Generator Relocation

How to move a diesel generator to a new site without losing reliability: decommissioning, lifting, transport, reassessing the installation and recommissioning.

In short. Moving a generator is not a transport job. The engine, alternator and controller stay the same, but the cable lengths, fault level, earthing, ventilation, exhaust route, fuel arrangement, transfer switch interface and ambient conditions at the new site are all different, and each has to be re-engineered. A relocation done properly runs from documented isolation and decommissioning, through engineered lifting and transport, to a fresh installation assessment and full recommissioning with a loaded test.

Why the installation has to be re-engineered

A set that has run reliably for years in one plant room carries no guarantee into the next. Everything that made the original installation work was designed around that site: cable size for that route and load, the earth electrode for that soil, ventilation for that room, the exhaust for that building, and protection settings for that fault level.

At the new site every one of those assumptions changes. The most common failures after a relocation are a longer cable run that drops voltage under motor starting, an undersized room that overheats the set at full load in April, and an earthing arrangement copied from the old site that does not suit the new one. The installation planning guide sets out what has to be re-examined.

Before disconnection: record and isolate

The first task is a record, not a crane. Before anything is disconnected, the set is photographed and documented: nameplates of engine, alternator and controller; every cable and termination with its core identification; the control wiring to the ATS or AMF panel and any remote monitoring; the protection settings and controller configuration, photographed page by page; the fuel, exhaust and earthing arrangements; and the operating condition, confirmed by a short run with readings. The battery is disconnected and the fuel tank drained to a safe level for transport.

Isolation follows a written procedure: breakers opened and locked, the ATS placed in a known state so the remaining site is not left exposed, and the fuel supply closed and capped. Cables are labelled at both ends before they are disconnected; control wiring that is not labelled now is guesswork later.

Lifting, transport and arrival

A canopied 500 kVA set weighs several tonnes with its centre of gravity offset toward the engine, and the lifting points on the base frame or canopy are the only approved points. The handling plan covers crane capacity against the documented weight, the slinging, the route out of the room including door and floor loadings, the vehicle and securing for the road. Open sets are protected from rain in transit; a wet alternator is a common reason a relocated set fails its insulation test on arrival. The set is inspected for transit damage before it is positioned, because damage found after reconnection becomes a dispute.

Assessing the receiving site

The new site is treated as a new installation, with a survey that covers each of the items below before the set is placed. A set that is positioned first and engineered afterwards usually ends up in the wrong place.

ItemWhat changes with the siteWhat has to be decided
Load and dutyDifferent connected load, motor sizes, UPS and VFD content, running hoursWhether the set is still correctly sized; see the capacity calculator
CablingRoute length, installation method, ambientCable size for voltage drop and fault withstand; the old cable is rarely the right length or size
Fault level and protectionDifferent source impedance and downstream devicesBreaker ratings and settings, coordination with the site’s existing protection
Earthing and neutralSoil resistivity, existing earthing system, neutral arrangement of the siteNew electrode design and test; neutral earthing at the set or at the panel, not both
Ventilation and exhaustRoom size, inlet and outlet positions, prevailing wind, neighboursAirflow for the radiator at the local ambient; exhaust route, height and silencer
FuelTank location, delivery access, day tank or bulkPipework, lift height for the fuel pump, storage approvals
Foundation and accessFloor loading, vibration transmission, service clearancePlinth or anti-vibration mounts, space to pull the radiator and open the canopy doors
Transfer and controlsDifferent ATS or AMF panel, different signalsInterface wiring and who is master; see ATS service

Earthing deserves a specific warning. The earth electrode cannot be copied from the previous site because it depends on the soil at the new one, on the prospective fault current and on the site’s existing earthing and lightning protection. The earthing and neutral grounding guide explains what has to be designed.

Reinstallation and recommissioning

Reinstallation reconnects the set into a system that has been designed for it: new or verified cables terminated and tested, earthing installed and its resistance measured, exhaust fitted with correct supports and expansion, fuel lines pressure-tested, control wiring reconnected against the record taken at the old site, and the controller configuration restored and checked against the new installation’s requirements. Recommissioning then follows the same sequence as for a new set. Insulation resistance of the alternator and cables is measured before first energisation, because the alternator has been through transport.

Phase sequence is confirmed on both sides of the transfer switch before the first transfer. The set is run on no load, then under load, preferably by load-bank test at full rating for long enough for coolant temperature to settle, with the room doors and louvres in their service position, because that is the only way to prove the new ventilation. Finally the automatic sequence is proven: mains failure, start, transfer, retransfer, cool-down and return to standby. The handover record lists what was done, every test result, and anything left unresolved.

