In short. In July 2017 a fabrication contractor working on the Ramagundam Fertilizers & Chemicals Limited (RFCL) plant in Telangana hired three 250 kVA soundproof diesel generators from Reddy Generators, each with an operator, for a 12-hour working day and a minimum hire of six months per set.
| Client | A tank and pressure-vessel fabrication contractor (name withheld) |
|---|---|
| Site | Ramagundam Fertilizers & Chemicals Limited (RFCL) project site, Ramagundam, Telangana |
| Order | 18 July 2017 |
| Equipment | 3 × 250 kVA soundproof diesel generator sets |
| Operation | One operator per set, 12 hours per day |
| Duration | Minimum 6 months per set |
The requirement
The Ramagundam fertiliser plant was being rebuilt as one of the country’s major fertiliser projects. Fabrication contractors on such a site need heavy temporary power for welding, cutting, lifting and testing long before the plant’s own supply is energised. The contractor needed several large sets on site quickly, with operators, for a hire of at least six months.
Three sets, one supplier
Instead of one very large generator, the site took three 250 kVA soundproof sets, each run by its own operator on a 12-hour day. Splitting capacity this way lets each set serve its own work area, keeps engines loaded efficiently, and, with suitable separation of work areas and feeders, means a fault on one set need not stop every work area; the affected area still needs a recovery plan. Soundproof enclosures kept noise down for the crews working around them.
What a fabrication contractor needs from temporary power
Tank and pressure-vessel fabrication is one of the heaviest users of temporary power on a plant construction site. Welding runs for most of the day, plates are cut and ground, heavy sections are lifted, finished vessels are pressure tested, and welds may need heat treatment. These loads are large, often fluctuating, and spread across several work areas, which is why their power supply is planned like a small industrial system.
| Load (illustrative) | Character on a generator | Point to manage |
|---|---|---|
| Welding machines | Large, fluctuating, often all day | Voltage dips and distortion for other users |
| Weld heat treatment heaters | Steady resistive load for hours | Long periods near full load |
| Cranes and hoists | Short heavy motor starts | Starting steps on a loaded set |
| Pressure test pumps | Motor start, then steady running | Starting method and cable length |
| Grinders, cutters and lighting | Many small single-phase loads | Balance across the phases |
Worked example: dividing load across three 250 kVA sets (illustrative)
Each 250 kVA set gives 200 kW at 0.8 power factor. Suppose the site has a main welding bay drawing up to about 140 kW, a heat treatment and testing area of about 120 kW, and a lifting and assembly area of about 100 kW, with lighting spread across them. Giving each area its own set keeps every engine between about half and three-quarters loaded, where it runs efficiently and cleanly.
A single set of around 500 kVA could in theory carry the combined load, but it would run lightly loaded at night and during breaks, and a fault would stop every area at once. With three sets, a fault affects one area, and that area can be supported by moving priority loads to a neighbouring set if the feeders allow it.
Welding loads on generators
Modern inverter welders draw current in short pulses that distort the generator waveform, while older transformer welders draw large, poorly balanced currents. On a dedicated set, these effects matter little. Where welding shares a set with other loads, voltage dips during heavy welding can disturb control equipment and lighting. Keeping welding on its own set or feeder, spreading single-phase welders across the three phases, and choosing a set with a robust voltage regulator keep the supply steady for everyone else.
Service planning for a 12-hour day
A 12-hour working day across most of the month gives roughly 300 to 360 running hours per set each month. With oil and filters at 250 to 500 hours, each set needs a service roughly every three to six weeks, so across three sets and a six-month hire there are many service visits to plan.
| Item (illustrative) | Per set over six months | Across three sets |
|---|---|---|
| Running hours | About 1800 to 2100 | About 5400 to 6300 |
| Oil and filter services | About four to eight | About twelve to twenty-four |
| Air filter checks | Weekly on a dusty site | Weekly for each set |
Staggering the services so that only one set is down at a time, and only during a break in the work, keeps two areas working while the third is serviced.
Three operators, one record
With one operator per set, each machine is looked after by someone who knows it, but the site still needs a single view. A shared daily log covering all three sets, with hours, fuel, load, alarms and defects, lets the site supervisor see the whole power picture at a glance and plan fuel and services together. Operators also agree how they will help each other if one set has a fault, so priority loads are moved quickly and safely.
Worked example: fuel for three sets (illustrative)
If each set averages about 120 kW over a 12-hour day at roughly 0.28 litres per kWh, each uses about 34 litres an hour, around 400 litres a day. The three sets together use about 1200 litres a working day, and over 26 working days about 31,000 litres a month. Fuel at that rate needs planned deliveries, secure storage, and a daily reconciliation of fuel issued against hours and load for each set.
