In short. The 125 kVA diesel generator — 100 kW at 0.8 power factor, about 174 A per phase at 415 V — is one of the most traded sizes in the used market, because it fits so many duties: bank branches and offices, mid-size apartment blocks, function halls, small factories, cold rooms and commercial floors. Reddy Generators sells used (as-is) and refurbished 125 kVA sets of all major makes, every one load-tested at our Pedda Amberpet workshop before it is offered. Stock changes weekly: message WhatsApp 98852 01608 for what is on the floor today.
What a 125 kVA set runs
With 100 kW of engine behind it, a 125 comfortably carries a typical commercial floor of lighting, computers, lifts and pumps, or a small works — direct-on-line motor starting is its one real limit, with roughly a 12–15 kW motor the comfortable DOL ceiling at a 15% dip, and motors into the thirties of kW handled easily through a star-delta or soft starter.
We proved the duty ourselves: four 30 kVA sets serve a private bank’s Hyderabad branches, and a single 125 kVA machine has carried a Begumpet business-services office since 2015 — the same rating class doing exactly this work. If your largest motor is big relative to the set, run the motor-starting calculator before deciding.
Why 125 kVA buys well used
Every major maker builds this frame — Kirloskar, Mahindra, Ashok Leyland, Cummins, Eicher, Escorts and more — so parts and service skills are everywhere in Telangana and AP, and there are always sets to choose from. Most 125s come out of standby duty with modest hours. That combination — plentiful, well-supported, lightly used — is what makes the rating a sound second-hand purchase when the individual machine passes a proper load test.
What we check before a 125 is offered
Cold start, smoke colour, oil pressure and temperatures on a sustained load-bank run; voltage and frequency stability; alternator insulation; canopy, battery, charger and gauges. A used (as-is) set then carries its inspection report and load-test record, no warranty; a refurbished set has been rebuilt where the inspection demanded and carries our six-month warranty (rubber and plastic parts, consumables, fuel-quality damage and overloading excluded). The definitions are spelled out on the used and refurbished page.
Sold as a complete system, not a bare machine
With the set we supply and install whatever your site lacks: AMF panel, manual or motorised changeover, cabling, earthing and exhaust. One accountable supplier for the machine and the switchgear — and the same team services it afterwards, anywhere in Telangana, Andhra Pradesh and the districts around Hyderabad.
Fuel at the loads a 125 actually carries
| Load on a 125 kVA set | Electrical output | Fuel, about | Four hours a day for a month |
|---|---|---|---|
| 50% | About 50 kW | 15 litres an hour | About 1800 litres |
| 75% | About 75 kW | 21 to 23 litres an hour | About 2520 to 2760 litres |
| 100% | About 100 kW | 27 to 30 litres an hour | About 3240 to 3600 litres |
These ranges span the published data of different makers for modern engines in this class; an older engine or one in poor condition burns more, which is one thing the load test shows. A set that burns noticeably more than this at a given load on the load bank is telling you about injectors, air filtration or wear before you have paid for it. See DG fuel consumption chart.
What the load test and inspection look at, and why
| Check | What good looks like | What a poor result points to |
|---|---|---|
| Cold start | Fires within a few seconds without excessive cranking | Weak compression, injector or fuel system faults |
| Smoke on load steps | A brief puff that clears quickly | Worn injectors, turbo or air restriction, overfuelling |
| Oil pressure, hot and on load | Steady and within the maker’s band | Bearing wear or a tired oil pump |
| Coolant temperature on a sustained run | Stable, well below the alarm point | Blocked radiator, failing pump or thermostat |
| Crankcase breather | Light vapour | Heavy blow-by from worn rings and liners |
| Voltage and frequency on steps | Quick recovery, steady at load | Governor or regulator faults |
| Alternator insulation | High, stable readings | Moisture or ageing windings |
| Canopy, battery, charger and wiring | Sound, dry, secure | Hidden costs after purchase |
Hours on the meter say less than these checks. A set with modest hours that stood idle for years in a damp room can be in worse shape than one with more hours that was run and serviced regularly.
What comes with a used or refurbished 125
- The inspection report, listing what was checked and what was found.
- The load-bank test record, with load steps, voltage, frequency, temperatures and oil pressure.
- For a refurbished set, the list of work done and parts replaced, and the warranty terms in writing.
- Engine and alternator nameplate details, so spares can be ordered correctly later.
Size, weight and the site
A canopied 125 kVA set is typically about 3.0 to 3.3 m long, 1.1 m wide and 1.5 to 1.8 m high, weighing about 1.7 to 2.0 tonnes, depending on the engine and enclosure. It needs a level plinth, a clear metre around the canopy for doors and servicing, a cable route to the changeover sized for about 174 A after derating, an earth connection, and an exhaust outlet that discharges away from windows, air intakes and neighbours. Most commercial sites can accommodate one in a parking corner or terrace, subject to the structure carrying the load.
The first months after purchase
Treat the first weeks as a check on the decision. Run the set on load at least monthly, not just started and stopped, because standby engines suffer more from idling than from work. Keep the fuel clean and the tank topped up to limit condensation, check the battery and charger, and book the first service with fresh filters and oil so that the history starts on your terms. Any change in smoke, oil pressure or starting in the first months is easier to trace while the test record is fresh.
