In short. An industrial microgrid coordinates grid supply, diesel or gas generators, battery storage and rooftop solar under one controller, so a factory can cut demand charges in normal operation and keep its process safe when the DISCOM fails. It must be designed around the production sequence, not the meter: which loads must stay on, which can be shed, and in what order the plant restarts.
Start with the process, not the energy bill
A pharmaceutical plant in Genome Valley, a plastics moulder in Jeedimetla and a food processor near Shamshabad may draw similar maximum demand from the DISCOM, yet need entirely different microgrids. The first loses a batch if HVAC and process water stop; the second freezes material in its barrels if heaters drop for too long; the third loses product if cold rooms warm up. A design that begins with the electricity bill tends to optimise kWh and kVA demand, and then discovers during the first outage that the plant could not survive the transition. Begin instead with a load classification that the production manager signs.
| Class | Typical loads | Microgrid behaviour on grid failure |
|---|---|---|
| Must stay on | PLC and DCS, safety systems, instrument air for safe shutdown | UPS for no-break, generator behind it |
| Short break acceptable | Process cooling, critical pumps, clean room HVAC | Generator or BESS picks up within seconds |
| Restart in sequence | Motors, extruders, chillers, large motors | Restored one step at a time once sources are stable |
| Sheddable | Comfort cooling, non-process lighting, some production lines | Dropped on islanding, restored if capacity allows |
The classification decides generator capacity, battery power rating, UPS scope and the shedding list. Manufacturing power gives examples by sector.
Grid-connected operation: where the savings come from
Most of the time an industrial microgrid runs in parallel with the grid, and its value comes from controlling what the factory draws. Telangana HT consumers pay a demand charge on recorded maximum demand in kVA, so a short peak during a shift change can set the charge for the month. A BESS that discharges during those peaks, or a generator that synchronises and shares load briefly, reduces recorded demand. Solar reduces daytime energy import. Power factor correction and harmonic filtering keep kVA close to kW.
P_bess = P_site − P_limit, and E_bess = Σ (P_site − P_limit) × Δt
P_site is the instantaneous site demand, P_limit the demand target, P_bess the battery discharge power needed and E_bess the energy over every interval Δt in which demand exceeds the target. Worked example (illustrative): a plant peaks at 1450 kVA for about 40 minutes each morning and wants to hold 1250 kVA. At unity power factor from the battery, it needs roughly 200 kW of discharge and about 135 kWh of usable energy for that peak, more with margin for a longer peak. Generator-based peak shaving requires grid paralleling approval and protection agreed with the DISCOM; see peak-shaving power systems.
Island mode: the hard part
When the grid fails, the microgrid must open its point of common coupling, detect the island, form a stable bus from its own sources and reconnect loads in order. Each step has an engineering requirement. Islanding detection must operate before the DISCOM’s auto-reclose closes back onto an energised, unsynchronised plant.
The forming source, either a generator or a grid-forming inverter, must hold voltage and frequency while loads return. Motor restarts must be staggered so the combined inrush stays within the sources’ capability. Protection must work with the lower fault current of an inverter-held bus and the higher fault current of generators. Reconnection to the grid must be synchronised, never a dead closure onto a live plant.
Restoration order after islanding
- Control power and safety systems, which should never have dropped if UPS-supported.
- Process cooling and critical pumps, so the process returns to a safe state.
- Instrument and process compressed-air plants, one at a time.
- Production lines in the order the process engineer specifies.
- Comfort loads last, only if spare capacity remains.
The controller should own this sequence centrally, using breaker positions, voltage and frequency measurements and source status, rather than scattering it across unrelated logic in different panels. See microgrid controllers and islandable microgrids.
Production risk is part of the business case
An energy-saving strategy that interrupts production is not an optimisation. If peak shaving discharges the battery to its floor at 11:00 and the grid fails at 11:20, the plant has less backup than before the project. The microgrid business case must therefore value downtime as well as tariff savings, and the controller must reserve enough battery energy and generator readiness for the island transition. For many factories, the honest answer is a modest battery for peak management and ride-through support, with generators for sustained islanding, rather than a large battery expected to do everything.
Worked example: islanding a moulding plant (illustrative)
A plastics plant has a 1200 kW maximum demand, two 500 kVA diesel sets (400 kW each), a 500 kW and 500 kWh battery with a grid-forming inverter, and 300 kWp of rooftop solar. Its production manager has signed this load classification:
| Class | Loads | Load |
|---|---|---|
| Must stay on | PLCs, barrel temperature controllers, safety systems | 40 kW on UPS |
| Short break acceptable | Barrel heaters, mould cooling pumps | 250 kW |
| Restart in sequence | Moulding machine hydraulics, chillers, granulators | 600 kW |
| Sheddable | Comfort cooling, warehouse lighting, the tool room | 300 kW |
When the grid fails, the sequence runs like this:
| Time | Event | Sources carrying the island |
|---|---|---|
| 0 s | Grid lost; islanding breaker opens; sheddable loads tripped | Battery forms the island and carries about 290 kW |
| About 10 to 15 s | Both diesel sets start, synchronise to the battery and take load | Sets and battery share; battery returns to standby duty |
| Following minutes | Restart-in-sequence loads return in steps of about 150 kW | Sets carry up to their planned loading; battery covers each step |
| When capacity allows | Sheddable loads restored as solar and set headroom permit | All sources, under the controller |
The two sets give 800 kW and the battery 500 kW, so the 890 kW of essential and sequenced load is carried with margin. The 300 kW of sheddable load comes back only if solar is producing and the sets are below their planned loading. The barrels never cool, because the heaters were back within seconds; the machines restart under control, not all at once.
