Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Steel, Metals & Foundry Power

Emergency generator design for steel plants and foundries, covering furnace coil cooling, hydraulics, cranes, dust and heat derating and safe-state testing.

In short. In steel plants, rolling mills and foundries the melting and rolling loads are far too large to back up with diesel, so the generator’s job is safety and asset protection: furnace coil cooling water, tilt hydraulics, ladle cranes, fume extraction, lubrication and the controls that bring the process to a safe state. Size the set from that subset and its restart sequence, protect it from heat and dust, and test it with the real pumps.

What a generator can and cannot do in a melt shop

A medium-frequency induction furnace of a few tonnes draws one to several megawatts through a converter. An electric arc furnace draws tens of megawatts. Rolling mill main drives are measured in megawatts too. None of these are candidates for standby diesel; the plant stops when the DISCOM supply fails and restarts when it returns. What must not stop is the equipment that keeps people and plant safe while the heat is still there.

Molten metal sitting in a furnace whose coil cooling has stopped is a lined crucible with water channels next to it, and the failure modes include coil burnout, refractory damage and, in the worst case, a water and metal explosion. Reddy Generators approaches foundries and steel units in Telangana and Andhra Pradesh with that subset as the starting point and the method in generator sizing applied to it.

LoadWhy it is critical after an outageTolerable gapSupply
Induction furnace coil and converter cooling pumpsCoil and capacitor damage within minutes; explosion risk with molten chargeSeconds; many plants add a header tank or diesel-driven pump as a second pathGenerator, first step, with independent backup
Hydraulic power packs for furnace tiltAllows emergency pour or holding at a safe angleMinutesGenerator, early step
Ladle and charging cranes, selected hoistsMove hot metal and empty ladles safelyMinutesGenerator, after cooling
Fume extraction and baghouse fansVentilation of the melt shop while metal is hotMinutesGenerator, staged
Rolling mill lube oil, roll cooling, descaler controlsBearing damage, strip stuck in standsSeconds to minutesGenerator with DC or UPS backup for lube controls
Control rooms, PLCs, furnace instrumentationVisibility and control of the safe-state sequenceNoneUPS, fed from generator
Emergency lighting, gas detection, fire pumpsLife safetySecondsGenerator

Cooling water is the load that cannot wait

Induction furnace coils, converter cabinets and capacitor banks are water cooled, and the manufacturers specify how long cooling may be interrupted. That interval is short, and a well-designed melt shop does not rely on the diesel generator alone to meet it.

The usual arrangement is an elevated emergency header tank that gravity-feeds the coil for the generator start interval, or a diesel engine-driven pump that starts independently, with the electric pumps returning on the generator. The generator then carries those pumps as its first load step, which is easy to size and must simply work every time, a matter of maintenance and testing. See single-point-of-failure elimination for the logic of the second path.

Hydraulics and the emergency pour

If the safe-state procedure calls for pouring out a furnace during an extended outage, the tilt hydraulics, the ladle crane and the pouring area lighting must all be live together, in addition to cooling. That simultaneous requirement defines the generator’s second step, and the procedure should be written with the furnace supplier and rehearsed under generator power.

Heat, dust and derating

A generator room beside a melt shop or a rolling mill sees ambient temperatures well above the 40 °C that most ratings assume, together with conductive dust, scale and fume. Output must be derated for the real intake temperature, radiators foul quickly, and air filters need shorter intervals than a clean site.

The set should be placed to draw intake air from the coolest, cleanest side available, with ducted discharge away from the shop, and the room or canopy should keep a slight positive pressure with filtered air where the dust is severe. Containerised sets need the same thought, because a steel enclosure does not by itself provide filtration or adequate airflow. Painted enclosures near pickling lines or in coastal plants corrode faster and need a specification to match. See ambient temperature derating and generator room ventilation.

P_available = P_rated × (1 − d_T × (T_ambient − T_ref)) × (1 − d_alt × altitude)

P_rated is the nameplate output, d_T the manufacturer’s derate per degree above the reference temperature T_ref, and d_alt the derate per unit of altitude. A worked example (illustrative): a 500 kVA set with a derate of 1% per 5 °C above 40 °C, installed where the intake air reaches 50 °C, gives roughly 500 × (1 − 0.02), or about 490 kVA, before any dust-related loss of radiator performance; the exact factors must be taken from the engine and alternator data sheets, and radiator fouling can cost far more than the published derate.

Power quality, converters and the rest of the plant

Where a plant chooses to run smaller process loads on generator, the furnace converter and any thyristor drives must be checked as harmonic sources against the generator’s much higher source impedance, because distortion the utility transformer swallowed will appear on the generator bus. Power factor correction capacitors left connected to a lightly loaded generator can push it into leading power factor and unstable voltage, so capacitor banks should be interlocked to disconnect on transfer. Earthing is also plant-specific: the generator neutral arrangement must follow the existing plant earthing scheme and the furnace supplier’s requirements, not a generic diagram. See harmonics and THD and earthing and neutral.

