In short. An apartment generator usually backs up lifts, water pumps, common lighting, security and the fire system’s support loads — and, in many communities, a limited supply to each flat. The sizing questions are how many lifts may run at once, how pumps start, and how much each flat is allowed to draw on backup. Without a per-flat limit, a few air-conditioners can overload a set sized for lights and fans.
Who this page is for: For apartment associations, facility managers and builders: decide what the community generator should back up, how much each flat can draw, and how to keep the set reliable and fair to all residents.
Key facts
- Lifts and pumps are the loads that dominate sizing because of their starting current.
- Modern lift drives can push energy back into the supply when a loaded car descends; a lightly loaded generator may over-speed or trip unless the lift is set up for generator operation.
- Per-flat backup is normally limited by a load limiter or dedicated backup circuit, so the set is not overloaded.
- Generator placement must consider exhaust, noise and fuel safety for residents.
What the community set usually carries
| Load | Why it matters | Sizing note |
|---|---|---|
| Lifts | Residents, elderly and medical needs | Count lifts that may run together; check drive type and regeneration |
| Water pumps (borewell, transfer, booster) | Water supply during long cuts | Starting method decides surge; avoid simultaneous starts |
| Common lighting and security | Safety, CCTV, gates, intercom | Small, steady |
| Fire system support | Fire alarm, pressurisation fans, jockey pumps | Follow the fire design; main fire pumps often have their own diesel engine |
| Clubhouse, gym, STP | Amenities | Often shed or limited during outages |
| Flat backup | Lights, fans, refrigerator, Wi-Fi | Limit per flat; ACs usually excluded |
Worked example: 120-flat block (hypothetical)
Hypothetical figures to show the method.
| Load | Running kW | Type / starting | Priority |
|---|---|---|---|
| 4 lifts, 2 running together on average | 22 | VFD (check regeneration) | 1 |
| Water pumps: 2 × 10 HP transfer, one at a time | 7.5 | Star-delta | 1 |
| Common lighting, CCTV, gates, intercom | 8 | Electronic / lighting | 1 |
| Fire alarm, pressurisation fans | 6 | Fans | 1 |
| STP blowers | 7.5 | Motor | 2 |
| Flat backup: 120 flats × 0.5 kW limit, about 60 % diversity | 36 | Mixed | 2 |
Running load ≈ 87 kW. At 0.8 PF and no more than 80 % loading: 87 ÷ 0.8 ÷ 0.8 ≈ 136 kVA, before checking pump and lift starting. A 160 kVA set may suit; if flats were allowed 1 kW each, the flat load alone would roughly double. The per-flat limit is the biggest decision the association makes.
Association backup-policy sheet
| Item | Your site |
|---|---|
| Number of flats and per-flat backup limit (kW) | |
| Loads excluded from flat backup (e.g. ACs, geysers) | |
| Lifts on backup and how many may run together | |
| Pumps on backup and their starting method | |
| Amenities shed during outages | |
| Monthly test day and time | |
| Who records running hours and fuel |
Placement, noise and safety
- Exhaust discharged well away from windows, balconies and air intakes
- Acoustic canopy and placement that respects neighbouring blocks
- Fuel stored safely, with spill containment and no ignition sources nearby
- Earthing designed and tested; access restricted to trained staff
When the usual assumptions fail
- “Only lights and fans in flats.” Without a limiter, residents will connect ACs. Enforce it electrically.
- Lift regeneration. A set that trips when a full lift descends at night is usually seeing regenerated energy, not overload. The lift and generator must be set up together.
- Light-load running. Large sets that carry only common lighting at night run very lightly; schedule meaningful-load exercise.
Questions for the association’s managing committee
- What per-flat backup limit is fair, and how will it be enforced?
- How many lifts must run during outages, and do their drives suit generator supply?
- Who runs the monthly test, and who records hours and fuel?
- How is generator cost shared — by flat, by backup meter, or in maintenance charges?
- Is the set’s canopy and exhaust acceptable to residents nearest it?
Checking motor starting: lifts and pumps
Running load decides whether the set can carry the community; starting load decides whether it can get there. A motor draws several times its running current while it accelerates, at a poor power factor, and the generator’s voltage dips while it does. If the dip is deep enough, lift drives drop out, contactors chatter and lights flicker in every flat.
| Starting method | Typical starting current (multiple of full-load current) | Where it is found in apartments |
|---|---|---|
| Direct-on-line (DOL) | About 6–7 × | Small booster pumps; many submersible borewell pumps |
| Star-delta | About 2–2.5 × | Transfer pumps of 7.5 HP and above |
| Soft starter | About 2.5–3.5 ×, adjustable | Larger pumps, sewage lifting |
| Variable-frequency drive | About 1–1.5 × | Modern lifts; hydro-pneumatic booster systems |
Starting kVA ≈ 1.732 × 415 × starting current ÷ 1000
Compare the largest single starting step with the alternator’s motor-starting capability on the data sheet, which is stated as starting kVA at a given voltage dip. Then make sure no two large starts can happen together: a timer that holds pump restarts for a minute or so after changeover, while lifts settle, costs very little and removes the worst case. Our motor starting page explains the dip calculation in depth.
Diversity: why 120 flats do not draw 120 limits
Diversity describes how far the group’s actual maximum demand falls below the sum of every flat’s limit; the 60 % figure in the 120-flat example above means about 60 % of that sum is drawn at the evening peak. Not every flat uses its full backup allowance at the same instant. In the evening, when lights, fans, televisions and refrigerators are all on, diversity is lowest — that is the hour to size for. At 2 am it is very high and the community draw may fall to a small fraction of the evening figure. Measure both: one evening reading and one late-night reading from the set’s meter tell the association more than any estimate.