Agreeing the scope

Relocation involves a crane and transport contractor, an electrical contractor, civil work for the plinth and the generator service team, and problems arise when nobody holds the whole picture. The scope should state who isolates and disconnects, who lifts and carries the transit risk, who designs and installs cabling and earthing, who commissions, and who signs off. Where the set is also due for an overhaul, doing it before the move avoids transporting a machine twice; see generator refurbishment.

The relocation sequence and the proof at each step

StepWhat must be proved before moving on
RecordNameplates, connections, settings and a run with readings documented at the old site
Isolate and disconnectBoth sources isolated, cables identified, nothing left live or unlabelled
Lift and transportWeight known, approved lifting points used, set secured and protected from rain
Receive and inspectNo transit damage, insulation of the alternator still acceptable
Re-engineerCable, earthing, ventilation, exhaust, fuel and protection checked against the new site
ReconnectTerminations tested, earthing measured, fuel lines pressure-tested
RecommissionRun on load, protection proved, transfer sequence proved, handover record issued

A set that has arrived at the new site has been transported. It has been relocated only when the last row is complete.

What usually changes between the old site and the new

ItemWhy the old answer may not hold
Cable length and sizeA longer route raises voltage drop, most of all during motor starts
Fault level and protectionDifferent cable lengths and a different main board change the fault current that settings rely on
EarthingSoil, moisture and electrode arrangement differ; the old earth test result proves nothing at the new site
VentilationA different room or position changes the air path and the risk of hot air returning to the radiator
ExhaustNew length, bends and height change back pressure, and the outlet must clear people and windows
FuelTank position, suction height and pipe routing change; the fuel system is recommissioned, not just reconnected
DutyNew loads, starting methods and running hours may change what the set must do

Proving the starting system after transport

Transport loosens terminals, disturbs batteries and strains wiring. Before relying on the set, the starting system is proved by measurement rather than by a single successful start: battery condition on a load test, cranking voltage at the starter, voltage drop on both the positive and the negative cranking circuits, cranking speed, and the charger’s output once the set is back on standby. A set that starts on the third attempt after a move is telling you something about its connections.

The relocation handover record

The record that closes a relocation lists the readings taken at the old site and the new one side by side: insulation resistance of the alternator, earth resistance, voltage and frequency on load, coolant temperature with the room or canopy in its service condition, and the transfer sequence timings. It notes every item that changed, such as a new cable size, new earth electrodes or new protection settings, and anything left unresolved with an owner and a date. Comparing the two sets of readings is the quickest way to show that the set works at least as well in its new home as it did in the old one.

Common mistakes

What to send us

Send the generator nameplate, photographs of the existing installation including the panel, cable route, exhaust and fuel tank, the single-line diagram if available, the address and photographs of the receiving site with its plant room or outdoor position, and the connected load at the new site. Tell us the access for a crane and vehicle at both ends. Use the application engineering enquiry form so the new installation can be assessed before the move is planned.

Questions engineers ask

What has to be re-checked when a generator is moved?

The cable size for the new route and its voltage drop, the fault level and protection settings, the earthing at the new site, the ventilation and the risk of hot air returning to the radiator, the exhaust length and outlet, the fuel suction and pipework, and the duty the set will now do. The old installation proves nothing about the new one until each is checked.

How is the starting system checked after moving a generator?

By measurement rather than a single successful start: a battery load test, cranking voltage at the starter, voltage drop on both the positive and the negative cranking circuits, cranking speed and the output of the charger once the set is back on standby. Transport loosens terminals and strains wiring, so a set that needs several attempts to start after a move has a fault to find.

Can the existing cables and panel be reused at the new site?

The panel usually can, after its ratings and settings are checked against the new fault level and load. The cables can be reused only if the new route is no longer than the old one and the installation method and ambient are equivalent; otherwise they are resized. Treat the cable as a new design item and reuse it only when the calculation says it is adequate.

Does a relocated generator need new statutory approvals?

An installation at a new address generally needs the electrical inspectorate, pollution control and local approvals that apply to any new generator installation in that state. Confirm the requirements early, because they can affect where the set may be placed and how high the exhaust must be.

How long does a relocation take?

The physical move of a canopied set can be done in a day or two, but the civil, cabling, earthing and exhaust work at the new site typically takes one to three weeks, and recommissioning with a loaded test a further day. Plan the new installation before the old one is disconnected so the set is not sitting in a yard waiting for a plinth.

Should the generator be serviced before or after the move?

Before, if it is due. Running the set under load before disconnection establishes its condition and gives a baseline for recommissioning, and any overhaul is easier in a workshop than at a new site under time pressure. After arrival, change the fuel and air filters anyway, because transport disturbs sediment in the tank and dust in the intake.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.