Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

125 kVA standby rental for a leading aluminium producer’s Bhubaneswar office, renewed for two more years

A 125 kVA acoustic DG set hired with an operator, site works and statutory clearances for an aluminium producer’s Bhubaneswar office from 2010.

In short. In May 2010 a leading Indian aluminium producer awarded Reddy Generators a contract to hire, install and run a 125 kVA acoustic diesel generator at its corporate office in Bhubaneswar. The scope covered the whole installation, from earthing, armoured cabling, busbar and changeover switch to statutory clearances, an operator on a 12-hour shift, and all maintenance. The initial 12-month contract, with a performance review at six months, was then renewed for a further two years.

ClientA leading Indian aluminium producer (name withheld)
SiteCorporate office, Baramunda, Bhubaneswar, Odisha
AwardLetter of award dated 5 May 2010
Duration12 months, then renewed for 2 more years
Equipment1 × 125 kVA Cummins acoustic DG set with control panel and canopy
OperationOperator on a 12-hour shift; periodic, scheduled and breakdown maintenance included
Site worksEarth pit and earthing strip, 90 m of 3½-core armoured aluminium cable, 200 A busbar, 200 A changeover switch, base, drainage and protection shed
ClearancesElectrical Inspector and Pollution Control Board clearances obtained by Reddy Generators

The requirement

A busy corporate office cannot stop for power cuts: computers, servers, lighting, lifts and air conditioning all depend on it. The client chose to hire rather than buy, and wanted one contractor to deliver a complete, legally cleared installation and keep it running, with nothing left for office staff to manage.

A complete installation, not just a generator

The contract treated the generator as one part of a working system. Around the set, the scope included its earth pit and earthing strip, 90 metres of armoured aluminium cable to the building, a 200 A busbar and a 200 A changeover switch, a compacted and levelled base with drainage, and a protection shed. Reddy Generators also took responsibility for obtaining clearance from the Electrical Inspector and the Pollution Control Board, so the installation was legal from day one.

Running it for three years

An operator ran the set on a 12-hour shift. Running hours and diesel were recorded in a log book signed by the client’s representative, and every monthly bill was reconciled against it. All periodic, scheduled and breakdown maintenance stayed with Reddy Generators. The contract built in a performance review after six months; at the end of the first year the client renewed it for two more years.

Why a complete installation matters more than the generator

A generator is only useful if it is connected safely, legally and reliably to the building it serves. In a corporate office the installation includes everything between the set and the loads: earthing, cabling, a busbar, a changeover switch, a base with drainage and a shed to protect the set. When all of this is delivered by one contractor, there is no gap where responsibilities overlap or fall between parties.

ElementPurposeWhat to check
Earth pit and earthing stripSafe fault path and protection operationEarth resistance at installation and in the dry season
Armoured cableCarries generator current to the buildingCurrent rating, voltage drop and route protection
Busbar and changeover switchConnect the set without paralleling it with mainsRating and interlocking
Base, drainage and shedStable, dry and protected locationLevel base, clear drains, ventilation

Worked example: voltage drop on a 90-metre feeder (illustrative)

A 125 kVA set at 415 V carries about 174 A at full load. Suppose the 90-metre route uses an aluminium cable with a resistance of about 0.32 ohms per kilometre at working temperature and a reactance of about 0.075 ohms per kilometre. At 0.8 power factor, the drop is 1.732 times 174 amperes times 0.09 kilometres times the sum of 0.32 times 0.8 and 0.075 times 0.6, which comes to about 8.2 volts, roughly 2%. That is acceptable for the feeder, leaving room within the overall allowance for the building wiring. The real cable size is chosen from the actual current, route and installation method.

Statutory clearances for a generator installation

A diesel generator installation needs electrical safety approval and, depending on its size and location, consent from the pollution control authority. The steps typically include submitting drawings and equipment details, an inspection of the installation and its earthing, and issue of the approval before regular use. On this contract the rental supplier obtained the clearances, with fees paid by the owner. Agreeing who does this, and when, before mobilisation prevents delays in putting the set into service.

The operator on a 12-hour shift

With an operator present, small issues are seen and dealt with early, and the log book becomes the basis for monthly billing and fuel reconciliation.

What a six-month performance review should cover

AreaQuestions to ask
AvailabilityDid the set start and take load every time it was needed?
MaintenanceWere services done on time, and were faults dealt with properly?
FuelDoes fuel used match hours and load?
RecordsAre logs complete and signed?
ChangesHas the office load or use changed?

A review built on records rather than impressions gives both sides a clear basis for renewal.

Worked example: reconciling diesel (illustrative)

Suppose the log shows 300 running hours in a month at an average load of about 60 kW. At roughly 0.28 litres per kWh, the expected fuel is about 5000 litres. If the log shows 5100 litres used, the difference is within normal variation. If it shows 6000 litres, the extra thousand litres is investigated, starting with leaks, meter readings and the accuracy of the hours and load recorded.

