In short. In July 2014 one of India’s leading infrastructure contractors, building an onshore oil and gas terminal for a major Indian energy company at Gadimoga in East Godavari district, hired a 125 kVA silent diesel generator with operator from Reddy Generators, for a minimum of six months on a 10-hour, 26-day monthly pattern.
| Client | A leading Indian infrastructure contractor (name withheld) |
|---|---|
| Site | Onshore terminal project, Gadimoga, Tallarevu mandal, East Godavari district, Andhra Pradesh |
| Work order | 4 July 2014 |
| Equipment | 1 × 125 kVA silent diesel generator |
| Operation | With operator; about 10 hours a day, 26 days a month |
| Duration | Minimum six months (July 2014 to January 2015) |
| Scope | Hire, mobilisation and demobilisation |
The requirement
Construction of an onshore terminal on the Godavari coast needs reliable temporary power for site offices, workshops and tools well before permanent supply is available. The contractor needed a silent set with an operator, mobilised to a remote coastal site and kept running for the construction period.
What a terminal construction site asks of temporary power
Before permanent supply reaches a new terminal, the construction team depends entirely on temporary generators. The loads are a mix of steady and harsh: site offices with computers and air conditioning, stores and workshops with power tools, yard and security lighting, small pumps for dewatering, and sometimes welding sets. Several crews may switch equipment on and off through the day, so the load changes often and sometimes sharply.
| Load group (illustrative) | Character | Point to manage |
|---|---|---|
| Site offices and stores | Steady through working hours | Restart of air conditioning after any stop |
| Workshop tools | Intermittent, short motor starts | Spread across phases |
| Welding sets | Fluctuating, with short bursts | Voltage dips for other users |
| Dewatering pumps | Motor starts, sometimes long running | Starting method and cable length |
| Lighting | Steady at night | Separate circuits for safety lighting |
Worked example: loading a 125 kVA set on a construction site (illustrative)
A 125 kVA set gives 100 kW at 0.8 power factor. A typical daytime mix on a site of this kind might be 25 kW of offices and stores, 20 kW of tools in use at any moment, a 15 kW pump and about 10 kW of other loads, roughly 70 kW in total. That leaves headroom for the pump start and for a welding set drawing short bursts. Single-phase tools and lighting are spread across the three phases, because each phase can carry only a third of the rating. If welding is heavy, a separate small set for welding keeps its fluctuations away from office computers.
Planning service inside a 260-hour month
A hire priced on about 10 hours a day for 26 days a month means roughly 260 running hours each month. Over a six-month hire that is about 1560 hours, so the set needs several services within the hire, not one at the end.
| Item | Approximate frequency over a six-month hire (illustrative) |
|---|---|
| Oil and filter service at 250 to 500 hours | About every one to two months, so three to six services |
| Air filter check and cleaning | Weekly on a dusty site, by indicator |
| Radiator cleaning | As inspection shows, more often in dry, windy weeks |
| Coolant level and condition | Daily check by the operator |
| Fuel water drain | Weekly |
Planning these visits at the start, and recording hours daily, means the set is never overdue while it is working hardest.
The operator routine on a working site
With an operator supplied with the set, daily care is in the hands of someone who knows the machine. A sound routine covers the following each working day:
- Before start: oil and coolant levels, fuel level, visible leaks, belts and air filter indicator.
- After start: oil pressure, voltage, frequency and charging.
- During the shift: load, temperatures and any alarms, logged at set times.
- At shutdown: hours, fuel used and any defect, entered in the log.
The log becomes the basis for service planning and for reconciling fuel with the contractor.
Working in coastal air
A site near the Godavari coast exposes equipment to salt-laden, humid air, which corrodes terminals, panel components and canopy fixings and allows moisture into alternator windings. Acoustic enclosures help, but they also need care: door seals kept intact, drain holes clear, and anti-condensation heaters working when the set is idle overnight. At each service, terminals are cleaned and protected, insulation resistance of the alternator is checked, and any corrosion on the canopy is treated before it spreads.
Fuel logistics at a remote site
At about 260 hours a month, even a modest set uses a substantial quantity of diesel. On a remote coastal site, deliveries can be delayed by weather or road conditions, so the base tank is kept well topped up and a reorder level is set that covers the longest likely delay. Clean filling practice matters on a dusty construction site: caps closed, funnels clean and fuel filtered where possible, because contaminated fuel is a common cause of breakdowns on temporary sets.
Safety on a hydrocarbon project site
Oil and gas sites run strict safety systems, and temporary power must fit within them. The set is positioned away from areas classified for flammable atmospheres, as directed by the site safety team. It stands on a level base with spill containment for fuel and oil, its earthing is tested before first use, cables are protected where vehicles cross them, and any hot work near the set is done under the site permit system. Fire extinguishers suited to oil and electrical fires are kept at the set, and the operator takes part in the site safety induction like any other worker.
Mobilisation and demobilisation
- Confirm access for the delivery vehicle and lifting equipment.
- Prepare the base, spill containment and earthing before arrival.
- Deliver a set that has been load-bank tested before dispatch.
