In short. A refinery or process plant rarely asks a generator to keep production running. It asks the generator to bring the plant to a safe, recoverable state: lubrication and seal oil pumps, instrument air, flare and firewater systems, control rooms and emergency lighting. The emergency generator is sized for that defined shutdown load, starts within seconds, feeds a dedicated emergency switchboard, and is tested against the written shutdown sequence rather than the plant’s total demand.
Full production or safe shutdown
The first decision in any process plant is the objective of backup power. A refinery drawing 40 MW from the grid and its captive power plant will not carry production on diesel generators, and it does not need to. What it needs is to protect rotating equipment, prevent product loss, keep the flare and fire systems available and preserve the operator’s view of the plant while the process is brought down in a controlled way.
Wellsite and gathering station power is a different problem, covered on the upstream oil and gas page. Smaller process plants, such as a bulk drug unit in the Hyderabad pharmaceutical belt or a speciality chemical plant near Visakhapatnam, may define a wider objective that keeps a reactor cooling train or a critical batch running, but the principle is the same: the process owner states the operating condition the generator must support, and the generator is sized for it. Sizing for the full plant load produces a set that is too large, lightly loaded during real events and never tested properly.
| Load group | Purpose during an outage | Typical supply | Interruption tolerated |
|---|---|---|---|
| DCS, ESD, safety instrumented systems | Keep the plant visible and shutdown logic alive | UPS with generator behind it | None |
| Lube oil, seal oil, barring gear | Protect motors and turbines on coast-down | DC or UPS for emergency pumps, generator for AC pumps | Seconds |
| Instrument compressed-air plant | Hold control valves in a controllable state | Emergency generator | Until receiver pressure decays |
| Firewater jockey pump, flare pilots, gas detection | Fire and emergency readiness | Emergency generator, often with diesel-driven main pumps | Seconds |
| Emergency lighting, communication, control room HVAC | Safe egress and operator working conditions | Emergency generator | 10 to 15 seconds |
| Process heating, main pumps, utilities | Production | Not supported | Shut down |
Start time and the emergency switchboard
Process plants normally define the emergency generator as the source for a dedicated emergency switchboard, fed in normal operation from the main plant board and transferred to the generator on loss of supply. The transfer time is driven by the most sensitive emergency load, typically the lube oil pumps on large machines, and emergency sets are specified to accept load within 10 to 15 seconds of the supply failing.
That requirement shapes the set: jacket water heaters so the engine starts warm, duplicated starting batteries with chargers, a controller that attempts several start cycles, and a weekly automatic test run. The AMF panel page describes the start and transfer logic, and the emergency and standby architecture guide covers how the emergency board is separated from the normal distribution so that a fault on the normal side cannot take the emergency supply with it.
Emergency set kW = Σ (connected emergency loads × demand factor) + largest motor starting allowance
Here the demand factor reflects which emergency loads genuinely run together during a shutdown, and the starting allowance is the extra capacity needed to start the largest emergency motor, usually the instrument compressed-air plant or a firewater jockey pump, without an unacceptable voltage dip. For an emergency board with 420 kW of connected load, a demand factor of 0.7 and a 55 kW motor started direct-on-line, the set lands around 500 kVA at 0.8 power factor (illustrative), confirmed against the alternator’s motor-starting data. The generator sizing guide explains the method in full.
Hazardous areas and plant integration
A refinery is divided into classified zones under IS/IEC 60079-10, and the emergency generator belongs outside them, usually in or beside the substation that houses the emergency switchboard. Where the only available location is close to process units, the project will specify spark arrestors, air intake shut-off valves and gas detection interlocked to the generator, and the installation will be reviewed by the plant’s electrical safety authority and, for petroleum installations, under OISD practice.
The generator also has to fit the plant’s protection and earthing philosophy. Many refineries use resistance-earthed systems at 6.6 kV or 11 kV and solidly earthed systems at 415 V; the generator’s neutral earthing must match the system it feeds so that earth-fault protection and the existing relay settings remain valid. The earthing and neutral architecture page covers the options.
UPS, DC systems and restart sequencing
The control system and safety instrumented systems sit on UPS and station battery supplies, which must bridge the generator start and continue through the whole shutdown if the generator fails. UPS battery autonomy in process plants is therefore specified in tens of minutes to hours, not the ten minutes common in commercial buildings, and the generator must be able to carry the UPS rectifier load, which is nonlinear and presents a step when the batteries begin recharging.
Restoration is as important as the outage. When grid supply returns, loads are brought back in a documented order: control power and lighting first, then lubrication and cooling, then utilities, and only then process equipment under the process team’s authority. The restart sequencing guide explains how to keep a large block load from tripping the generator or the restored supply.
Testing against the shutdown scenario
An emergency generator that has only ever been run on no-load test is not a proven system. Process plants should test the full sequence at acceptance and at planned intervals: fail the normal supply to the emergency board, record the start and transfer time, confirm each emergency load picks up in sequence, run under real load long enough to reach stable temperature, and confirm the return transfer.
