Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Critical-Power FMEA and Failure-Scenario Engineering

How to run a failure mode and effects analysis on a critical-power system, build failure scenarios, rank risks and turn findings into design and test actions.

In short. A failure mode and effects analysis (FMEA) lists how each part of the power system can fail, what that failure does to the critical load, and how quickly it would be noticed. Each risk is scored, and the highest risks get actions. In critical power, the most useful results usually come from hidden failures, such as a flat starting battery or a breaker left open after maintenance. Scenarios that combine failures add what a part-by-part list misses.

Who this page is for: For facility managers, consultants and reliability engineers reviewing critical power systems for weak points.

Key facts

  • List each part, its failure modes and their effect on the critical load.
  • Score severity, occurrence and detection, each from 1 to 10.
  • Risk priority number = severity × occurrence × detection.
  • Review every high-severity item, whatever its total score.
  • Hidden failures, found only on demand, deserve the most attention.
  • Re-score after actions to confirm the risk fell.

Worked example: four entries (illustrative)

Failure modeSODScoreActionScore after
Generator starting battery weak956270Battery monitoring with alarm90 (D 2)
UPS bypass breaker left open after maintenance847224Checklist and position alarm64 (D 2)
Fuel contaminated936162Periodic fuel testing54 (D 2)
Changeover controller fails to transfer935135Regular on-load transfer test81 (D 3)

S is severity, O is occurrence and D is detection, where a higher D means harder to detect. Each action improved detection, which is often the cheapest way to cut risk. See availability modelling.

Do not rank by total score alone. A failure that would drop the whole critical load deserves action even if it seems rare.

From parts to scenarios

ScenarioWhy a part list misses it
Mains fails during UPS maintenanceTwo normal states combined
Generator starts but the changeover failsEach part passes its own test
Cooling fails, then the UPS overheatsFailure spreads between systems

See continuity chain and transfer coordination.

FMEA sheet

Seven parts of a 500 kW vaccine cold store and quality-control laboratory, scored on the one-to-ten scales. It is a different installation from the one in the example above, which is why the generator battery is deliberately left out of this sheet rather than scored again; these are the seven lines that came after it. S is severity if the failure happens, O is how often it is expected, D is the chance it stays undetected until it matters — so a high D is a bad thing, and RPN is the three multiplied together.

PartFailure modeEffectSODAction
Battery string connectionHigh-resistance jointString drops out under load; half the autonomy gone with no warning and no alarm848RPN 256. Impedance test every six months and alarm the string breaker position
Day tank level switchSticks in the full positionTransfer pump never calls. The 500-litre day tank empties in about seven hours at 74 litres an hour while the bulk tank is still full, and the set stops937RPN 189. Independent low-level float on its own alarm, plus a dipped reading at every monthly run
UPS static switchFails to transfer to bypass on a UPS faultAll 104 kW of no-break load lost, with a healthy supply sitting on the other side of the switch927RPN 126. Exercise the transfer twice a year on load and alarm the switch position continuously
Monitoring supply at the server rackPlug pulled out during cleaningAudit trail gap. Nothing is damaged but batch release is delayed until the gap is explained654RPN 120. Locked plug, a labelled socket and a daily check that data is arriving
Refrigeration anti-recycle timerFails short, so the delay is lostAll three motors restart together instead of in sequence. The 135 kW block arrives as one step, the frequency dip goes past the 10% limit and the set can trip, so the building loses the supply it had just recovered735RPN 105. Stagger the restarts 30 seconds apart in the controller and prove it on the next black-building test
Cold-store feeder cableMechanical damage at the yard crossingRefrigeration lost. A second feeder exists but has to be changed over by hand, so the loss lasts as long as it takes somebody to get there726RPN 84. Route survey, mechanical protection at the crossing and a labelled manual changeover
Mains contactor in the changeoverContacts weld closedThe set could close onto a live mains and back-feed into a fault1016RPN 60. Mechanical interlock between the two contactors and auxiliary contact proving before any close
       
       

The sheet is sorted by RPN, and the order it produces is not the order anybody expected. The welded mains contactor is the most frightening line on the page — severity 10, a back-feed onto a live network — and it ranks last, at 60, because it is rare and because a mechanical interlock makes it visible.

The highest score, 256, belongs to a loose battery terminal: a joint nobody can see, on equipment nobody tests between services, which quietly removes half the autonomy the whole design depends on. That is the pattern FMEA exists to expose. Severity alone ranks the dramatic failures; the product ranks the ones that are actually waiting for you.