Cyclones and heavy rain on the east coast

Odisha faces cyclones and very heavy rain. Before the cyclone season, the protection shed is checked for secure fixings, drainage around the base is cleared, cable joints are sealed and extra fuel is arranged where safe and permitted, because outages and road closures often follow a storm. After a storm, the set and its installation are inspected before it is relied on again.

Lessons for corporate offices

For corporate offices, the value of a long-term rental lies in a complete, legally cleared installation and a service that leaves nothing for office staff to manage. Sound earthing and cabling, a proper changeover, an operator who keeps clear records, and regular reviews based on those records are what make such an arrangement run smoothly for years.

Lifts and air conditioning on a 125 kVA set

A corporate office load includes lifts and central or split air conditioning, both of which start motors. A lift motor start, or several cooling units restarting together after a transfer, can cause a sharp voltage dip on a set of this size. Restoring lifts one at a time, staggering cooling restarts and keeping the running load comfortably inside the 100 kW the set gives at 0.8 power factor avoid trips and nuisance alarms. Where a lift has a regenerative drive, the set must be able to absorb the small amount of power returned during braking, which is checked with the lift supplier.

Ventilation inside a protection shed

A shed protects the set from rain and sun, but it can trap heat. The shed is designed so that radiator air leaves freely, fresh air enters low on the opposite side, and the exhaust is carried clear of the roof. On hot afternoons, the air reaching the radiator is checked; if it is much warmer than outside air, openings are enlarged or the discharge is ducted to stop hot air recirculating.

Operating the changeover safely

The changeover switch decides whether the office runs on mains or generator, and must never connect both at once. Its operation is part of the operator routine: confirm mains has failed, start the set and let it stabilise, then change over; on mains return, confirm mains is steady before changing back, then run the set off load to cool. Clear labels on the switch positions and a written procedure beside it prevent mistakes during night shifts.

At each renewal

A renewal is a good moment to recheck the earthing, the cable and its terminations, the changeover switch and the shed, and to confirm that the clearances remain valid. Recording these checks with the renewal keeps the installation documented for the next term.

Fire safety at an office generator

A diesel set beside an office brings fuel, hot surfaces and electrical equipment together. Suitable extinguishers for oil and electrical fires are kept at the shed, the area is kept free of stored materials, refuelling is done with the set stopped where possible and spills are cleaned at once. The operator knows where the emergency stop is and how to isolate the supply, and the office fire plan includes the generator location.

The same checks are repeated after any cyclone or flood before the set is returned to service.

Outcome and limits

The hire ran for about three years in total, with the client choosing to renew after the first year. A renewal is the clearest evidence of satisfactory service that a rental contract can give. This record is based on the client’s letter of award and the renewal; operating logs are not published.

Questions engineers ask about this project

What does a complete rental generator installation include?

An earth pit and earthing strip, armoured cable to the building, a busbar and changeover switch that prevents paralleling with mains, a level base with drainage and a protection shed. Delivering all of it under one contractor leaves no gaps between responsibilities. Each element is checked again at every renewal.

How is voltage drop checked on a long generator feeder?

Use current, length, cable resistance and reactance at the load power factor. In the illustrative 90-metre case, 174 A in an aluminium cable gives about 8.2 volts, roughly 2%, leaving room for building wiring within the overall allowance. The actual cable size is chosen from the real current, route and installation method.

What should a six-month generator performance review cover?

Availability, whether the set started and took load every time; maintenance, whether services and faults were handled on time; fuel, whether use matched hours and load; records, whether logs were complete and signed; and any change in office load or use. Records, not impressions, guide the decision.

How is rented generator diesel use reconciled?

Compare logged fuel with the expected figure from hours, load and typical litres per kWh. In the illustrative month, 300 hours at about 60 kW suggests about 5000 litres; a log far above that is investigated for leaks, meter errors or recording mistakes. Small differences are normal variation.

What site work does a long-term rental generator need?

More than the set itself: an earth pit, armoured cable to the building, a busbar and changeover switch, a level base, drainage and a protection shed. Here all of it was built as part of the hire. Each item is tested before the set takes load.

Who obtains statutory clearance for a rental DG set?

On this contract the rental supplier took responsibility for obtaining clearance from the Electrical Inspector and the Pollution Control Board, with the fees paid by the owner. Agree who does this before mobilisation. Write it into the contract, with the documents each side must provide and the timeline.

How is diesel use checked on a rented generator?

Through a log book of running hours and fuel received, signed by the owner’s representative and submitted with each monthly bill, so fuel is reconciled against actual use. Litres per running hour at a typical load make an easy check: a sudden change points to a leak, a meter error, a change in load or a fault that needs attention.

Engineering record reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Client name withheld. Source: client letter of award dated 5 May 2010 and subsequent renewal. Last reviewed: 20 October 2026.