In short. Critical power equipment wears out in predictable ways. Batteries lose capacity, UPS capacitors and fans age, generators need service by running hours and by time, and breakers stiffen when they are never operated. A maintenance plan combines time-based tasks, condition checks and replacement before end of life. It must be carried out without putting the critical load at risk.
Who this page is for: For facility managers and maintenance engineers responsible for generators, UPS, batteries and switchgear.
Key facts
- Batteries usually wear out well before their nominal design life.
- Heat shortens battery life sharply; keep battery rooms cool.
- UPS capacitors and fans have shorter lives than the UPS itself.
- Generators need service by running hours and by calendar time.
- Breakers should be exercised and checked, not left untouched for years.
- Plan replacement of ageing equipment before it fails.
A typical maintenance plan
| Equipment | Task | Typical interval |
|---|---|---|
| Generator | Run on load; check fluids, belts, starting battery | Monthly |
| Generator | Oil and filter change; coolant replacement | Oil and filters every 250–500 running hours or six months, whichever is earlier; coolant every year |
| UPS | Inspection, alarm review, fan check | Every 6 to 12 months |
| Batteries | Block voltage, internal resistance, temperature | Quarterly; discharge test yearly |
| Switchgear | Thermal imaging under load; breaker exercise | Yearly |
Worked example: a battery room at 32 °C (illustrative)
| Item | Value |
|---|---|
| Expected battery life in a cool room | about 5 years in service |
| Room average | 32 °C |
| Rule of thumb | Life roughly halves for each 8–10 °C above about 25 °C |
| Likely life | about 3 years |
| Action | Dedicated cooling for the battery room; discharge test brought forward |
The discharge test showed the batteries giving only 60% of their rated time in their third year, so the string was replaced at once. See battery autonomy and monitoring.
Do not carry out maintenance on a critical path without first confirming the other path is healthy and carrying the load. Many maintenance outages come from that single check being skipped.
Planning replacement
- Keep an asset register with install dates and condition.
- Replace batteries on test results, not on calendar alone.
- Plan UPS and switchgear renewal well before spares run out.
See modernisation.
Asset and maintenance sheet
The register for a 500 kW vaccine cold store and quality-control laboratory, which is a cool-room installation and not the 32 °C battery room in the example above. Eight assets, with the year each went in rather than its age, so the sheet stays readable in five years’ time. The last column is the one that makes this a plan instead of an inventory: every line names a year or an interval, and a line with neither is an asset nobody owns.
| Asset | Installed | Last service or test | Condition | Plan |
|---|---|---|---|---|
| Generator set, 500 kVA | 2014 | Full service at 820 running hours; now at 850 | Oil analysis clean, starting reliable, no blow-by | Calendar governs here, not hours: top overhaul planned 2030 whatever the hour meter reads |
| Generator starting batteries | 2024 | Load-tested four months ago at 94% of rated cranking | Good | Replace 2028. Load-test every six months, not just measure voltage |
| Day tank, transfer pump and fuel | 2014 | Tank cleaned and drained nine months ago | Free water found at the drain point on each of the last two drains | Fit a water-in-fuel alarm. Drain, sample and record every six months |
| UPS, 3 × 60 kVA modules | 2019 | Capacitors replaced in modules 1 and 2 at five years; module 3 not done | Module 3 fans audibly worn. Nominal fan life about seven years | Fans and capacitors in module 3 this year, then a fan set every seven years across all three |
| UPS battery, two strings | 2022 | Discharge test five months ago | String A at 86% of rated capacity, string B at 91% | Replace both strings together at 80%, expected 2027. Discharge test every six months |
| Changeover panel and contactors | 2014 | Contacts inspected and transfer timing checked eleven months ago | Pitting on the mains contactor tips | Replace the mains contactor now. Inspect, exercise and re-time yearly |
| Main LV board, 800 A incomer | 2014 | Thermal survey ten months ago, no hot joints | Sound, but no record of the incoming breaker being serviced since 2019 | Service the incoming breaker this year, then every five years |
| Cold-store units, 3 × 45 kW | 2014 | Motor 2 rebuilt 2023 | Motors 1 and 3 still on their original internals | Rolling rebuild, one a year from 2027, so no two are ever due in the same season |
The first line carries the lesson that catches out most standby installations. The set has run 850 hours in twelve years, which is about 70 a year, so at that rate it would reach a 3000-hour overhaul somewhere around the middle of the century. Hours will never be the thing that retires it.
Hoses perish, belts harden, gaskets take a set, control electronics age and the alternator’s insulation picks up moisture and dust whether the engine turns or not, so the plan has to be written against the calendar and the hour meter treated as the lesser of the two triggers. A maintenance regime indexed only to running hours will leave a standby set untouched for a decade and call that compliance.
Two more patterns are worth lifting off the sheet. The battery line replaces both strings together even though string B is the better of the two, because a new string paralleled with an aged one shares current unequally and the new one works harder for its whole life — the matched pair is worth more than the four years left in string B. And the last line spreads the motor rebuilds one a year rather than doing all three when they come due, which costs a little more in visits and removes the case where two of the three are open at once. Both are the same idea from different directions: on a resilient installation the schedule is arranged so that no single week concentrates the risk.
The two lines with the word “no record” on them deserve one last note, because an absent record is itself a condition. Nobody knows what state the incoming breaker is in, so it has to be planned as though it is the worst of the eight, which it may well not be. That is the real cost of a register that was not kept: the work gets done twice, once to find out and once to fix it.