Choosing a flat-backup scheme
How the association shares backup decides fairness, generator size and the number of complaints the committee receives. All of these schemes must be designed and installed by a licensed electrical contractor, with the mains and generator sources interlocked so they can never be connected together.
| Scheme | How it works | Enforcement | Fair billing | Watch-outs |
|---|---|---|---|---|
| Dedicated backup circuit | Selected flat circuits (lights, fans, a socket) wired to a separate generator-fed board | Fixed by wiring; residents cannot add loads to other circuits | Usually shared equally in maintenance charges | Rewiring needed in existing buildings; residents may extend the backup circuit informally |
| Load limiter on each flat | A device trips the flat’s backup feed if draw exceeds the set limit, then resets | Electrical and automatic | Shared equally, or by limit chosen | Limit setting must be sealed; repeated tripping needs a clear resident rule |
| Dual-source meter | Each flat’s meter records grid and generator energy separately and applies a backup limit | Electrical and automatic | Most precise: residents pay for generator kWh used | Meter must receive a reliable “generator on” signal; billing needs someone to administer it |
| Common areas only | Flats get no backup; set carries lifts, pumps and common loads | Not needed | Simple | Residents fit home inverters; the set may run very lightly |
Residents must never connect a home generator or inverter output into the building’s common wiring or a neighbour’s supply. Back-feeding can energise cables that maintenance staff believe are dead.
The night light-load problem
A 160 kVA set carrying 15 kW of common lighting through a night outage runs at under 12 % of its rating. Diesel engines held at such light loads for long periods do not reach full working temperature; unburnt fuel and oil collect in the exhaust (wet stacking), fuel consumption per useful kW rises, and lift regeneration is more likely to trip the set because there is so little load to absorb it. Remedies, in order of effort: run the monthly test at a meaningful load rather than idling it; keep pumps scheduled to refill tanks during long night outages; arrange a periodic load-bank run if the logs show long light-load hours; and, for new projects, consider two smaller sets so that one carries the night load.
Maintenance governance across committee changes
Generator problems in apartments are as often administrative as mechanical. Managing committees change every year or two, and knowledge leaves with them. Keep a single generator file that passes to each new committee: the set’s data, service contract scope and dates, the running-hours and fuel log, test records, the flat-backup limit decision and the lift company’s confirmation that drives are set for generator supply. A simple fuel sanity check catches leakage and pilferage: a healthy diesel set at moderate-to-high load typically uses roughly 0.25–0.3 litres per kWh generated, so litres used ÷ kWh recorded should stay steady month to month.
A second worked example: the borewell pump that dimmed the towers
Illustrative case. A two-tower community has a 200 kVA set. During an outage the set is carrying 90 kW when a 15 HP (11 kW) borewell pump starts direct-on-line. Lights dip across both towers and one lift stops between floors and re-levels.
| Step | Working | Result |
|---|---|---|
| Pump full-load current | 11 × 1000 ÷ (1.732 × 415 × 0.85 × 0.88) = 11,000 ÷ 538 | about 20.5 A |
| DOL starting current | 20.5 × 6 | about 123 A |
| Starting kVA, DOL | 1.732 × 415 × 123 ÷ 1000 | about 88 kVA |
| Starting kVA with a soft starter at 3 × | 1.732 × 415 × 61.5 ÷ 1000 | about 44 kVA |
| Running load after the start | 90 + 11 = 101 kW ÷ 0.8 PF | about 126 kVA, 63 % of rating |
The set is not overloaded; the running figure is comfortable. The problem is a sudden 88 kVA step at low power factor on a set already carrying over half its rating (90 kW of the 200 kVA set’s 160 kW at 0.8 power factor); the resulting transient dip is enough to trip this lift drive’s under-voltage protection. Fitting a soft starter halves the step, and a restart timer keeps the pump from starting within the first minute after changeover. Buying a larger generator would have been the expensive and less effective answer.
Common mistakes
- Sizing from the total sanctioned load of all flats instead of measured demand with diversity.
- Forgetting the lifts’ and pumps’ starting current when choosing the set.
- Running a large set all night on common-area load alone, which causes light-load damage.
- Leaving maintenance to whoever is on duty, with no log, no AMC and no tested changeover.
What to send us
Send the number of blocks and flats, lifts (number and motor size), pumps, common-area loads, how backup is shared with flats today, the existing set’s kVA and age if any, and the typical outage pattern. Use the application engineering enquiry, or WhatsApp the details and photographs.
Questions residents’ associations ask
What size generator does an apartment complex need?
Add lifts that may run together, pumps, common loads and the agreed per-flat backup, allow for starting, and keep the set at no more than about 80 % of rating.
Why does our generator trip when the lift comes down?
Many modern lift drives return energy to the supply when a loaded car descends. A lightly loaded generator cannot absorb it, so it over-speeds or trips. The lift drive needs a braking resistor or generator-mode setting.
How much backup should each flat get?
That is the association’s decision, but it must be enforced with a load limiter or dedicated backup circuit. Even small increases per flat add up quickly.
Can ACs be run on apartment generator backup?
Usually not in flats, because they would multiply the required generator size. Common-area or critical ACs can be included by design.
Related pages
Technical content reviewed by D. Srinivas Reddy, Managing Partner and service engineer. Last updated 3 November 2026.