Upgrading or trading in
If the 125 replaces an older or smaller set, Reddy Generators also buys used generators and takes sets in part exchange, so the old machine can leave the site on the day the replacement arrives. Tell us its make, rating, hours and condition when you enquire.
Questions to ask any seller of a used 125
- Can I see this exact set run on a load bank, at full load, for long enough for temperatures to settle?
- Where did the set work, and was it standby or daily duty?
- Which parts were replaced, and is there a written list?
- What emission stage is it certified to, and will my site accept it?
- What exactly does the warranty cover and exclude, if there is one?
- Who will install, commission and service it afterwards?
A seller who cannot answer these with documents is asking you to buy on trust. Every 125 we offer comes with the inspection report and the load-test record, and refurbished sets with the work list and warranty terms.
Worked example: a typical standby load on a 125 (illustrative)
| Load | kW | Power factor |
|---|---|---|
| Lighting | 12 | 0.95 |
| Computers and small UPS | 15 | 0.95 |
| Lift, 11 kW motor | 12.5 | 0.85 |
| Water pump, one duty unit | 8.5 | 0.85 |
| Split air conditioners | 30 | 0.90 |
| Total | 78 kW, 36.4 kVAr | About 86 kVA |
About 86 kVA is 69% of a 125 kVA set, a healthy running load with room for the lift and pump to start and for some growth. The same load on a 100 kVA set would run at 86% with little margin for the motor starts; on a 160 it would run lightly loaded for years. That is the arithmetic we show before recommending a size.
Standby duty and daily duty change the ownership
| Duty | Running hours a year, roughly | Oil and filter service | What wears first |
|---|---|---|---|
| Standby behind a reliable grid | 50 to 200 | Usually by calendar, once a year | Batteries, hoses and fuel quality from standing |
| Daily power cuts, four hours | About 1400 | Every two to four months, by hours | Filters, injectors, belts |
| Prime power, most of the day | 4000 or more | Every few weeks | The engine itself; plan for an overhaul |
Many current engines in this class specify oil changes at around 500 running hours, so a set on daily duty needs a service plan built on hours, while a standby set needs one built on the calendar and on regular runs. Buying the right condition for the duty, as is for light standby and refurbished for daily running, keeps both kinds of ownership predictable.
Mistakes that make a used 125 disappoint
- Buying on hours and paint without a load test.
- Sizing from the connected load, so the set runs at 30% and smokes.
- Ignoring the largest motor start until the first day the lift and pump start together.
- Installing with an undersized cable or no proper earth.
- Starting the set once a month without load, which harms a diesel more than running it.
Each of these is avoidable with an hour of planning, and each one is something we check before a set leaves the workshop for a new site.
Ask what is in stock this week
WhatsApp 98852 01608 or the enquiry form. Tell us the duty (standby or regular), the largest motor if any, and your town. Viewing and witnessing the load test at the workshop is by appointment — and if a 125 is the wrong size for your load, we will say so and show the arithmetic.
Questions buyers ask about used 125 kVA sets
How much diesel does a 125 kVA generator use?
Typically about 15 litres an hour at half load, 21 to 23 at three quarters and 27 to 30 at full load for a modern engine in good condition, depending on the make. Four hours a day for a month at 75% load is about 2520 to 2760 litres. A used set that burns noticeably more on the load bank is showing injector, air or wear problems.
How big and heavy is a 125 kVA generator?
A canopied 125 kVA set is typically about 3.0 to 3.3 m long, 1.1 m wide and 1.5 to 1.8 m high, and weighs about 1.7 to 2.0 tonnes, depending on the engine and enclosure. Allow a level plinth and about a metre of clear space around it for doors and servicing.
What is the price of a used 125 kVA generator?
It depends on the make, the hours, the emission stage and above all the condition proven on the load test, and whether it is sold as is or refurbished with a warranty. Send a WhatsApp message to 98852 01608 for the current 125 kVA stock, with the test records for each set.
How many amps does a 125 kVA generator give?
About 174 A per phase at 415 V three phase, which is 100 kW at a power factor of 0.8. The output cable, changeover and breaker must be sized for that current after derating for the installation method, and the full table for every rating is on the full load current chart.
Will a 125 kVA set start my 30 kW motor?
Not direct on line within a normal voltage dip, because a 30 kW motor starting that way draws far more than the set can supply without a deep dip. With a star delta starter, soft starter or drive, and started while the set is lightly loaded, a 125 handles it comfortably.
Used or refurbished 125 — which should I buy?
For light standby duty behind a reliable grid, a good as is set with a clean load test record serves well. For daily power cuts or long running, choose a refurbished set, rebuilt where the inspection required and covered by the six-month warranty, because the extra running exposes any weakness quickly.
Can I see the set run before buying?
Yes. Workshop viewing at Pedda Amberpet is by appointment, and you can witness the load bank test of the exact set you are buying, with temperatures, oil pressure, voltage and frequency recorded on the test sheet that comes with it, so you judge the set by how it behaves at load.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 1 November 2026.