Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Generators on Rent for Election Counting and Exam Centres: Security, Continuous Duty and Government Timelines

In short. Counting centres and examination centres are not ordinary events. The loads that must never drop are the CCTV, webcasting and strong-room systems, and at an exam centre also the halls at the moment the paper starts. The generators must sit outside the secured perimeter with supervised access, run continuously overnight, and be refuelled under the security protocol. Several centres often go live on the same morning. Plan from the government timeline backwards, and close every job with signed records.

Who this page is for: returning and assistant returning officers and their electrical staff, district and departmental administration, examination boards, recruitment and test agencies, centre superintendents, and colleges and schools that host counting or exam centres.

Key facts

How these sites differ from an ordinary event

A wedding or a concert is judged by the guests. A counting or exam centre is judged by observers, candidates and the official record. A dark CCTV feed in a strong room, a gap in a webcast or a hall that loses power at paper-start is a procedural issue, not just an inconvenience. The power plan therefore follows the security plan and the official timetable, and it must be documented so it can be shown to be sound afterwards.

For general event practice (event periods, noise and placement among guests, and stage and catering power), see event power rental.

Election counting centres: what must stay live

Put the computers, recorders, webcasting and network equipment behind a UPS, and the UPS on the generator. The generator covers duration; the UPS covers the transfer. Test the UPS on generator supply in advance, as described in UPS on generator supply.

Examination centres: zero tolerance at paper-start

Redundancy for counting and exam centres

Use two sets, each able to carry the critical load alone. What is specific here is which load counts as critical and how the second set is used:

Placement, cabling and security perimeter

Continuous duty and refuelling under security

Government timelines, work orders and documentation

Election and exam dates are announced well in advance, but approvals, work orders and site access can take time. Plan backwards from the date.

When What happens
As soon as the schedule is announced Share the list of centres, dates and hours. Reserve sets and operators per centre.
Before the work order Provide the technical proposal: sets per centre, critical circuits, redundancy, fuel and operator plan, and the rental terms.
On receipt of the work order Confirm quantities, centres, dates and the officer in charge at each centre.
Site survey Agree set location outside the perimeter, cable entry, internal board position and access arrangements with the officials.
Installation Sets placed, earthed and cabled; earth-resistance and insulation readings recorded.
Trial Full-load trial on the real critical load, changeover tested, UPS tested on generator, results signed by the centre’s electrical lead.
Operation Operator on site through the guarding period, counting day or exam sessions; log kept hourly.
Handover and close Shut-down only on the officer’s instruction, disconnection, removal, and the signed handover record.

Arrangement decision table

Centre type Suggested arrangement Point to watch
Strong room guarding, poll to count Duty and standby sets, continuous duty, external fuel tank Overnight refuelling windows agreed with security.
Counting hall with webcasting Duty and standby sets; CCTV, webcast and tabulation behind a UPS Network and encoder equipment on the protected supply.
Pen-and-paper exam centre Duty and standby sets; halls on generator before paper-start Do not switch back to mains mid-session.
Computer-based test centre Duty and standby sets feeding the centre’s UPS UPS input and recharge sized with margin; tested on generator.
Question-paper strong room or printing point Dedicated protected circuit for strong room, CCTV and printers Printing timed when both sets are running.
Several centres on one day A pair of sets and a named operator per centre Reserve early; no shared standby between centres.

Worked example (illustrative): strong room and counting hall at one centre

A counting centre in a college has two strong rooms that must be guarded for four days before counting, and two counting halls, a control room and a webcast point on counting day.

Guarding period (four days, continuous).

Load Estimate (kW)
CCTV cameras, recorders and guard monitors 1.5
Strong-room door and corridor lighting 1.0
Strong-room air conditioning, 2 × 1.8 kW 3.6
Guard post fans and lighting 0.5
Total 6.6

Counting day. Add hall lighting (6.0 kW), hall fans (3.0 kW), tabulation computers and printers (6.0 kW), public address (2.0 kW), webcast and network (1.0 kW) and control-room air conditioning (3.6 kW): 21.6 kW more, for a total of 28.2 kW, or about 33 kVA at a power factor of 0.85.

