In short. A microgrid is a defined group of loads and energy sources, such as diesel or gas generators, batteries and solar, inside a clear electrical boundary, controlled so that it can operate as one system. It is defined by that boundary and by its controls, not by how many technologies it contains. Most microgrids must handle grid-connected operation, islanded operation, the transition between them and resynchronisation, and each mode needs a source that holds voltage and frequency.
What separates a microgrid from a collection of assets
Many Indian industrial sites already have a DISCOM supply, two or three diesel sets, a rooftop solar plant and perhaps a UPS bank. That is not yet a microgrid. Each asset runs on its own logic: the generators start on mains failure through AMF panels, the solar inverters shut down when the grid disappears, and nobody coordinates them.
A microgrid adds three things: a defined point of common coupling with the utility, a supervisory controller that sees every source and controllable load, and a control philosophy that states which source does what in each operating mode. Only with those three in place can the site keep its solar running through an outage, hold a battery reserve, or shed the right loads in the right order.
Typical architecture
At the top sits the utility connection through the point of common coupling (PCC), normally a breaker with its own protection and synchronising check. Below it is the site bus, often split into sections. Connected to the bus are generators with their synchronising panels, a battery with its PCS, PV inverters, and loads grouped by priority. The microgrid controller communicates with every generator controller, the PCS, the inverters, the PCC breaker and the load-shedding relays. See microgrid controller architecture for the control hierarchy.
Operating modes
| Mode | What holds voltage and frequency | Main control task |
|---|---|---|
| Grid-connected | The utility | Dispatch sources for economics; respect import and export limits |
| Transition to island | Handover from utility to local grid-forming source | Detect the event, open the PCC, stabilise the bus |
| Islanded | Grid-forming generator or battery | Balance generation and load; hold reserve; shed load if short |
| Resynchronisation | Local source, matched to returning utility | Match voltage, frequency and phase angle; close PCC |
| Black start | First local source onto a dead bus | Restore auxiliaries and loads in stages |
The grid-connected and islandable pages go deeper into the first four modes.
Who forms the grid
In an island, at least one source must set voltage and frequency, and the others must follow. A diesel generator in isochronous mode can do this, as can a grid-forming battery inverter. PV inverters normally cannot. When several sources can form the grid, they must share the job through droop control or a master controller; two sources trying to regulate the same bus without coordination will fight, oscillate and trip. Deciding this is the core engineering decision of any microgrid and is covered in grid-forming and grid-following coordination.
Δf = −R × ΔP
Here Δf is the frequency change, R the droop setting and ΔP the change in a source’s output as a fraction of its rating. With 4% droop on a 50 Hz bus (R = 2 Hz per unit), a source picking up an extra 25% of its rating lets frequency fall by 0.5 Hz to 49.5 Hz (illustrative), and parallel sources with equal droop share load in proportion to their ratings.
Where microgrids fit in Telangana and Andhra Pradesh
The strongest cases are sites where outages are costly and long enough that diesel alone becomes expensive: process plants, cold chains, hospitals, campuses, data centres and remote mining or quarry sites. Industrial parks with rooftop solar and frequent short grid interruptions are another good fit, because a microgrid lets solar keep producing through outages that would otherwise shut the inverters down. Sites with a reliable grid and few outages rarely justify the control investment. Sector detail is in industrial microgrids.
Protection in a microgrid
Fault levels change with the operating mode. Grid-connected, the utility contributes high fault current; islanded on a battery, fault current may be little more than the inverter rating. Protection that works in one mode may not operate in the other, so settings groups that change with mode, or protection based on voltage and directional elements, are often needed. Anti-islanding requirements from the DISCOM must also be met at the PCC.
Related photographs and videos
What the microgrid controller actually does
| Function | What it means on site |
|---|---|
| Dispatch | Decides which sources run and at what output, every few seconds |
| Mode transitions | Moves between grid-connected, islanded and black-start states |
| Reserve management | Keeps enough running capacity or stored energy for the next event |
| Solar curtailment | Limits solar output so the generator stays above minimum load |
| Load shedding and restoration | Drops and restores loads in priority order when capacity is short |
| Resynchronisation | Returns the island to the grid smoothly when supply is back |
| Logging and reporting | Records events, energy and fuel for review |
These functions can sit in one controller or be shared between generator controllers, inverters and switchgear relays. What matters is that each is defined, has an owner and is tested.
Sizing a small islandable microgrid (illustrative)
A rural processing unit has a daytime load of about 150 kW, a night load of 30 kW and an unreliable grid with several long outages a month. A 200 kW solar array covers much of the daytime energy on clear days. A battery of 250 kWh nameplate, with an inverter of 150 kW that can form the grid, carries the night load for several hours and smooths solar swings. A 250 kVA generator, giving 200 kW, covers cloudy days, long outages and battery recharging. The controller keeps the generator above about 30% load whenever it runs, curtails solar when needed, and connects to the grid when it is available.
