure and fuel capacity
Load-bank test reportShows the set delivered its rated output before dispatch
Earthing and insulation test recordsConfirms electrical safety at installation
Maintenance plan for the hireShows when services will fall and who carries them out
Safety informationCovers fuel handling, hot surfaces, noise and emergency stop

Every rental set is load-bank tested before dispatch, and the report from that test forms part of the delivery documents.

Planning for an extension from the start

Marine campaigns depend on weather windows and vessel schedules, so their end dates move. A hire ordered for three months may well run to five or more, as happened here. The safest approach is to plan from day one as though the hire will be extended: service intervals counted in running hours and calendar time, consumables and filters held for the longer period, and the breakdown arrangements written to cover any extension. When the extension comes, it then needs only a revised order, not a new set of arrangements.

Service across a five-month hire

If the base runs about 14 hours a day, seven days a week, the set runs around 420 hours a month and roughly 2100 hours over five months. With oil and filters at 250 to 500 hours, that means a service roughly every three to five weeks. Planning those visits around port and base routines, and recording hours daily, keeps the set serviced on time while the campaign is at its busiest.

Port and coastal conditions

A base near a port faces salt air, humidity and, in the monsoon, heavy rain and flooding risk. The set is placed on raised ground or a plinth clear of standing water, the enclosure is kept closed and its drains clear, terminals are cleaned and protected at each service, and alternator insulation is checked regularly. Cable routes avoid low points where water collects.

Reporting to the client

International contractors often expect regular reports on equipment they hire. A simple monthly summary of running hours, fuel used, services carried out and any faults, signed by both sides, gives the client the evidence its own systems require and keeps fuel reconciliation clear.

Worked example: fuel for the base (illustrative)

At an average load of about 35 kW over a 14-hour day and around 0.29 litres per kWh, the set uses roughly 10 litres an hour, about 140 litres a day and some 4300 litres a month. Knowing the figure lets the base plan deliveries and storage, and lets both sides check the log against what the hours and load justify.

Closing out the hire

  1. Agree the end date once the base no longer needs temporary power.
  2. Prove that any replacement supply is working before disconnection.
  3. Record final hours and fuel, and agree any fuel left in the tank.
  4. Remove the set and cables safely and leave the area clean.
  5. Hand over the final log and service records to the client.

Lessons for similar marine projects

For marine and pipeline projects, the onshore base is the quiet foundation of the whole campaign. Separating sensitive communications from workshop loads, protecting the set against coastal conditions, preparing the documents an international client expects, and planning service as though the hire will be extended are what keep the base powered while attention is focused offshore.

Distribution around the base

A single set feeding several buildings needs a small but properly designed distribution system. A main board beside the set feeds separate circuits to the office, the communications room, stores and the workshop, each with its own protection. Residual current devices protect circuits feeding portable tools and outdoor sockets. Cables are buried or raised clear of vehicle routes and protected where they cross roads. Labelling each circuit at both ends makes isolation safe and fault finding quick, especially when base staff change during the campaign.

Keeping communications powered through every transfer

Communications with vessels cannot drop out while the generator is serviced or when mains, if available, is connected or removed. A small online UPS on the communications circuit carries it through these moments. Its battery is sized for the longest planned break, such as a service changeover, with margin, and it is tested by switching off its input during a planned check. The UPS is also checked for compatibility with the generator, so it stays on its rectifier rather than draining its battery whenever the set frequency moves slightly.

What changes when a hire is extended

ItemShort hireExtended hire
ServicingPerhaps none during the hireSeveral services planned inside the hire
ConsumablesFew neededFilters, oil and belts held for the longer period
RecordsBasic hours logMonthly reports for the client
Breakdown arrangementsSimpleWritten into the revised order

Spares worth keeping at the base

Oil, fuel and air filters, a drive belt, fuses for the control panel and a spare starting battery cover the faults most likely to stop a set on a remote base. Holding them on site means a minor fault can be put right quickly instead of waiting for parts to travel.

Noise and rest areas

Bases often include rest rooms or accommodation for crews working long shifts. Placing the set away from these areas, using an acoustic enclosure and keeping its doors closed while running lets crews rest properly between shifts.

Earthing on sandy or reclaimed ground

Coastal bases often sit on sandy or reclaimed land, where soil resistivity changes sharply between wet and dry seasons. An earth electrode that tests well after rain may read much higher in the dry months. Testing the earth at installation and again after a dry spell, and adding electrodes or treatment where readings rise, keeps fault protection effective for the whole campaign. The generator earth is bonded to the base distribution earth so no dangerous voltage can appear between equipment.

Planning for the monsoon

A campaign that runs into the monsoon faces heavy rain, flooding and occasional storms that stop deliveries. Before the season, the set location is checked for drainage, cable joints are sealed, extra fuel is stored where safe and permitted, and the anti-condensation heaters are confirmed working. These steps prevent the most common wet-season failures: water in fuel, damp alternator windings and flooded cable joints.

A short pre-monsoon walk round, recorded in the log with the date and the actions taken, gives the client evidence that the base power is ready for the season and shows the next team what was checked.

Kept together, the log, reports and test records form a complete history of the hire that both sides can rely on.

Outcome and limits

The set was supplied from August 2009 and the hire extended once, for about five months in total. This record is based on the client’s purchase order and its revision; operating logs are not published.

Questions engineers ask about this project

What documents does an international contractor expect with a rental generator?

Typically an equipment data sheet, the load-bank test report from before dispatch, earthing and insulation test records from installation, a maintenance plan for the hire and safety information covering fuel, hot surfaces, noise and the emergency stop. Preparing them in advance avoids gate delays. Copies stay at the base.

How should a rental be planned when the end date may move?

As though it will be extended. Count service intervals in hours and calendar time, hold filters and consumables for the longer period, and write breakdown arrangements to cover extensions, so a later extension needs only a revised order rather than new arrangements. Marine projects especially need this approach.

How are communications kept running when a base generator is serviced?

With a small online UPS on the communications circuit, its battery sized for the longest planned break with margin. It is tested by switching off its input during a planned check, and checked for generator compatibility so it does not drain its battery needlessly. Results are logged each time.

What spares should a remote base keep for its generator?

Oil, fuel and air filters, a drive belt, control panel fuses and a spare starting battery. These cover the faults most likely to stop a set at a remote base, so a minor problem can be fixed quickly instead of waiting for parts to arrive.

How long can a generator be hired?

As long as the project needs. Here an initial three-month hire was extended by two months; hires of months or years need maintenance, fuel and breakdown cover written into the agreement. Every rental set is load-bank tested before dispatch, and service at 250 to 500 running hours is planned inside the hire.

What does an extended rental need that a short one does not?

Scheduled servicing inside the hire period, a plan for consumables and spares, and an agreed response to breakdowns, because the set becomes an operating asset rather than a short-term stopgap. A running log keeps the service dates, running hours and fuel use visible to both sides.

Engineering record reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Client name withheld under the confidentiality terms of the order. Source: client purchase order on file. Last reviewed: 20 October 2026.

Related: rental power · ports and marine power · temporary and bridging power projects · all verified projects