What shortens the life of each item, and what to watch
Every item in a critical power system has a design life stated by its maker, and almost every item reaches the end of its real life sooner or later than that figure depending on how it is used and where it stands. Knowing what drives each item’s ageing tells you what to measure, and the measurements tell you when the item is really due.
| Item | What shortens its life | Evidence to watch |
|---|---|---|
| Lead-acid UPS batteries | Heat above the rated temperature, deep and frequent discharges, poor charging | Discharge test results, block voltages, internal resistance trend, room temperature |
| UPS fans and capacitors | Heat and running hours, dust on filters | Internal temperatures, fan alarms, the maker’s replacement interval |
| Generator engine | Light-load running, infrequent use, poor fuel and coolant care | Oil analysis, starting time, exhaust condition, running hours |
| Generator starting batteries | Heat, age and repeated cranking | Voltage during cranking at each test |
| Circuit breakers | Number of operations, fault interruptions, lack of exercise | Operation counters, contact wear indication, timing tests |
| Switchboard joints and cables | Load cycling, overheating, poor termination | Thermal imaging under load, insulation resistance trend |
Two items in the table age even when nothing is happening: batteries and breakers. A battery sitting on float in a warm room ages every day, and a breaker that has not operated for years can stick when it is finally called on. Both are reasons why a quiet system, with no outages for a long time, is not necessarily a healthy one; it may simply be one whose weaknesses have not yet been asked to show themselves.
Which spares to hold on site
The time a critical system spends without its redundancy after a failure is set largely by how long the replacement part takes to arrive. For most parts, a supplier’s stock and a delivery the next day are enough. For a few, the wait is weeks, and those are the spares worth holding on site.
| Spare | Why hold it |
|---|---|
| UPS fuses, fans and a control or interface card | Common failures that restore a unit to service in hours |
| A few battery blocks of the installed type | Replace a failed block at once, keeping the string intact |
| Generator filters, belts and a starting battery | Keep a set running through a long outage |
| Controller of the type used on the generators or changeover | Long lead times and no workaround without one |
| Breaker trip units, coils and auxiliary contacts of the installed types | Restore a breaker without replacing the whole unit |
Spares held on site must be stored correctly, recorded with their part numbers and checked against the installed equipment whenever that equipment changes. A spare control card of the wrong revision, discovered at night during a failure, is worse than no spare at all, because time is lost finding out that it does not fit.
Planning for the end of support
Critical power equipment often outlives the maker’s support for it. Spare parts are discontinued, firmware is no longer updated, and the specialists who knew the model move on. Equipment past the end of support may run perfectly well, but each repair becomes slower and more uncertain, and eventually a single failure cannot be repaired at all.
The way to stay ahead is to ask each maker, for each major item, for its support status and the date at which spares and service will end, and to record those dates in the asset register. Plan replacement two to three years before support ends, so that the work can be done in a controlled programme, one path at a time, rather than forced by a failure that cannot be repaired. Where replacement must wait, buy a stock of the critical parts while they are still available, and keep them as described above.
A yearly review of the maintenance plan itself
A maintenance plan written at commissioning describes the system as it was then. Each year, review it against what has changed: new equipment added, running hours far higher or lower than expected, a battery room hotter than designed, a supplier contract renewed or lapsed. Compare the year’s test results and failures with the plan, and ask of each failure whether the plan should have prevented it. A plan adjusted every year from the evidence keeps pace with the system; one left unchanged for a decade maintains a system that no longer exists.
Common mistakes
- Batteries replaced only after failure.
- Hot battery rooms.
- Breakers never operated.
- Maintenance without checking the other path.
What to send us
Send your asset list and maintenance records. WhatsApp 98852 01608 or use the application engineering enquiry.
Evidence note. Values are illustrative.
Questions engineers ask
Which spares should a critical power site keep on hand?
Those whose wait would otherwise be weeks, or that restore a failed unit in hours: UPS fuses, fans and a control or interface card; a few battery blocks of the installed type; generator filters, belts and a starting battery; a spare controller of the type used on the generators or changeover; and breaker trip units, coils and auxiliary contacts of the installed types. Record part numbers and recheck them whenever the installed equipment changes.
What happens when critical power equipment reaches the end of maker support?
It may keep running well, but spares are discontinued, firmware stops being updated and specialists move on, so each repair becomes slower and eventually a failure may not be repairable at all. Ask each maker for the support end date of every major item, record it in the asset register, and plan replacement two to three years earlier. Where replacement must wait, buy the critical spare parts while they are still available.
How often should a standby generator be serviced?
Follow the manufacturer’s schedule and your running hours, with more frequent checks of starting, fuel and controls. As a working standard, change oil and filters every 250 to 500 running hours or six months, whichever comes first, change coolant every year, and test the set on load regularly.
Why are batteries so important?
They are often the first thing to fail and are critical to starting and bridging. Measure their health, not just voltage. Internal resistance or conductance measurements show weak blocks long before their voltage falls, and a load test confirms real capacity. Starting batteries and UPS batteries are both replaced on condition and age, before they fail in service.
What is condition-based maintenance?
Doing tasks when measurements show a need, not only at fixed intervals. Oil analysis, thermography, battery monitoring, vibration and insulation resistance trends show when a component needs attention, which avoids both unnecessary work and missed deterioration, while safety-related tasks and maker-required services keep their fixed intervals.
How do I avoid maintenance-caused outages?
Use method statements, work one path at a time and restore and test the system after each task. Each task is planned with the affected loads identified, isolation points listed and a second person checking the switching, and the system is returned to its normal automatic state and confirmed healthy before the next task starts.
This guide gives general principles. Follow manufacturers’ instructions and site safety rules.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.