Choosing the sets. A 62.5 kVA duty set carries counting day at about 53 %, with an identical standby set; the margin covers UPS battery recharge, air-conditioner compressor starts and the non-linear load of the computers. During guarding, the 6.6 kW load is only about 12 % of one 62.5 kVA set, which is too light for days on end. The better plan is a separate pair of 15 kVA sets for the strong rooms during guarding (6.6 kW is about 55 % of one), with the 62.5 kVA pair added for counting day. That keeps every set reasonably loaded and limits light-load running. See light loading and wet stacking.

Fuel for guarding. At 6.6 kW, about 55 % load, and a typical 0.26–0.33 L/kWh at 50–100 % load, the duty set uses about 1.7–2.2 litres an hour; allow 2.5 litres an hour for air-conditioner cycling and margin. Over four days (96 hours), plan roughly 96 × 2.5 = 240 litres for the duty set, plus a reserve, with refuelling at agreed daytime windows. Confirm against the set’s fuel curve using the fuel consumption estimator.

All figures are illustrative. Each centre is surveyed and sized on its own loads.

Centre handover sign-off sheet

Item Recorded value or Yes/No Signed (centre) Signed (operator)
Centre name and officer in charge
Set serial numbers and ratings (duty and standby)
Set location outside perimeter agreed
Critical circuits identified and labelled
Earth resistance readings
Earth-leakage protection tested
Full-load trial completed (date, time)
Changeover tested
UPS tested on generator supply
Fuel at start (litres, both sets)
Refuelling windows agreed with security
Operator names and access passes
Log book opened
Shut-down on officer’s instruction (date, time)
Fuel at close and total used
Equipment removed and site restored

Exceptions and cautions

  • Official instructions take priority. The officer in charge decides access, timings and shut-down. The power plan must fit their security plan, not the other way round.
  • Never back-feed the building’s main board without a proper changeover that isolates the incoming supply.
  • Do not trust a campus earth without testing it.
  • Light load during guarding. A large set idling on a strong-room load for days will suffer; size the guarding sets separately.
  • Monsoon and storms. Protect the cable entry, joints and the internal board from water, and keep the sets above flood level.

Common mistakes

What to send us

Send the list of centres with addresses, the dates and hours for each (including any strong-room guarding period), the critical loads at each centre, any UPS or computer-based systems, and the name of the officer in charge. Use the generator rental enquiry, or WhatsApp the details to 98852 01608. For rental terms, see our rental rates guide and use Get price for your centres and dates. Rental covers the generator only: transport is at actuals in the customer’s scope, and cable and an operator are extra if required. For continuous duty at a counting or exam centre, an operator is usually needed.

Questions engineers ask

Which loads must never drop at a counting centre?

CCTV and recording, webcasting, strong-room lighting and monitoring, and the tabulation and result systems. Put them on a protected board that either set can feed, with a UPS for the electronic equipment.

Should exam halls change over to generator before the paper starts?

Yes. Transfer to generator supply before paper-start, confirm it is stable, and stay on generator until the session ends. Do not rely on a changeover at the critical moment.

Where should the generators be placed?

Outside the secured perimeter, at a location agreed with the officials, with cables entering through one protected route. That way refuelling and checks never need access to strong rooms or halls.

How is refuelling handled during strong-room guarding?

At fixed windows and routes agreed with security, standby set first, with every litre logged. An external bunded tank lets the sets run between refuelling windows.

Can one standby set cover several centres?

No. Centres often go live at the same time, so each needs its own pair of sets and a named operator.

What records should be handed over?

Set details, earth and protection test readings, the full-load trial result, fuel at start and close, the operating log and a signed handover sheet for each centre.

Related pages

Technical content reviewed by D. Srinivas Reddy, Managing Partner and service engineer. Last updated 5 November 2026.