Between integrated tests, a monthly load run on a resistive load bank at 50 to 70% of rating prevents wet stacking in a set that otherwise idles. The load bank testing page describes the procedure and the records to keep for the plant’s safety audit.
What an emergency generator carries in a refinery (illustrative)
A refinery’s emergency generator does not keep production running. It supports a safe, controlled shutdown and keeps the plant safe until normal power returns.
| Load | Purpose |
|---|---|
| UPS and DC system chargers | Keep control, safety instrumented systems and communications alive |
| Emergency and escape lighting | Safe movement of people |
| Fire water jockey pumps and selected fire systems | Fire protection readiness |
| Instrument air supply | Valves move to and hold safe positions |
| Critical cooling and lube oil pumps | Protect rotating machinery during run-down |
| Control room HVAC and pressurisation | Keep the control room habitable and safe |
These loads are defined by the plant’s shutdown philosophy. The generator is sized for them and their start sequence, not for the process load.
The emergency switchboard
The emergency switchboard is fed normally from the plant supply and by the emergency generator when that fails. Its design separates emergency loads from the rest of the plant, so a fault elsewhere cannot take the emergency supply down. The generator starts automatically on loss of supply, and the switchboard transfers the emergency loads within the time the shutdown philosophy requires.
Recording the shutdown test
Testing proves the scenario, not just the engine: loss of supply simulated, generator start and transfer timed, each emergency load confirmed running, and the run continued long enough to show the set holds temperature and voltage. On our standard, oil and filters are changed every 250 to 500 running hours or six months, whichever comes first, and coolant is replaced every year, with every test and service recorded with the plant’s safety documentation.
Location and hazardous areas
The emergency generator sits in a safe area outside classified zones, with its air intake drawing from a location where flammable gas cannot reach it. Its fuel supply is independent of the process plant, and its room is protected so that a process fire does not also destroy the emergency supply meant to manage it.
Fuel for the emergency generator is stored in a protected tank sized for the autonomy the shutdown philosophy requires, sampled regularly and kept separate from process fuels.
Common mistakes
- Sizing the emergency generator for the whole plant because the load list was never classified. The set is three times too large, runs lightly loaded during real events and is never properly tested.
- Feeding the emergency board through the same switchgear section as the normal supply. A busbar fault on the normal side removes the emergency supply at the moment it is needed.
- Specifying UPS autonomy at ten minutes as in an office building. The batteries are flat before the shutdown is complete if the generator fails to start.
- Changing the generator neutral earthing to suit the set rather than the plant system. Earth-fault relays stop coordinating and a fault clears by tripping the whole emergency board.
What to send us
Send the emergency load list with the shutdown objective agreed by the process owner, the required transfer time for the most sensitive load, and the single-line diagram showing the emergency switchboard and its normal feed. Include the area classification around the proposed generator location, the plant’s neutral earthing arrangement and voltage levels, and the UPS and DC system ratings the generator must support. Send your refinery or process plant requirement.
Questions engineers ask
What does a refinery emergency generator carry?
The loads defined by the shutdown philosophy: UPS and DC chargers for control and safety systems, emergency lighting, fire water jockey pumps and selected fire systems, instrument air, critical cooling and lube oil pumps for machinery run-down, and control room HVAC and pressurisation. It supports a safe shutdown rather than production.
How is a refinery emergency generator tested?
Against the shutdown scenario: loss of supply simulated, generator start and transfer timed, each emergency load confirmed running, and the run continued long enough to show the set holds temperature and voltage. Every test and service is recorded with the safety documentation of the plant.
How fast must a refinery emergency generator start?
Most process plants specify that the emergency generator accepts load within 10 to 15 seconds of supply failure, driven by lubrication and firewater systems. Loads that cannot wait even that long, such as control systems and emergency lube oil pumps, are carried by UPS or DC systems during the gap.
Should the emergency generator carry production load?
Normally no. The emergency generator is sized and arranged for the loads in the shutdown philosophy, which keep people and equipment safe. Adding production load risks overloading it at the moment it matters most, so any production backup is provided by separate generation if the plant needs it.
Can the emergency generator be installed near process units?
It should sit in a safe area outside classified zones, with its air intake where flammable gas cannot reach it, its own fuel supply and protection so that a process fire does not destroy the emergency supply meant to manage it. Location is fixed with the safety team.
How often should an emergency generator in a process plant be tested?
With regular runs on load and periodic tests of the full shutdown scenario, as the plant procedures require. Servicing follows our standard of oil and filters every 250 to 500 running hours or six months, whichever comes first, with coolant replaced every year, and all results recorded.
Does the generator need to match the plant earthing system?
Yes. The neutral earthing of the generator must suit the plant earthing philosophy, so that earth-fault protection works when the emergency switchboard is fed from the generator. The arrangement is designed with the protection engineer, tested at commissioning and checked again whenever the emergency switchboard or its feeders are modified.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.