- Connect, test the earthing and run on load before handing over.
- At the end of the hire, prove the permanent supply, disconnect safely, agree the fuel left in the tank and leave the area clean.
Lessons for similar construction sites
Temporary power on construction sites succeeds when it is treated as a small power system rather than a box with a socket. Spreading single-phase loads, keeping welding away from sensitive equipment, planning services inside the hire, protecting the set from coastal corrosion and keeping fuel clean prevent most of the problems that interrupt site work. A silent set with an operator, running on a clear daily routine, gives the site team one thing less to worry about while the terminal itself is being built.
Earthing and protection for temporary distribution
Temporary distribution on a construction site carries more risk than a finished building, because cables move, tools are handled by many people and ground conditions change with the weather. The generator neutral and frame are earthed and tested before first use, outgoing circuits feeding tools and portable equipment are protected by residual current devices, and distribution boards are robust, weatherproof and locked. Earth continuity is checked again whenever the set or boards are moved, and damaged cables are replaced rather than repaired with tape.
What a contractor should state when hiring a site generator
| Item | Why it matters |
|---|---|
| Loads, including the largest motor and any welding | Sets the rating and checks the starting duty |
| Running pattern, such as hours per day and days per month | Sets the service plan inside the hire |
| Duration, with likely extensions | Decides how servicing and spares are planned |
| Operator required or not | Decides who carries out daily checks |
| Site conditions such as dust, salt air or flooding risk | Decides enclosure care and inspection frequency |
| Site safety rules and inductions | Ensures the set and operator fit the site system |
Planning for a breakdown on a remote site
No machine is immune to faults, and on a remote site the cost of a stoppage is high. Good planning reduces both the chance and the impact: consumable spares such as filters and belts are kept with the set, the operator is trained to recognise early warning signs, the daily log shows trends before they become failures, and the arrangements for breakdown attendance are agreed in the hire terms before work starts. Where the site cannot accept any interruption, a second set or a prepared connection point for a replacement is considered.
Noise in a crowded work area
Terminal construction brings many crews, offices and accommodation close together. A silent set reduces noise at source, but placement still matters: away from office windows and rest areas, with the exhaust pointing away from people and the radiator discharge clear of walls that would reflect sound. Keeping enclosure doors closed while running preserves the acoustic performance the set was chosen for.
Worked example: fuel for a month of site work (illustrative)
At an average load of about 70 kW and around 0.28 litres per kWh, the set uses roughly 20 litres an hour. Over a 10-hour day that is about 200 litres, and over 26 working days about 5200 litres a month. Knowing this figure lets the contractor plan deliveries, size any additional storage and check the operator log for unexplained differences. If a month shows noticeably more fuel than the hours and load justify, the cause is looked for at once: a leak, a fault, or fuel leaving the site.
Handover between shifts and crews
Where site work runs beyond one shift, a short written handover at the set records hours, fuel, alarms and anything unusual. The next operator then starts from facts rather than memory, and small problems are not lost between shifts.
Outcome and limits
The set was hired under the work order for the minimum six-month term. This record is based on the client’s work order; operating logs are not published.
Questions engineers ask about this project
How should a 125 kVA set be loaded on a construction site?
Keep the busy-period load well inside the 100 kW the set gives. In the illustrative site, about 70 kW of offices, tools, a pump and other loads leaves headroom for motor starts and welding bursts, with single-phase loads spread across the three phases. Heavy welding may justify its own set.
How often does a site generator need servicing on a 10-hour, 26-day pattern?
About 260 running hours a month means an oil and filter service roughly every one to two months, so several services within a six-month hire, plus weekly air filter checks on dusty sites, regular radiator cleaning and weekly fuel water draining. The operator log tracks hours so no service is missed.
What should a generator operator check each day on site?
Before start, oil, coolant and fuel levels, leaks, belts and the air filter indicator; after start, oil pressure, voltage, frequency and charging; during the shift, load, temperatures and alarms; and at shutdown, hours, fuel used and any defect entered in the log. The log supports service planning and fuel reconciliation.
How is a generator protected in coastal air?
Salt and humidity corrode terminals and let moisture into windings. Keep enclosure seals intact and drains clear, run anti-condensation heaters when idle, clean and protect terminals at each service, check alternator insulation resistance and treat canopy corrosion before it spreads. Inspections are more frequent during the monsoon months on exposed sites.
Why are silent generators used at oil and gas terminals?
Terminals have many crews and offices working close together, and acoustic enclosures cut noise and protect the set from dust, salt air and rain. In coastal air, corrosion protection matters, so terminals, panels and the canopy are inspected at each visit and anti-condensation heaters keep moisture out of the alternator and controls.
What does a 26-day, 10-hour rental mean?
The hire was priced on the set running about 10 hours a day for 26 days a month, which matches a construction work pattern and sets the service interval inside the hire. That is about 260 running hours a month, so a service at 250 to 500 hours falls roughly every one to two months.
Engineering record reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Client name withheld. Source: client work order dated 4 July 2014. Last reviewed: 20 October 2026.
Related: oil and gas power · construction-site power · all verified projects