Testing with the real loads

A load bank proves the engine. The safe-state sequence has to be proved with the actual cooling pumps, hydraulics and cranes under a simulated mains failure with the furnace cold, recording the time to restore cooling flow, the voltage dip on the crane start and the state of the UPS-fed controls. Where a plant relies on a single set for this duty, a rental set during overhauls is not optional; see rental power for shutdowns.

What the generator carries in a foundry (illustrative)

A foundry with a 1500 kW induction furnace does not put the furnace on the generator. It protects the systems that keep the furnace and the people around it safe while the melt is held or tapped.

LoadWhy it is protectedDemand
Furnace coil cooling water pumpsA coil without cooling can be damaged within minutes with molten metal inside45 kW
Cooling tower or heat exchanger fansKeep the cooling water within temperature30 kW
Hydraulic tilting systemAllows a controlled pour or tilt if the melt must be emptied22 kW
Fume extractionKeeps the melt shop safe to work in55 kW
Control room, lighting, cranes for emergency movesSafe operation during the outage60 kW
Total212 kW

That is about 265 kVA at 0.8 power factor. With motor starts and the heat of the melt shop, a 320 to 380 kVA set placed away from the furnace and its heat carries it comfortably, while the 1500 kW furnace waits for the DISCOM supply.

Cooling water comes first

The cooling pumps restart within seconds of the transfer, ahead of everything else. Many foundries also keep a gravity-fed emergency water tank or a battery-backed pump as a second line of protection, because the consequence of losing coil cooling with metal in the furnace is severe. The generator and the emergency water supply are tested together, so the plant knows how long each takes to act.

Placing the set away from heat and dust

Melt shops are hot and dusty. A generator placed near the furnace breathes hot, dirty air, derates and clogs its radiator. The set is placed in a separate, ventilated room or outside, with its air intake drawing cool air away from the shop and its exhaust directed clear of building openings. On our standard, oil and filters are changed every 250 to 500 running hours or six months, whichever comes first, coolant is replaced every year, and air filters and radiators are checked more often in foundry dust.

Converters and power quality

Induction furnace converters and rolling mill drives distort the supply heavily. Even though the furnace is not on the generator, other converter-fed loads on the standby bus can be, so the share of converter load is declared when the alternator is selected, and voltage distortion is measured during the commissioning test on the real loads.

Common mistakes

What to send us

Send the furnace or mill supplier’s cooling and safe-shutdown requirements, the list of safety and asset-protection loads with motor ratings and starting methods, the plant single-line diagram with the earthing arrangement, and the location and ambient conditions proposed for the generator. Photographs of the existing set and its air intake side help us judge derating and filtration. Send your application details and we will propose the load steps and the second cooling path with you.

Questions engineers ask

What should a foundry generator carry during an outage?

Not the furnace. It carries furnace coil cooling water pumps, cooling tower fans, the hydraulic tilting system, fume extraction, the control room, lighting and cranes for emergency moves. In the example on this page that is about 212 kW, roughly 265 kVA, so a 320 to 380 kVA set placed away from the furnace heat suits.

Where should a generator be placed in a melt shop?

In a separate ventilated room or outside, away from the furnace heat and dust, with its air intake drawing cool clean air and its exhaust directed clear of building openings. A set near the furnace breathes hot dirty air, derates and clogs its radiator just when it is needed most.

Can a diesel generator run an induction furnace?

Technically a very large set could, but it is rarely sensible. Induction furnaces draw heavily distorted current and very large power, so a generator plant for them would be huge and costly. The usual approach is to put coil cooling, tilting, fume extraction and controls on the generator and let the furnace wait for the grid.

How long can furnace coil cooling be interrupted?

Only for a very short time with molten metal in the furnace, often measured in minutes, and the furnace maker sets the limit. That is why cooling pumps restart first on the generator, and why many foundries also keep a gravity tank or battery-backed pump as a second line of protection.

What size generator does a foundry need?

One sized for the protected loads, not the furnace: coil cooling, cooling tower fans, tilting hydraulics, fume extraction, controls, lighting and emergency crane moves. In the example on this page that is about 212 kW, so a 320 to 380 kVA set, checked against the largest motor start and the summer derating.

Why does our generator output drop in summer near the furnace?

Intake air temperature and radiator fouling. Engines lose output above the reference ambient and a radiator coated in scale dust cannot reject the heat, so the set derates or trips on high coolant temperature. Relocating the intake and cleaning the radiator on a shorter interval usually recovers it.

Should the control room be on UPS as well as the generator?

Yes. Control systems, furnace controls and safety instrumentation must stay alive through the few seconds before the generator takes load, so they sit on UPS. The generator then carries them and recharges the UPS for the rest of the outage, while cooling and fume extraction restart around them.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.

CallWhatsAppEnquire