Safety on a large plant construction site
A fertiliser plant under construction is a busy, hazardous place. Each set stands on a level base with containment for fuel and oil, away from areas where flammable materials are stored or classified hazardous zones identified by the site safety team. Earthing is tested before first use and after any move. Cables run on routes protected from vehicles and cranes, and the steel structures being built are bonded so that no dangerous voltage can appear between them and the welding return. Hot work near the sets follows the site permit system, and operators attend the site safety induction.
A recovery plan for a set fault
- List the priority loads in each area that must keep running.
- Identify which neighbouring set could carry them and through which feeder.
- Check that the neighbouring set has enough spare capacity at the busiest time.
- Agree who switches the loads and how isolation is confirmed.
- Record the plan in the operators log and rehearse it once.
Lessons for similar fabrication sites
Fabrication sites reward a split supply. Several sets, each matched to an area, keep engines well loaded, limit the effect of a fault and keep welding disturbances away from sensitive loads. Planning services around the working day, keeping one log for all sets, managing fuel at the scale the site consumes it, and fitting the generators into the site safety system are what keep heavy fabrication moving through a long construction period.
Cable runs on a large site
Plant sites are large, and work areas may be a long way from where a set can be placed. Long cables bring voltage drop, especially during motor starts and heavy welding. Each feeder is sized for its current and length, with the drop at full load checked against the allowance for the equipment it serves. Where a run would be very long, moving the set closer to its work area is often cheaper and safer than a heavier cable. Cable routes are marked, protected at crossings and kept clear of crane paths and excavations.
Heat treatment on generator supply
Weld heat treatment uses resistive heating elements controlled to follow a temperature programme for several hours. The load is steady but large, and an interruption part way through can spoil the treatment and require it to be repeated. Heat treatment is therefore given a set that is not shared with fluctuating loads, its fuel is checked before the cycle starts, and the operator stays with the set for the duration of the programme.
Noise among working crews
Hundreds of workers on a plant site spend long days close to equipment. Soundproof sets reduce noise at source, and placing them away from site offices, rest shelters and areas where crews communicate by voice reduces it further. Enclosure doors are kept closed while the sets run, and the exhaust is directed away from people.
Working through the monsoon
A six-month hire from July runs straight through the monsoon in Telangana. Bases are raised above standing water, cable joints are sealed, fuel caps are kept closed against rain, and alternator insulation is checked after heavy rain before the sets are loaded again.
Handing the sets back
When an area no longer needs temporary power, its set is released rather than kept idle until the end of the whole hire. Before removal, the area supply is confirmed from its permanent source or another set, final hours and fuel are recorded, cables are recovered and the base area is left clean. Releasing sets area by area keeps the hire matched to the work actually being done.
A short closing note for each released set, signed by the area supervisor, keeps the hire record complete.
Outcome and limits
All three sets were hired under the order with operators for the construction period. This record is based on the client’s purchase order; operating logs are not published.
Questions engineers ask about this project
How should load be divided between several site generators?
Give each work area its own set where possible. In the illustrative fabrication site, welding, heat treatment and testing, and lifting areas each get a 250 kVA set, keeping every engine about half to three-quarters loaded and limiting the effect of any single fault to one area.
How often do generators running 12 hours a day need servicing?
At roughly 300 to 360 hours a month, each set needs an oil and filter service about every three to six weeks. Across three sets and a six-month hire that means many visits, staggered so only one set is down at a time, during a break in the work.
Why should weld heat treatment have its own generator?
Heat treatment follows a temperature programme for several hours, and an interruption can spoil it and force a repeat. A set not shared with fluctuating welding loads, fuel checked before the cycle and an operator present throughout protect the treatment from supply disturbances. Its log records the full cycle.
How much fuel do three 250 kVA site generators use?
In the illustrative case, each set averaging about 120 kW for 12 hours at roughly 0.28 litres per kWh uses about 400 litres a day, so the three use about 1200 litres a working day, around 31,000 litres over 26 working days, needing planned deliveries and daily reconciliation.
Why use three 250 kVA sets instead of one large generator?
Three sets spread the load across the site, keep each engine at a healthy loading and mean that one breakdown need not stop every work area, provided the feeders are separated and the affected area has a recovery plan. Sets can also be added or removed as construction needs change.
What does an operated generator hire include?
Here each set came with its own operator for a 12-hour working day, so starting, monitoring, refuelling and daily checks were handled by people who knew the equipment. Daily logs recorded hours, fuel, readings and any alarms, so each set was watched closely and service was planned before it fell due.
Why choose soundproof sets on an industrial site?
Large plant sites have many crews working close together. Acoustic enclosures cut noise for workers and neighbouring areas and protect the set from dust and weather. They also make it easier to meet site noise limits, and they keep rain off the alternator and controls, while the canopy air path still lets the set cool properly at full load.