Grid-forming and grid-following inverters
Most solar inverters, and many battery inverters, are grid-following: they need an existing voltage and frequency to synchronise to, and they switch off when the grid disappears. A grid-forming inverter creates the voltage and frequency itself, so it can hold an island on its own and let the generators synchronise to it. An island needs at least one grid-forming source at every moment: the battery for the first seconds, the generators once they are running. Rooftop solar on grid-following inverters reconnects only after the island is stable, and the controller limits its output so a cloud passing over does not upset a lightly loaded island.
Protection when the plant is islanded
On the grid, a fault draws a large current that every breaker can detect. In an island fed by inverters, the fault current may be little more than the inverters’ rating, so overcurrent devices set for grid conditions can fail to trip. Protection relays carry a second settings group for island operation, selected automatically when the islanding breaker opens, and the generators’ own fault contribution is counted once they are running. The settings for both groups come from a protection study of the plant in each operating state, and both are tested.
Proving the island before relying on it
- Open the incoming breaker on a planned day, with production informed, and record the time each class of load is restored.
- Record voltage and frequency at the main bus for the whole transition with a power-quality recorder.
- Prove each shed and restore step, and the reconnection to the grid when it returns.
- Repeat the test after any change to sources, controls or the load classification.
The first test usually finds something: a drive that does not restart, a controller on the wrong supply, a step that is too large. Finding it on a planned day is the purpose of the test.
Classifying the plant loads before design
Every industrial microgrid design starts with a load list split into classes, because the island cannot carry everything the grid carries. The classes decide the battery rating, the number of generators in service and the order in which loads come back.
| Class | Typical loads | Island treatment |
|---|---|---|
| Critical | Controls, servers, safety systems, process instruments | Never shed; fed through the grid-forming source from the first cycle |
| Essential process | Moulding machines with material in the barrel, cooling water, compressed process air | Restored in early steps once generators are on the bus |
| Deferrable | Comfort cooling, workshop machines, battery charging for vehicles | Restored last, or left off until the grid returns |
| Excluded | Loads too large or too disturbing for the island | Locked out while islanded |
The classification is agreed with production and maintenance, signed and kept with the protection settings. When a new machine is installed, it is given a class before it is energised, otherwise the island quietly grows beyond what the sources can carry and the next outage shows it.
The same list is used at every islanding test, so the record shows which class each tripped or slow load belonged to and whether the step sizes still suit the sources available.
Common mistakes
- Designing around the monthly bill and treating islanding as an afterthought. The first grid failure shows the plant cannot restart its motors on the microgrid.
- Letting every motor restart automatically when the bus returns. The inrush collapses the island and the plant suffers a second blackout.
- Running generators in parallel with the grid without DISCOM approval and proper reverse power and loss of mains protection. The arrangement is unsafe for line staff and may breach the supply agreement.
- Spending the battery’s reserve on peak shaving. The site has no stored energy when the outage arrives.
What to send us
Send twelve months of HT bills with recorded maximum demand, a load list with motor ratings and starting methods, the single-line diagram, details of existing generators and their controllers, and a process engineer’s note on which loads must stay on and in what order the plant restarts. Fifteen-minute demand data from the meter is ideal. Send your application details. Remote sites with similar logic are covered under telecom microgrids.
Questions engineers ask
What happens in the first seconds when a factory microgrid islands?
The islanding breaker opens, sheddable loads are tripped and a grid-forming battery holds voltage and frequency for the essential loads. The diesel sets start, synchronise to the battery within about 10 to 15 seconds and take over, and sequenced loads then return in controlled steps.
Why does an island need a grid-forming source?
Because most solar and many battery inverters only follow an existing voltage and switch off without it. A grid-forming inverter, or a running generator, creates the voltage and frequency that everything else synchronises to, so at least one must be present at every moment of island operation.
Can our existing diesel generators become part of a microgrid?
Often yes, if their controllers support synchronising and load sharing or can be upgraded to do so. Older sets with basic AMF controllers usually need new control panels. Engine condition, CPCB compliance status and running hours decide whether upgrading is worthwhile, and a load-bank test on each set shows whether it can accept the load steps the island design asks of it.
Do we need DISCOM permission for an industrial microgrid?
Any arrangement that parallels on-site generation or battery export with the grid needs approval and protection agreed with the DISCOM. A microgrid that only islands, with no parallel operation, has fewer interface requirements, but the changeover arrangement must still prevent backfeed. Confirm the current requirements with the DISCOM at design stage, before equipment is ordered.
How large should the battery be for a factory?
Size it for its assigned job. Peak management needs power and energy matched to recorded peaks; ride-through support needs power for seconds to minutes; generator-free islanding needs hours of energy and is rarely economic at industrial scale. Most plants combine a battery sized for ride-through and peaks with diesel sets that carry the long outages.
What is the payback of an industrial microgrid?
It varies with the tariff, demand profile, outage frequency and value of lost production. Treat any generic payback figure with caution; a defensible number comes from interval meter data and a costed downtime estimate for your plant. Include the avoided cost of scrapped batches and restart time, which often outweighs the energy saving.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.