The design is checked against the worst week in the outage and weather record: several cloudy days during a long grid outage. If the generator and fuel store can carry the site through that week, the microgrid is resilient; the battery and solar then reduce how much fuel that takes in normal weeks.
Screening whether a microgrid is worth it
- How often and for how long does the grid fail, and what does each outage cost the site?
- How many hours a year does the generator run now, and at what load?
- Is there space and sunlight for solar, and does the load match daytime generation?
- Can the site staff operate and maintain the added equipment, or is a service agreement needed?
- What approvals does the grid connection need for solar and any paralleling?
Sites with frequent long outages, high generator hours and good solar potential usually screen well. Sites with a reliable grid and a standby set used a few hours a year rarely do.
Commissioning a microgrid
- Test each source alone at its rated output.
- Test the grid-connected mode, including solar limits and any export settings.
- Open the grid supply and record the transition to island mode.
- Run islanded with load steps, solar changes and generator starts and stops.
- Trip the forming source and confirm the response is safe.
- Restore the grid and record the resynchronisation.
- Start from a fully dead state to prove black start where it is required.
Operating and maintaining it
A microgrid needs the same generator service as any other site, with oil and filters every 250 to 500 running hours or six months, whichever comes first, and coolant every year, plus battery health monitoring, solar panel cleaning, inverter checks and a review of controller logs. Settings changes are controlled and recorded, because a small change in one controller can affect how the whole system behaves. A yearly test of the main transitions confirms the system still works as designed.
Data that shows whether it is working
Monthly figures from the controller tell the story: generator running hours and fuel, solar energy used and curtailed, battery cycles and state-of-charge range, grid energy imported, and the number and length of islanded periods. Compared with the design estimates, they show whether settings need adjusting, such as a higher solar limit or a different generator start point, and they give the owner clear evidence of what the investment delivers.
A short monthly report built from these figures keeps the owner informed and highlights any change in behaviour early.
Common mistakes
- Calling a site with uncoordinated generators and solar a microgrid. Solar still trips on every outage and the expected benefit never appears.
- Leaving two grid-forming sources without a sharing scheme. They fight over frequency and the island collapses.
- Using one set of protection settings for all modes. Faults in island mode are not cleared.
- Skipping resynchronisation design. Return to the grid needs a full outage every time.
What to send us
Send the single-line diagram, details of every source including generator nameplates, PV and battery ratings, an hourly load profile, outage records for the past year and the loads that must stay on. State whether grid paralleling or export is permitted. Use the application engineering enquiry and we will propose an architecture and control philosophy.
Questions engineers ask
What does a microgrid controller do?
It dispatches the sources, manages transitions between grid-connected, islanded and black-start states, holds a reserve, limits solar output so the generator keeps a healthy load, sheds and restores loads in priority order, resynchronises with the grid and logs every event. These functions can sit in one box or several.
How do I know if my site suits a microgrid?
Sites with frequent long grid outages, high generator running hours, good solar potential and loads that match daytime generation usually screen well. Sites with a reliable grid and a standby set used a few hours a year rarely do. Outage cost, space, approvals and operating skill complete the picture.
How is a microgrid sized for the worst case?
It is checked against the worst week in the outage and weather record, such as several cloudy days during a long grid outage. If the generator and fuel store can carry the site through that week, the design is resilient, and the battery and solar reduce fuel use in normal weeks.
What maintenance does a microgrid need?
Generator service with oil and filters every 250 to 500 running hours or six months, whichever is earlier, and coolant every year, plus battery health monitoring, solar panel cleaning, inverter checks, controller log reviews, controlled settings changes and a yearly test of the main transitions.
Is a microgrid controller a single box?
It can be, but it is better understood as a function: supervisory control coordinating sources and loads within the boundary. It may be a dedicated controller, a PLC or a function within a power management system. Whatever form it takes, the protection and trips stay hardwired and independent of it, and it must fail to a safe state.
Can my existing generators become part of a microgrid?
Usually yes, if their controllers support synchronising, load sharing and remote setpoints. Older mechanical-governor sets may need controller upgrades. Engine condition, running hours and emission compliance decide whether upgrading is worthwhile, and a load-bank test on each set shows whether it can accept the load steps the microgrid design asks of it. The upgraded controls are tested on load before the microgrid relies on them.
Does a microgrid need a battery?
Not always. A generator-only microgrid can island and resynchronise. A battery adds fast response, the ability to switch generators off and a seamless transition, which is why most modern designs include one. The battery is sized for its assigned job, not as a general reserve.
Do I need DISCOM approval?
Any arrangement that parallels with the utility or exports needs the DISCOM’s approval and the protection it specifies. A microgrid that only islands via an open transition may need less, but confirm with the utility. Seek the approval before equipment is ordered, because the protection the DISCOM specifies can change the design.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.