The two highest lines also share a cause, and it is worth naming: both are failures of a measurement, not of a machine. The battery joint and the stuck float switch are both cases where the system is telling the control panel that everything is in order and the panel has no way to know otherwise. Four of the seven actions in the last column are therefore detection measures rather than repairs — an impedance test, an independent float, a switch-position alarm, a daily data check — because on a standby installation the detection score is almost always the easiest of the three to move.

A starting library of failure modes

An FMEA is only as complete as its list of failure modes, and the most common weakness is listing each component as simply “fails”. Each type of component fails in several distinct ways, with different effects, and each way needs its own line. The library below is a starting point for the main items in a critical power system.

ComponentFailure modes to list separately
Circuit breakerFails to open on command or fault; fails to close; opens without cause; loses its position indication
Automatic transfer switchFails to transfer; transfers when it should not; stuck between sources; transfers to a dead source
GeneratorFails to start; fails to take load; fails while running; fails to synchronise; shares load wrongly
UPSInverter failure with transfer to bypass; failure to transfer; battery unable to carry the load; output fault
Protection relayFails to trip; trips without a fault; loses its auxiliary supply
Control systemStops issuing commands; issues a wrong command; loses communication with field devices
Cable or busbarShort circuit; earth fault; open circuit at a joint

The modes that do something unwanted — a breaker opening without cause, a transfer switch moving to a dead source, a control system issuing a wrong command — are the ones most often omitted, because designers think about equipment failing to do its job rather than doing the wrong job. They are also among the most damaging, because redundancy designed to cover a missing function may do nothing against an active wrong one.

Common mistakes

  • Scoring done once and filed.
  • Human error left out.
  • Only single failures considered.
  • Actions with no owner or date.

What to send us

Send your single-line diagram and maintenance records. WhatsApp 98852 01608 or use the application engineering enquiry.

Evidence note. Scores are illustrative.

Scoring S, O and D without flattering the design

An FMEA is only as good as its three columns, and all three are routinely scored in whichever direction makes the result comfortable. The scales below are the ones used on the sheet above, written down before the scoring started rather than agreed afterwards, which is the single thing that most improves an FMEA.

Two rules keep the output usable. First, re-score after the action, not just before: the point of the last column is to move a number, and an action that leaves the RPN where it was has not earned its place.

The battery joint above goes from 256 to about 64 once impedance testing drops detection from 8 to 2 — the failure is just as likely, and that is fine, because it is now found at a test instead of at an outage. Second, never let a low RPN close out a high severity: a severity of 9 or 10 gets a control regardless of what the product says, because the product is an ordering tool and not a licence.

Lastly, a date and a name. Every line that carries an action carries who does it and by when, and the sheet is reviewed against the fault log once a year. An FMEA with no review date is a document about a building that no longer exists.

Questions engineers ask

What failure modes should an FMEA list for a circuit breaker?

Each distinct mode on its own line: fails to open on command or on a fault, fails to close, opens without cause, and loses its position indication. Listing a component as simply failing hides these differences, and each has a different effect on the system. The same applies to every component: a transfer switch can fail to transfer, transfer when it should not, stick between sources or transfer to a dead source.

Why do unwanted actions matter so much in an FMEA?

Because designers tend to list equipment failing to do its job and miss equipment doing the wrong job: a breaker opening without cause, a transfer switch moving to a dead source, a control system issuing a wrong command. These are among the most damaging failures, because redundancy designed to cover a missing function may do nothing against an active wrong one. List them explicitly for every component.

When should an FMEA be done?

During design, so findings can change the design, and again after major changes or incidents. An FMEA done after construction can only add procedures and monitoring, while one done during design can change the architecture, which is far cheaper. A review after an incident checks whether the analysis missed the failure that occurred.

Is a risk priority number reliable?

It is a ranking aid based on judgement. Use it to prioritise discussion, not to claim precision. Two people can give the same failure different scores, so the numbers are agreed in a team review, and a high severity item is addressed even if its overall score is modest.

What is the difference between FMEA and a fault tree?

An FMEA starts from component failures and traces effects. A fault tree starts from an unwanted outcome and traces possible causes. They complement each other: the FMEA finds what each failure does, while the fault tree shows the combinations of failures that lead to an outage of the critical load.

How many scenarios should I test?

All high-ranked ones, and a sample of others, as the site allows. Tests are planned with the operations team, run under controlled conditions with rollback ready, and recorded with the observed result, so the analysis is confirmed by real behaviour rather than by assumption alone.

This guide gives general principles. A site-specific FMEA needs your drawings and operating experience.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 8 November 2026.

CallWhatsAppEnquire